Date of the Judgment: January 18, 2022
The Supreme Court of India, in a recent judgment, addressed a critical question regarding the eligibility of resolution applicants under the Insolvency and Bankruptcy Code, 2016 (IBC). Specifically, the court examined whether a person who has given a personal guarantee for a corporate debtor is disqualified from submitting a resolution plan if that guarantee has been invoked by a creditor. This case clarifies the scope and application of Section 29A(h) of the IBC, impacting future insolvency proceedings. The judgment was delivered by a two-judge bench comprising Justice Sanjay Kishan Kaul and Justice M.M. Sundresh, with Justice Sundresh authoring the opinion.

Case Background

M/s. MBL Infrastructures Limited (Respondent No. 1), established by Mr. Anjanee Kumar Lakhotiya (Respondent No. 3) in the early 1990s, obtained loans and credit facilities from a consortium of banks. When MBL Infrastructures failed to meet its repayment obligations, some banks invoked the personal guarantees provided by Mr. Lakhotiya. RBL Bank initiated proceedings under Section 13(2) of the Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 (SARFAESI Act) after invoking Mr. Lakhotiya’s personal guarantee. Similar actions were taken by Allahabad Bank and State Bank of Bikaner and Jaipur in February and March 2013.

Subsequently, RBL Bank filed an application under Section 7 of the IBC before the National Company Law Tribunal (NCLT), Kolkata, to initiate the Corporate Insolvency Resolution Process (CIRP) against MBL Infrastructures. The NCLT admitted the application on March 30, 2017, appointing an Interim Resolution Professional and imposing a moratorium under Section 14 of the IBC. The CIRP period was later extended by 90 days.

Two resolution plans were received, one of which was submitted by Mr. Lakhotiya on June 29, 2017, before Section 29A of the IBC was introduced.

Timeline

Date Event
Early 1990s M/s. MBL Infrastructures Limited (Respondent No.1) was set up by Mr. Anjanee Kumar Lakhotiya (Respondent No. 3).
February-March 2013 RBL Bank, Allahabad Bank, and State Bank of Bikaner and Jaipur invoked personal guarantees of Respondent No.3 under Section 13(2) of SARFAESI Act.
March 30, 2017 NCLT Kolkata admitted application under Section 7 of IBC filed by RBL Bank initiating CIRP against Respondent No.1.
June 29, 2017 Respondent No.3 submitted a resolution plan.
October 16, 2017 – November 17, 2017 Series of meetings took place with the Committee of Creditors (CoC) on the resolution plan submitted by Respondent No.3.
November 18, 2017 CoC sought an appropriate resolution plan from Respondent No.3.
November 22, 2017 Respondent No.3 submitted a modified resolution plan.
November 23, 2017 Section 29A was introduced to the IBC.
December 1, 2017 CoC met to discuss the impact of the amendment on the eligibility of Respondent No.3.
December 18, 2017 NCLT held Respondent No.3 eligible to submit a resolution plan.
December 21, 2017 NCLAT passed an interim order that the Adjudicating Authority will not accept or reject the resolution plan without prior approval of the Appellate Tribunal.
December 21-22, 2017 Resolution plan submitted by Respondent No.3 was put to vote by CoC, receiving 68.50% vote share.
January 11, 2018 NCLAT allowed the adjudicating authority to proceed further but not to accept the resolution plan, without its prior approval.
January 12, 2018 Respondent No.3 filed an application seeking direction to dissenting creditors.
January 18, 2018 Amendment to Section 29A(h) came into effect.
January 31, 2018 Bank of Maharashtra set conditions for approval of resolution plan.
February 12, 2018 Resolution professional filed a report stating the resolution plan gathered 78.50% vote share.
February 27, 2018 Appeals against the eligibility of Respondent No.3 were withdrawn.
March 23, 2018 NCLAT permitted the withdrawal of appeals and vacated the interim order.
April 18, 2018 NCLT approved the resolution plan submitted by Respondent No.3.
June 6, 2018 Further amendment to Section 29A(h) came into effect.
January 18, 2022 Supreme Court disposed of the appeal.

