LEGAL ISSUE: Whether acquisition proceedings under the Land Acquisition Act, 1894 lapse if compensation is not paid to a subsequent purchaser, even if possession has been taken.
CASE TYPE: Land Acquisition
Case Name: Delhi Development Authority vs. Dayanand & Ors.
Judgment Date: 09 December 2022

Date of the Judgment: 09 December 2022
Citation: 2022 INSC 1066
Judges: M.R. Shah, J. and C.T. Ravikumar, J.
Can a subsequent purchaser of land challenge acquisition proceedings under the Land Acquisition Act, 1894, claiming that the acquisition has lapsed due to non-payment of compensation? The Supreme Court of India addressed this critical question, clarifying the interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The court held that a subsequent purchaser does not have the locus standi to challenge the acquisition and that the acquisition does not lapse if possession has been taken, even if compensation is not paid to the subsequent purchaser. This judgment was delivered by a bench comprising Justices M.R. Shah and C.T. Ravikumar, with the majority opinion authored by Justice M.R. Shah.

Case Background

The Delhi Development Authority (DDA) initiated acquisition proceedings for certain land under the Land Acquisition Act, 1894. Possession of the land was taken by the DDA on 26 November 2012. Subsequently, the original writ petitioner purchased the land. The petitioner then filed a writ petition before the High Court of Delhi, claiming that the acquisition proceedings had lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, because the compensation had not been paid to them. The High Court allowed the writ petition, declaring that the acquisition had lapsed. The DDA then appealed to the Supreme Court.

Timeline

Date Event
26 November 2012 Possession of the subject land taken by DDA.
Prior to 2016 Original writ petitioner (subsequent purchaser) purchased the land.
2016 Writ petition filed by the subsequent purchaser in High Court of Delhi.
Unknown High Court of Delhi allowed the writ petition.
09 December 2022 Supreme Court of India delivered the judgment in favour of DDA.

Course of Proceedings

The High Court of Delhi allowed the writ petition filed by the subsequent purchaser, holding that the acquisition proceedings had lapsed under Section 24(2) of the Act, 2013, because the compensation had not been paid to the subsequent purchaser. The High Court relied on the decision in Government (NCT of Delhi) Vs. Manav Dharam Trust and Anr., (2017) 6 SCC 751, to overrule the objection regarding the maintainability of the writ petition by a subsequent purchaser. The Delhi Development Authority (DDA) appealed this decision to the Supreme Court.

Legal Framework

The Supreme Court examined the following key legal provisions:

  • Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013: This section deals with the lapse of acquisition proceedings if certain conditions are not met. It states:

    “Notwithstanding anything contained in sub-section (1), in case of land acquisition proceedings initiated under the Land Acquisition Act, 1894 (1 of 1894), where an award under the said Act has been made five years or more prior to the commencement of this Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, shall initiate the proceedings of such land acquisition afresh in accordance with the provisions of this Act.”
  • Section 31(1) of the Land Acquisition Act, 1894: This section deals with the payment of compensation.
  • Section 16 of the Land Acquisition Act, 1894: This section deals with the possession of land after an award has been passed.

The Court emphasized that the interpretation of Section 24(2) of the Act, 2013, had been clarified by the Constitution Bench in Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129.

Arguments

Arguments by the Appellant (Delhi Development Authority):

  • The appellant argued that the High Court had erred in allowing the writ petition filed by the subsequent purchaser.
  • The appellant contended that the subsequent purchaser had no locus standi to challenge the acquisition proceedings.
  • The appellant relied on the decision in Delhi Development Authority Vs. Godfrey Philips (I) Ltd. & Ors., to argue that a subsequent purchaser cannot claim lapsing of proceedings under the Act, 2013.
  • The appellant further argued that the acquisition proceedings could not lapse under Section 24(2) of the Act, 2013, because possession of the land had already been taken.
  • The appellant relied on the decision in Indore Development Authority Vs. Manoharlal and Ors., to state that both conditions, of not taking possession and not paying compensation, must be satisfied for the acquisition to lapse.
See also  Supreme Court Upholds Cancellation of Protected Tenancy for Land Misuse: Gaddam Ramulu vs. Joint Collector (2019)

Arguments by the Respondent (Original Writ Petitioner):

  • The respondent argued that the acquisition proceedings had lapsed because the compensation had not been paid to them.
  • The respondent relied on the High Court’s decision, which had held that the acquisition had lapsed under Section 24(2) of the Act, 2013.
Main Submission Sub-Submissions
Appellant (DDA): Subsequent purchaser has no locus standi to challenge the acquisition. ✓ Relied on Delhi Development Authority Vs. Godfrey Philips (I) Ltd. & Ors.
✓ Acquisition cannot lapse if possession is taken, as per Indore Development Authority Vs. Manoharlal and Ors.
✓ Both conditions of non-possession and non-payment must be met for lapse under Section 24(2) of the Act, 2013.
Respondent (Original Writ Petitioner): Acquisition lapsed due to non-payment of compensation. ✓ Relied on the High Court’s decision that acquisition lapsed under Section 24(2).

