Date of the Judgment: October 10, 2023

Citation: 2023 INSC 899

Judges: Aniruddha Bose, J., Vikram Nath, J.

Can a court order payment in a currency different from what was agreed upon in a contract? The Supreme Court of India recently addressed this question in a dispute between National Projects Construction Corporation Limited (NPCCL) and Royal Construction Company Private Limited (RCCPL). The core issue revolved around the currency in which payments should be made following an arbitration award, specifically whether the awarded amount in Iraqi Dinars should be converted to Indian Rupees, and if so, at what date.

The Supreme Court held that, based on the original agreement and the arbitration award, the payment was to be made in US Dollars, not Indian Rupees, after converting the Iraqi Dinars. The court clarified that it could not alter the terms of the contract or the award to mandate payment in a currency not originally agreed upon.

Case Background

The dispute arose from a contract between NPCCL and RCCPL for earthwork in Iraq. The contract specified payments in Iraqi Dinars (ID) and US Dollars (USD). A dispute led to arbitration, with the arbitrator awarding RCCPL a sum in Iraqi Dinars, along with interest, and a separate sum in Indian Rupees (INR) related to a bank guarantee. The award stipulated that the Iraqi Dinar amount should be converted to US Dollars as per the original agreement.

Following the arbitration award, multiple rounds of litigation ensued. The Delhi High Court initially modified the interest rate and the date of currency conversion. However, the Supreme Court, in a previous judgment dated 24.02.2015, set aside the High Court’s orders, affirming that the arbitrator’s directions and the original agreement would govern the matter.

Timeline

Date Event
29th June 1982 Agreement executed between NPCCL and RCCPL for earthwork in Iraq.
26th September 1988 Arbitration clause invoked by the parties.
10th August 2002 Arbitrator gave an award in favor of RCCPL.
26th May 2008 Objections filed by NPCCL under Section 34 of the Arbitration and Conciliation Act, 1996 were dismissed.
19th May 2014 Delhi High Court disposed of appeal under Section 37 of the Arbitration and Conciliation Act, 1996, reducing interest rate and fixing the date of conversion to 10.08.2002.
19th September 2014 Review filed by the appellant was dismissed by the Division Bench.
24th February 2015 Supreme Court set aside the High Court’s orders, affirming the arbitrator’s directions and the original agreement.
26th May 2017 Single Judge directed payment in Indian Rupees, with conversion date as 26.09.1982.
17th December 2019 Division Bench allowed the appeal, set aside the Single Judge’s order, and referred the question of law to the Supreme Court.
10th October 2023 Supreme Court delivered the final judgment.

Course of Proceedings

Following the arbitration award, NPCCL filed objections under Section 34 of the Arbitration and Conciliation Act, 1996, which were dismissed. An appeal under Section 37 of the same Act was partly allowed by the Delhi High Court, which reduced the interest rate and fixed the date for converting US Dollars to Indian Rupees as the date of the award (10.08.2002). The Supreme Court, in a previous judgment, reversed this decision, stating that the arbitrator’s directions and the original agreement should prevail. Subsequently, a Single Judge of the Delhi High Court directed payment in Indian Rupees, using the date of the original agreement for conversion. This was appealed, leading to the Division Bench referring the question of law to the Supreme Court.

See also  Supreme Court clarifies the scope of blacklisting in tender processes: Caretel Infotech Ltd. vs. Hindustan Petroleum Corporation Ltd. (2019)

Legal Framework

The case primarily revolves around the interpretation of the contract between the parties and the arbitration award. The relevant clauses of the agreement are:

  • Clause 31: Specifies that all amounts are in Iraqi Dinars.
  • Clause 32.6: States that payments against monthly account bills shall be made 35% in Iraqi Dinars and 65% in US Dollars.
  • Clause 32.8: Defines the exchange rate for converting Iraqi Dinars to US Dollars as 1 ID = 3.37778 USD.

The arbitration award directed that the amount payable in Iraqi Dinars be converted to US Dollars as per the original agreement. The Supreme Court’s earlier judgment had also emphasized that the arbitrator’s directions and the original agreement would govern the matter.

Arguments

The core argument revolved around the date for converting the awarded amount from US Dollars to Indian Rupees. The respondent, RCCPL, sought payment in Indian Rupees, while the appellant, NPCCL, contended that the contract and the award did not provide for such conversion and payment should be made in US Dollars.