Course of Proceedings

The NCLT, on December 18, 2017, declared Mr. Lakhotiya eligible to submit a resolution plan, despite his personal guarantees being invoked. The NCLT reasoned that the guarantee was not yet crystallized as a debt, and therefore, did not disqualify him under Section 29A(h) of the IBC. This order was challenged by Punjab National Bank before the National Company Law Appellate Tribunal (NCLAT). The NCLAT passed an interim order on December 21, 2017, preventing the NCLT from accepting the resolution plan without its prior approval.

RBL Bank also filed an appeal against the NCLT order. On January 11, 2018, the NCLAT allowed the NCLT to proceed but not to accept the resolution plan without its approval. Mr. Lakhotiya then filed an application seeking to persuade dissenting creditors to support the plan. The resolution plan ultimately garnered 78.50% vote share from the Committee of Creditors (CoC).

On March 23, 2018, the NCLAT allowed the appellants to withdraw their appeals, vacating the interim order. The NCLT approved the resolution plan on April 18, 2018, stating that the issue of eligibility under Section 29A(h) had already been decided and the plan had crossed the required threshold. Bank of Baroda, the appellant before the Supreme Court, challenged this order before the NCLAT, which was dismissed. The NCLAT upheld the NCLT’s decision, stating that the resolution plan had been approved by a majority of the CoC and was backed by a techno-economic report. This decision was then appealed to the Supreme Court.

Legal Framework

The Supreme Court focused on Section 29A of the Insolvency and Bankruptcy Code, 2016, specifically clauses (c) and (h). Section 29A outlines the criteria for persons who are not eligible to submit a resolution plan. The relevant portions of the provision are:

“Section 29 A – Persons not eligible to be resolution applicant – A person shall not be eligible to submit a resolution plan, if such person or any other person acting jointly with such person or any other person who is a promoter or in the management or control of such person, –
xxx xxx xxx
(c) has an account, or an account of a corporate debtor under the management or control of such person or of whom such person is a promoter, classified as non-performing asset in accordance with the guidelines of the Reserve Bank of India issued under the Banking Regulation Act, 1949 and at least a period of one year has lapsed from the date of such classification till the date of commencement of the corporate insolvency resolution process of the corporate debtor:
Provided that the person shall be eligible to submit a resolution plan if such person makes payment of all overdue amounts with interest thereon and charges relating to non-performing asset accounts before submission of resolution plan;
xxx xxx xxx
(h) has executed an enforceable guarantee in favour of a creditor, in respect of a corporate debtor under insolvency resolution process or liquidation under this code.”

See also  Supreme Court Upholds Mandatory E-filing at DRTs and DRATs, Addresses Digital Divide Concerns (29 March 2023)

The court also considered the amendment to Section 29A(h) which came into effect on January 18, 2018, which stated:

“Section 29 A – Persons not eligible to be resolution applicant – A person shall not be eligible to submit a resolution plan, if such person or any other person acting jointly or in concert with such person –
xxx xxx xxx
(h) has executed an enforceable guarantee in favour of a creditor, in respect of a corporate debtor against which an application for insolvency resolution made by such creditor has been admitted under this code.”

Further, the court also took into account the amendment to Section 29A(h) which came into effect from June 6, 2018:

“Section 29 A- Persons not eligible to be resolution applicant – A person shall not be eligible to submit a resolution plan, if such person or any other person acting jointly or in concert with such person –
xxx xxx xxx
(h) has executed a guarantee in favour of a creditor, in respect of a corporate debtor against which an application for insolvency resolution made by such creditor has been admitted under this code and such guarantee has been invoked by the credit and remains unpaid if full or part.”