Issues Framed by the Supreme Court

The Supreme Court did not explicitly frame issues in a separate section. However, the main issues addressed by the Court were:

  1. Whether a subsequent purchaser has the locus standi to challenge the acquisition proceedings under Section 24(2) of the Act, 2013.
  2. Whether the acquisition proceedings lapse under Section 24(2) of the Act, 2013, if possession has been taken, but compensation has not been paid to the subsequent purchaser.

Treatment of the Issue by the Court

The following table demonstrates as to how the Court decided the issues:

Issue Court’s Decision
Whether a subsequent purchaser has the locus standi to challenge the acquisition proceedings under Section 24(2) of the Act, 2013. The Court held that a subsequent purchaser does not have the locus standi to challenge the acquisition proceedings.
Whether the acquisition proceedings lapse under Section 24(2) of the Act, 2013, if possession has been taken, but compensation has not been paid to the subsequent purchaser. The Court held that the acquisition proceedings do not lapse if possession has been taken, even if compensation has not been paid to the subsequent purchaser.

Authorities

The Supreme Court considered the following authorities:

Cases:

  • Government (NCT of Delhi) Vs. Manav Dharam Trust and Anr., (2017) 6 SCC 751 – The High Court relied on this case to hold that a subsequent purchaser can maintain a writ petition. However, this was overruled by the Supreme Court.
  • Delhi Development Authority Vs. Godfrey Philips (I) Ltd. & Ors. – The Supreme Court relied on this case to hold that a subsequent purchaser cannot claim lapsing of proceedings under the Act, 2013.
  • Delhi Administration Thr. Secretary, Land and Building Department & Ors. Vs. Pawan Kumar & Ors. – The Supreme Court followed this case, which followed the Godfrey Philips case.
  • Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129 – The Supreme Court relied on this Constitution Bench decision to interpret Section 24(2) of the Act, 2013, holding that both conditions, of not taking possession and not paying compensation, must be satisfied for the acquisition to lapse.

Legal Provisions:

  • Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013: The Court interpreted this section to mean that the acquisition lapses only if both possession has not been taken and compensation has not been paid.
  • Section 31(1) of the Land Acquisition Act, 1894: This section deals with the payment of compensation.
  • Section 16 of the Land Acquisition Act, 1894: This section deals with the possession of land after an award has been passed.
Authority Court How the Authority was Used
Government (NCT of Delhi) Vs. Manav Dharam Trust and Anr., (2017) 6 SCC 751 Supreme Court of India Overruled – The Supreme Court overruled the High Court’s reliance on this case, stating that a subsequent purchaser cannot maintain a writ petition.
Delhi Development Authority Vs. Godfrey Philips (I) Ltd. & Ors. Supreme Court of India Followed – The Supreme Court followed this case to hold that a subsequent purchaser cannot claim lapsing of proceedings.
Delhi Administration Thr. Secretary, Land and Building Department & Ors. Vs. Pawan Kumar & Ors. Supreme Court of India Followed – The Supreme Court followed this case, which followed the Godfrey Philips case.
Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129 Supreme Court of India Followed – The Supreme Court relied on this Constitution Bench decision to interpret Section 24(2) of the Act, 2013.
Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 Statute Interpreted – The Court interpreted this section to mean that both conditions (non-possession and non-payment) must be satisfied for the acquisition to lapse.
Section 31(1) of the Land Acquisition Act, 1894 Statute Mentioned – This section was mentioned in the context of payment of compensation.
Section 16 of the Land Acquisition Act, 1894 Statute Mentioned – This section was mentioned in the context of taking possession of land.
See also  Supreme Court quashes summoning order for drug manufacturing: JM Laboratories vs. State of Andhra Pradesh (2025)

Judgment

The Supreme Court allowed the appeal, setting aside the High Court’s judgment. The Court held that the subsequent purchaser had no locus standi to file the writ petition and that the acquisition proceedings did not lapse under Section 24(2) of the Act, 2013, because possession of the land had been taken. The Court clarified that for the acquisition to lapse under Section 24(2), both conditions—not taking possession and not paying compensation—must be satisfied. The Court also directed that if the compensation had not been paid to the recorded owner, it should be paid as and when the recorded owner or the person entitled to claim compensation approaches the authorities.

Submission by Parties How it was treated by the Court
Appellant (DDA): Subsequent purchaser has no locus standi to challenge the acquisition. Accepted. The Court held that the subsequent purchaser had no locus standi.
Appellant (DDA): Acquisition cannot lapse if possession is taken. Accepted. The Court held that the acquisition did not lapse because possession had been taken.
Respondent (Original Writ Petitioner): Acquisition lapsed due to non-payment of compensation. Rejected. The Court held that the acquisition did not lapse because possession had been taken, even if compensation was not paid to the subsequent purchaser.

How each authority was viewed by the Court?