  • RCCPL’s Argument: RCCPL argued that the awarded amount should be converted to Indian Rupees for payment, and the date of the original agreement should be used for conversion.
  • NPCCL’s Argument: NPCCL contended that the agreement and the award did not stipulate payment in Indian Rupees. The conversion was only from Iraqi Dinars to US Dollars as per the contract.
Main Submission Sub-Submissions
RCCPL’s Submission: Payment in Indian Rupees
  • Awarded amount should be converted to Indian Rupees for payment.
  • Date of original agreement (29.06.1982) should be used for conversion.
NPCCL’s Submission: Payment in US Dollars
  • Agreement and award do not stipulate payment in Indian Rupees.
  • Conversion is only from Iraqi Dinars to US Dollars as per contract.

Issues Framed by the Supreme Court

The substantial question of law framed by the High Court and considered by the Supreme Court was:

  1. “In terms of the agreement dated 29th June 1982 between the parties and in light of the judgment dated 24th February 2015 of the Supreme Court of India in Civil Appeal Nos. 2543 -44/2015, what should be the relevant date for conversion of the awarded sum from USD to Indian rupees?”

Treatment of the Issue by the Court

Issue Court’s Decision
What is the relevant date for conversion of the awarded sum from USD to Indian Rupees? The Court held that there was no provision in the agreement or the award for conversion of the awarded sum into Indian Rupees. The payment was to be made in US Dollars after converting the Iraqi Dinars as per the agreement. Therefore, the question of determining a date for conversion to Indian Rupees did not arise.

Authorities

The Court relied on the following authorities:

  • Previous judgment of the Supreme Court dated 24.02.2015 in Civil Appeal Nos. 2543-44/2015, which clarified that the arbitrator’s directions and the original agreement would govern the matter.
  • Clauses 31, 32.6 and 32.8 of the agreement between the parties, which specify the payment terms and currency conversion.
Authority Court How the Authority was Used
Judgment dated 24.02.2015 in Civil Appeal Nos. 2543-44/2015 Supreme Court of India Followed: The Court reiterated that the arbitrator’s directions and the original agreement would govern the matter.
Clause 31 of the agreement Considered: The clause specifies that all amounts are in Iraqi Dinars.
Clause 32.6 of the agreement Considered: The clause states that payments shall be made 35% in Iraqi Dinars and 65% in US Dollars.
Clause 32.8 of the agreement Considered: The clause defines the exchange rate for converting Iraqi Dinars to US Dollars.
See also  Supreme Court Denies Freehold Conversion for Leased Land: Bhasin Infotech vs. State of Uttar Pradesh (2023)

Judgment

Submission Court’s Treatment
RCCPL’s submission for payment in Indian Rupees with conversion date as 29.06.1982 Rejected: The Court found no basis in the agreement or the award for payment in Indian Rupees. The conversion was only permissible from Iraqi Dinars to US Dollars.
NPCCL’s submission for payment in US Dollars as per contract Accepted: The Court agreed that the payment should be made in US Dollars, as per the terms of the contract and the arbitration award.
Authority Court’s View
Previous Supreme Court Judgment dated 24.02.2015 The Court reiterated that the arbitrator’s directions and the original agreement would govern the matter.
Clauses 31, 32.6 and 32.8 of the Agreement The Court relied on these clauses to determine that payment was to be made in US Dollars, not Indian Rupees.

What weighed in the mind of the Court?

The Supreme Court’s decision was primarily driven by the principle of contractual sanctity and the need to uphold the terms of the arbitration award. The Court emphasized that it could not rewrite the contract or the award to introduce a payment term (in Indian Rupees) that was not originally agreed upon by the parties. The Court’s reasoning focused on the following points:

  • The agreement stipulated payments in Iraqi Dinars and US Dollars, with a defined exchange rate between them.
  • The arbitration award directed the conversion of Iraqi Dinars to US Dollars as per the original agreement.
  • There was no provision in the agreement or the award for converting US Dollars to Indian Rupees.
  • The Court’s role was to interpret and enforce the contract and the award, not to modify them.
Sentiment Percentage
Contractual Sanctity 40%
Upholding Arbitration Award 30%
Interpretation of Contract 20%
No Modification of Terms 10%
Ratio Percentage
Fact 30%
Law 70%