The court also discussed Section 30(4) of the Code, which was amended to reduce the percentage required for approval of a resolution plan by the CoC from 75% to 66%.

Arguments

Appellant’s Submissions:

  • The appellant argued that Section 29A should be interpreted holistically to disqualify guarantors who have not fulfilled their liabilities.
  • Respondent No. 3, being a promoter, was ineligible under Section 29A(h) as his personal guarantees were invoked before the CIRP commenced.
  • The appellant contended that Respondent No. 3 suppressed the fact of guarantee invocation, and the adjudicating authority failed to consider this.
  • The law at the time of the application should determine eligibility, and the ineligibility under Section 29A(h) cannot be waived.
  • The approval of the resolution plan was made after the 270-day CIRP period, violating Section 12 of the IBC.
  • The revised plan was not approved by the adjudicating authority, and the conditional assent by Respondent No. 11 was erroneously accepted.

Respondent’s Submissions:

  • The respondents argued that the CoC’s decision, based on commercial wisdom and expert reports, should not be interfered with.
  • The revised plan was an improvement, and there was no basis for grievance.
  • Section 29A(h) should be interpreted literally, barring only guarantors whose guarantees were invoked by the creditor who initiated the CIRP.
  • RBL Bank did not invoke the guarantee at the time of the Section 7 application.
  • The invocation of guarantees by Allahabad Bank and State Bank of Bikaner and Jaipur was illegal.
  • The object of the IBC is revival, and any interference would be detrimental.
  • The issue of extension and exclusion of time had been rightly construed by the lower forums.

The arguments by the parties can be summarised as follows:

Main Submission Appellant’s Sub-Submissions Respondent’s Sub-Submissions
Eligibility of Respondent No. 3 under Section 29A(h)
  • Respondent No. 3 was ineligible due to invoked personal guarantees.
  • Suppression of facts regarding guarantee invocation.
  • Ineligibility cannot be waived.
  • CoC’s decision based on commercial wisdom should not be interfered with.
  • Literal interpretation of Section 29A(h) should be adopted.
  • RBL Bank did not invoke guarantee at the time of application under Section 7.
  • Invocation by other banks was illegal.
Validity of the Resolution Plan
  • Approval was after the mandatory CIRP period, violating Section 12.
  • Revised plan was not approved by the adjudicating authority.
  • Revised plan was an improvement.
  • Object of IBC is revival, and interference would be detrimental.
Procedural Issues
  • Appellant was not a party earlier, so the issue can be raised again.
  • Appellant is estopped from questioning eligibility.
  • Issue of extension and exclusion of time was rightly construed.

Issues Framed by the Supreme Court

The Supreme Court addressed the following key issues:

  1. The interpretation of Section 29A(h) of the Insolvency and Bankruptcy Code, 2016, particularly regarding the eligibility of a resolution applicant who has provided a personal guarantee.
  2. Whether the ineligibility under Section 29A(h) is applicable only to the creditor who initiated the CIRP or to all creditors.
  3. The relevant date for determining the eligibility of a resolution applicant under Section 29A(h).
  4. Whether the appellant could raise the issue of eligibility again, despite the earlier appeals being withdrawn.

Treatment of the Issue by the Court

Issue Court’s Decision Brief Reasons
Interpretation of Section 29A(h) The word “such creditor” includes similarly placed creditors. The ineligibility applies to the resolution process, not just one creditor.
Applicability of Ineligibility Ineligibility applies to all creditors, not just the creditor who initiated CIRP. The process is one of rem, and all creditors of the same class have equal rights.
Relevant Date for Eligibility The relevant date is the time of submission of the resolution plan and continues till approval. If ineligibility arises after submission but before approval, the amended provision would apply.
Raising the Issue Again The appellant could raise the issue again. The appellant was not a party to the earlier decision, and the appellate authority did not decide on merit.
See also  Supreme Court Upholds High Court Decision in Property Dispute: Vimla Devi vs. Chhabiram (2021)