  • The Court overruled the High Court’s reliance on Government (NCT of Delhi) Vs. Manav Dharam Trust and Anr., (2017) 6 SCC 751, stating that a subsequent purchaser cannot maintain a writ petition.
  • The Court followed Delhi Development Authority Vs. Godfrey Philips (I) Ltd. & Ors., holding that a subsequent purchaser cannot claim lapsing of proceedings.
  • The Court followed Delhi Administration Thr. Secretary, Land and Building Department & Ors. Vs. Pawan Kumar & Ors., which followed the Godfrey Philips case.
  • The Court followed Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129, to interpret Section 24(2) of the Act, 2013, stating that both conditions (non-possession and non-payment) must be satisfied for the acquisition to lapse.

What weighed in the mind of the Court?

The Supreme Court’s decision was primarily influenced by the interpretation of Section 24(2) of the Act, 2013, as clarified by the Constitution Bench in Indore Development Authority Vs. Manoharlal and Ors. The Court emphasized that the word “or” in Section 24(2) should be read as “nor” or “and,” meaning that both conditions (non-possession and non-payment) must be met for the acquisition to lapse. The Court also considered the fact that the original writ petitioner was a subsequent purchaser, who, according to previous rulings, does not have the locus standi to challenge the acquisition proceedings. The Court’s reasoning was also influenced by the principle that once possession has been taken, the land vests in the State, and there is no divesting under Section 24(2) of the Act, 2013.

Sentiment Percentage
Interpretation of Section 24(2) of the Act, 2013 40%
Locus standi of the subsequent purchaser 30%
Principle of vesting of land in State after taking possession 30%

Fact:Law Ratio

Category Percentage
Fact 20%
Law 80%

The Court’s decision was heavily based on legal interpretations and precedents, with a smaller emphasis on the specific facts of the case.

Issue: Does acquisition lapse under Section 24(2) of the Act, 2013?

Question 1: Has possession been taken?

Answer: Yes, possession was taken on 26.11.2012.

Conclusion: Acquisition does not lapse under Section 24(2) of the Act, 2013.

The Supreme Court’s reasoning was clear and direct. Since possession had been taken, the acquisition could not lapse under Section 24(2) of the Act, 2013, regardless of whether compensation had been paid to the subsequent purchaser.

The Court quoted from the judgment in Indore Development Authority Vs. Manoharlal and Ors.:

“The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse.”

The Court also stated:

See also  Supreme Court Upholds Adverse Possession Over Waqf Property: Sabir Ali Khan vs. Syed Mohd. Ahmad Ali Khan (2023)

“In the case of Godfrey Philips (I) Ltd. & Ors. (supra) , it is observed and held that the subsequent purchaser is not entitled to claim lapsing of the proceedings under the Act, 2013. In that view of the matter, the original writ petitioner – subsequent purchaser had no locus to file the writ petition to claim lapsing of the acquisition proceedings under Section 24(2) of the Act, 2013.”

Further, the Court observed:

“Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2).”

Key Takeaways

  • A subsequent purchaser of land does not have the right to challenge acquisition proceedings under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
  • Acquisition proceedings do not lapse under Section 24(2) of the Act, 2013, if possession of the land has been taken, even if compensation has not been paid to the subsequent purchaser.
  • The word “or” in Section 24(2) of the Act, 2013, should be read as “nor” or “and,” meaning that both conditions (non-possession and non-payment) must be met for the acquisition to lapse.
  • If compensation has not been paid to the recorded owner, it should be paid as and when the recorded owner or the person entitled to claim compensation approaches the authorities.

Directions

The Supreme Court directed that if the compensation is not paid to the recorded owner, as and when the recorded owner and/or the person entitled to claim compensation under the Land Acquisition Act, 1894, approaches for claiming compensation, the same be paid in accordance with law.

Development of Law

The ratio decidendi of this case is that a subsequent purchaser does not have the locus standi to challenge acquisition proceedings under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, and that acquisition proceedings do not lapse if possession has been taken, even if compensation has not been paid to the subsequent purchaser. This judgment reinforces the interpretation of Section 24(2) as laid down in Indore Development Authority Vs. Manoharlal and Ors., clarifying that both conditions (non-possession and non-payment) must be met for acquisition proceedings to lapse. This case clarifies the position of law with respect to subsequent purchasers and the interpretation of Section 24(2) of the Act, 2013. This is a reaffirmation of the position of law settled by the Constitution Bench in Indore Development Authority Vs. Manoharlal and Ors.

Conclusion

The Supreme Court’s judgment in Delhi Development Authority vs. Dayanand & Ors. clarifies the legal position regarding the locus standi of subsequent purchasers and the interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The Court held that a subsequent purchaser cannot challenge acquisition proceedings and that such proceedings do not lapse if possession has been taken, even if compensation has not been paid to the subsequent purchaser. This decision reaffirms the principles established in previous judgments and provides clarity on the application of Section 24(2).