Supreme Court clarifies calculation of Scheduled Commissioning Date in Solar Power Agreements: Bangalore Electricity Supply Company Limited vs. E.S. Solar Power Pvt. Ltd. (2021) INSC 284 (3 May 2021)

Supreme Court Clarifies Scheduled Commissioning Date in Solar Power Agreements LEGAL ISSUE: How to calculate the Scheduled Commissioning Date (SCOD) in a Power Purchase Agreement (PPA) for a solar power project, specifically whether the date of approval of the PPA should be included or excluded in the calculation. CASE TYPE: This case falls under the […]

Supreme Court clarifies calculation of Scheduled Commissioning Date in Solar Power Agreements: Bangalore Electricity Supply Company Limited vs. E.S. Solar Power Pvt. Ltd. (2021) INSC 284 (3 May 2021) Read Post »