Authorities

The Supreme Court considered the following authorities:

Authority Court Legal Point How Considered
Seaford Court Estates Ltd. v. Asher, (1949) 2 KB 481 Court of Appeal Role of the court in statutory interpretation Cited to emphasize the court’s role in finding the intention of Parliament and supplementing the written word.
Reserve Bank of India v. Peerless General Finance and Investment Company Limited, (1987) 1 SCC 424 Supreme Court of India Interpretation based on text and context Cited to highlight that interpretation must depend on the text and the context, and that the best interpretation is one that matches the textual with the contextual.
Union of India v. Elphinstone Spg. and Wvg. Co. Ltd., (2001) 4 SCC 139 Supreme Court of India Balancing the letter and spirit of the statute Cited to emphasize the need for judges to strike a balance between the letter and spirit of the statute.
Arcellor Mittal India Pvt. Ltd. v. Satish Kumar Gupta, (2019) 2 SCC 1 Supreme Court of India Interpretation of the IBC Cited to show the court’s approach in interpreting the IBC, focusing on the objective of the Code.
Phoenix Arc (P) Ltd. v. Spade Financial Services Ltd., (2021) 3 SCC 475 Supreme Court of India Purposive interpretation Cited to support the principle of purposive and creative interpretation while interpreting statutes.
Arun Kumar Jagatramka v. Jindal Steel & Power Limited, (2021) 7 SCC 474 Supreme Court of India Interpretation of the IBC Cited to show the court’s approach in interpreting the IBC, focusing on the objective of the Code.
Swiss Ribbons (P) Ltd. v. Union of India, (2019) 4 SCC 17 Supreme Court of India Objectives of the IBC Cited to explain the primary focus of the IBC is to ensure revival and continuation of the corporate debtor.
Chitra Sharma & Ors. v. Union of India, (2018) 18 SCC 575 Supreme Court of India Purpose of Section 29A Cited to highlight that Section 29A was introduced to ensure that persons responsible for the insolvency of the corporate debtor do not participate in the resolution process.
K.N. Rajkumar v. V .N. Nagarajan 2021 SCC OnLine 732 Supreme Court of India Principles of statutory interpretation Cited by the respondent to support their arguments on statutory interpretation.
Committee of Creditors, Essar Steel India Ltd. v. Satish Kumar Gupta (2020) 8 SCC 531 Supreme Court of India Commercial wisdom of CoC Cited by the respondent to argue that the commercial wisdom of the CoC should not be interfered with.
Apollo Joti LLC & Ors. v. Jyoti Structures Ltd. (Company Appeal (AT) (Insolvency) No. 548 of 2018 NCLAT Interpretation of IBC Cited by the respondent to support their arguments on the interpretation of the IBC.
DBS Bank Ltd. vs. Sharad Sanghi (Civil Appeal No. 3434-3436 of 2019) Supreme Court of India Interpretation of IBC Cited by the respondent to support their arguments on the interpretation of the IBC.
Ebix Singapore Pvt. Ltd. vs. COC of Educomp Solutions Ltd. 2021 SCC OnLine SC 707 Supreme Court of India Binding nature of a resolution plan Cited to show that a resolution plan, once approved, becomes binding on all stakeholders.
National Spot Exchange v. Anil Kohli 2021 SCC OnLine SC 716 Supreme Court of India Interpretation of IBC Cited by the respondent to support their arguments on the interpretation of the IBC.
K. Shashidhar vs. Union of India (Order dated 05.02.2019 in Civil Appeal 10673 of 2018) Supreme Court of India Interpretation of IBC Cited by the appellant to support their arguments on the interpretation of the IBC.

Judgment

The Supreme Court held that the resolution plan submitted by Respondent No. 3 was not maintainable due to his ineligibility under Section 29A(h) of the IBC. The court interpreted “such creditor” in Section 29A(h) to include all similarly placed creditors, not just the creditor who initiated the CIRP. The court found that Respondent No. 3’s personal guarantees were invoked before the resolution plan was submitted, making him ineligible.