Logical Reasoning

Start: Agreement between NPCCL & RCCPL

Contract stipulates payment in Iraqi Dinars and US Dollars

Arbitration Award: Iraqi Dinars to be converted to US Dollars as per agreement

No provision for conversion to Indian Rupees

Court cannot alter contract terms

Payment to be made in US Dollars

The Court rejected the argument for payment in Indian Rupees because neither the original contract nor the arbitration award provided for it. The Court emphasized that it could not introduce new terms or modify existing terms that the parties had not agreed upon. The Court also noted that its role was to interpret and enforce the contract and the award, not to rewrite them.

The Court stated:

“We do not find any mention of payment being made in the Indian Currency i.e. INR from the agreement. Once there is no contract between the parties of making payment in Indian Currency INR, then, there would be no question of determining or finding out any date of conversion.”

“The award does not permit or grant the liberty to the appellant to make the amount payable in Iraqi Dinars to be converted into Indian Currency (INR).”

“In our considered view, perusal of the above material does not permit payment of the awarded amount in Indian currency except the amount of Rs. 20 lacs with admissible interest against the encashment of bank guarantee. As a necessary corollary, there would be no question of the amount awarded in Iraqi Dinars to be converted in Indian currency. The only conversion permissible was in US Dollars.”

There were no dissenting opinions; the judgment was unanimous.

See also  Supreme Court Upholds Bank Guarantee Invocation in Favor of Heavy Engineering Corporation Ltd. in Civil Dispute (18 December 2019)

The decision reinforces the principle that courts should respect the contractual agreements between parties and the decisions of arbitrators, and should not impose terms that were not part of the original agreement or award.

Key Takeaways

  • Courts will generally uphold the terms of contracts and arbitration awards.
  • Payment currencies specified in contracts must be adhered to, unless explicitly altered by mutual agreement or a valid arbitration award.
  • Courts will not typically order payment in a currency not stipulated in the original contract or the arbitration award.
  • The principle of contractual sanctity is paramount in commercial disputes.

Directions

The Supreme Court directed that the payment has to be made in the foreign currency (US Dollars) along with computed interest. The Court also clarified that the parties were free to agree to accept payment in Indian currency, either at the current rate or at an agreed rate, but the Court could not impose such a condition.

Development of Law

The ratio decidendi of the case is that the courts cannot alter the terms of the contract or the arbitration award to mandate payment in a currency not originally agreed upon. There is no change in the previous position of law, as the court reiterated the principle of contractual sanctity and the need to uphold the terms of the arbitration award.

Conclusion

The Supreme Court’s judgment clarifies that in cases involving international contracts and arbitration awards, the currency of payment is determined by the terms of the original contract and the award. The Court cannot mandate payment in a currency not specified in these documents. This decision reinforces the importance of clear contractual terms and the respect for arbitration decisions. The court has clarified that the payment has to be made in the foreign currency (US Dollars) along with computed interest.

Category

  • Contract Law
    • Currency of Payment
    • Interpretation of Contracts
  • Arbitration Law
    • Enforcement of Arbitral Awards
    • Arbitration and Conciliation Act, 1996
  • Civil Procedure
    • Execution Proceedings
  • Contract Law
    • Agreement dated 29th June 1982

FAQ

Q: What was the main issue in the case?

A: The main issue was whether the awarded amount in Iraqi Dinars should be converted to Indian Rupees for payment, and if so, what date should be used for conversion.

Q: What did the Supreme Court decide?

A: The Supreme Court decided that the payment should be made in US Dollars, as per the original contract and the arbitration award. There was no provision for payment in Indian Rupees.

Q: Can a court order payment in a currency different from what was agreed upon in a contract?

A: No, generally a court cannot order payment in a currency different from what was agreed upon in the contract, unless there is a valid reason for such a change.

Q: What is the significance of this judgment?

A: This judgment reinforces the principle that courts should respect the contractual agreements between parties and the decisions of arbitrators, and should not impose terms that were not part of the original agreement or award.

Q: What should businesses learn from this case?

A: Businesses should ensure that their contracts clearly specify the currency of payment and understand that courts will generally uphold those terms.