The court also held that the relevant date for determining eligibility is the date of submission of the resolution plan and continues till approval. If ineligibility arises after submission but before approval, the amended provision would apply. The court also stated that the appellant was not barred from raising the issue of eligibility again, as it was not a party to the earlier proceedings and the appellate tribunal did not decide the matter on merit.

However, despite the ineligibility, the court did not disturb the resolution plan due to the peculiar facts of the case, including the fact that the resolution plan had been approved by a majority of the CoC, the company was an ongoing concern, and the plan had been implemented since April 18, 2018. The court also noted that the interests of dissenting creditors were protected by the resolution plan.

The court’s treatment of submissions and authorities is summarised below:

Submission Court’s Treatment
Respondent No. 3’s eligibility under Section 29A(h) Held that Respondent No. 3 was ineligible due to invoked personal guarantees.
Literal interpretation of Section 29A(h) Rejected the literal interpretation, stating that “such creditor” includes all similarly placed creditors.
Validity of the resolution plan Held that the plan was not maintainable due to the ineligibility of Respondent No.3, but did not disturb it due to the peculiar facts of the case.
Appellant’s right to raise the issue again Upheld the appellant’s right to raise the issue as it was not a party to the previous proceedings.
Limitation Agreed with the lower courts that the delay was rightly condoned and excluded under Section 12(3) of the IBC.

The court’s view of the authorities is summarised as follows:

Authority Court’s View
Seaford Court Estates Ltd. v. Asher, (1949) 2 KB 481 *Cited to emphasize the court’s role in finding the intention of Parliament and supplementing the written word.* The court used this to justify its purposive interpretation of Section 29A(h).
Reserve Bank of India v. Peerless General Finance and Investment Company Limited, (1987) 1 SCC 424 *Cited to highlight that interpretation must depend on the text and the context.* The court used this to support its approach of considering the text and context of the IBC.
Union of India v. Elphinstone Spg. and Wvg. Co. Ltd., (2001) 4 SCC 139 *Cited to emphasize the need for judges to strike a balance between the letter and spirit of the statute.* The court used this to justify its approach of balancing the literal text with the purpose of the IBC.
Arcellor Mittal India Pvt. Ltd. v. Satish Kumar Gupta, (2019) 2 SCC 1 *Cited to show the court’s approach in interpreting the IBC, focusing on the objective of the Code.* The court used this to support its purposive interpretation of Section 29A(h).
Phoenix Arc (P) Ltd. v. Spade Financial Services Ltd., (2021) 3 SCC 475 *Cited to support the principle of purposive and creative interpretation while interpreting statutes.* The court used this to justify its approach of interpreting Section 29A(h) in light of the objectives of the IBC.
Arun Kumar Jagatramka v. Jindal Steel & Power Limited, (2021) 7 SCC 474 *Cited to show the court’s approach in interpreting the IBC, focusing on the objective of the Code.* The court used this to support its purposive interpretation of Section 29A(h).
Swiss Ribbons (P) Ltd. v. Union of India, (2019) 4 SCC 17 *Cited to explain the primary focus of the IBC is to ensure revival and continuation of the corporate debtor.* The court used this to justify its decision not to disturb the resolution plan despite the ineligibility of the applicant.
Chitra Sharma & Ors. v. Union of India, (2018) 18 SCC 575 *Cited to highlight that Section 29A was introduced to ensure that persons responsible for the insolvency of the corporate debtor do not participate in the resolution process.* The court used this to support its interpretation of Section 29A(h).
K.N. Rajkumar v. V .N. Nagarajan 2021 SCC OnLine 732 *Cited by the respondent to support their arguments on statutory interpretation.* The court did not find this persuasive in light of its interpretation of Section 29A(h).
Committee of Creditors, Essar Steel India Ltd. v. Satish Kumar Gupta (2020) 8 SCC 531 *Cited by the respondent to argue that the commercial wisdom of the CoC should not be interfered with.* The court acknowledged this principle but found that it did not override the ineligibility under Section 29A(h).
Apollo Joti LLC & Ors. v. Jyoti Structures Ltd. (Company Appeal (AT) (Insolvency) No. 548 of 2018 *Cited by the respondent to support their arguments on the interpretation of the IBC.* The court did not find this persuasive in light of its interpretation of Section 29A(h).
DBS Bank Ltd. vs. Sharad Sanghi (Civil Appeal No. 3434-3436 of 2019) *Cited by the respondent to support their arguments on the interpretation of the IBC.* The court did not find this persuasive in light of its interpretation of Section 29A(h).
Ebix Singapore Pvt. Ltd. vs. COC of Educomp Solutions Ltd. 2021 SCC OnLine SC 707 *Cited to show that a resolution plan, once approved, becomes binding on all stakeholders.* The court used this to support its decision not to disturb the resolution plan despite the ineligibility of the applicant.
National Spot Exchange v. Anil Kohli 2021 SCC OnLine SC 716 *Cited by the respondent to support the arguments on the interpretation of the IBC.* The court did not find this persuasive in light of its interpretation of Section 29A(h).
K. Shashidhar vs. Union of India (Order dated 05.02.2019 in Civil Appeal 10673 of 2018) *Cited by the appellant to support their arguments on the interpretation of the IBC.* The court found this persuasive in its interpretation of Section 29A(h).
See also  Supreme Court settles property rights under a will: Shri Shivaji Education Society vs. Omprakash (2021)

Conclusion

The Supreme Court’s judgment in Bank of Baroda vs. MBL Infrastructures clarifies the interpretation of Section 29A(h) of the IBC. The court held that a person who has given a personal guarantee for a corporate debtor is disqualified from submitting a resolution plan if that guarantee has been invoked by any creditor, not just the creditor who initiated the CIRP. The court also clarified that the relevant date for determining eligibility is the date of submission of the resolution plan and continues till approval.

Despite finding Respondent No. 3 ineligible, the court did not disturb the resolution plan due to the peculiar facts of the case, including the fact that the plan was approved by a majority of the CoC, the company was an ongoing concern, and the plan had been implemented since April 18, 2018. The court balanced the need for strict adherence to the eligibility criteria with the objective of revival under the IBC.

The key takeaways from this judgment are:

  • Section 29A(h) of the IBC should be interpreted broadly to disqualify guarantors whose guarantees have been invoked by any creditor.
  • The relevant date for determining eligibility is the date of submission of the resolution plan and continues till approval.
  • The commercial wisdom of the CoC is important but cannot override the statutory ineligibility criteria.
  • The courts have the power to balance the objectives of the IBC, including revival and strict adherence to eligibility criteria.

This judgment provides important guidance for future insolvency proceedings and highlights the importance of strict adherence to the eligibility criteria under Section 29A of the IBC.

Flowchart of the Process

Loan Default by MBL Infrastructures
Invocation of Personal Guarantees by Banks (including RBL, Allahabad, and State Bank of Bikaner)
RBL Bank Files Application under Section 7 of IBC
NCLT Admits Application and Initiates CIRP
Respondent No. 3 (Mr. Lakhotiya) Submits Resolution Plan
Section 29A of IBC Introduced
NCLT Declares Respondent No. 3 Eligible
NCLAT Issues Interim Order Against Acceptance of Resolution Plan
Resolution Plan Receives 78.50% Vote Share from CoC
Appeals Against Eligibility Withdrawn
NCLT Approves Resolution Plan
Bank of Baroda Appeals to NCLAT
NCLAT Dismisses Appeal
Bank of Baroda Appeals to Supreme Court
Supreme Court Rules on Eligibility under Section 29A(h)