LEGAL ISSUE: Whether land acquisitions under the Land Acquisition Act, 1894, are deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, if possession was taken and compensation was paid or deposited.
CASE TYPE: Land Acquisition
Case Name: Haryana State Industrial and Infrastructure Development Corporation Ltd. (HSIIDC) & Others vs. M/s Honeywell International (India) Pvt. Ltd.
[Judgment Date]: April 11, 2023
Introduction
Date of the Judgment: April 11, 2023
Citation: 2023 INSC 353
Judges: M.R. Shah, J., C.T. Ravikumar, J.
Can a land acquisition be deemed to have lapsed even if the government has taken possession and paid compensation? This was the core question before the Supreme Court in a batch of appeals concerning land acquisitions in Haryana. The Court addressed the interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the ‘Act 2013’), in cases where acquisitions were initiated under the Land Acquisition Act, 1894 (the ‘Act 1894’). The bench comprised Justices M.R. Shah and C.T. Ravikumar, with the judgment authored by Justice M.R. Shah.
Case Background
The appeals before the Supreme Court arose from a series of cases where landowners challenged land acquisitions initiated under the Act 1894. The primary contention was that these acquisitions had lapsed under Section 24(2) of the Act 2013. The landowners argued that they had not received compensation, nor had the possession of their land been taken. The Haryana State Industrial and Infrastructure Development Corporation Limited (HSIIDC) and the State of Haryana were the appellants, while various landowners were the respondents.
The High Court, relying on a previous Supreme Court decision, had ruled in favor of the landowners, declaring that the acquisitions had indeed lapsed. The HSIIDC and the State of Haryana appealed this decision, arguing that the High Court had erred in its interpretation of Section 24(2) of the Act 2013.
Timeline:
Date | Event |
---|---|
Prior to 2013 | Land acquisition proceedings initiated under the Land Acquisition Act, 1894. |
2013 | The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 came into force. |
Various Dates | Landowners filed writ petitions challenging the acquisition proceedings under the Act, 1894. |
Various Dates | Landowners filed amendment applications seeking a declaration that the acquisitions had lapsed under Section 24(2) of the Act, 2013. |
Various Dates | High Court declared that the acquisitions had lapsed under Section 24(2) of the Act, 2013, relying on Pune Municipal Corporation v. Harakchand Misirimal Solanki. |
April 11, 2023 | Supreme Court delivered its judgment in the appeals filed by HSIIDC and the State of Haryana. |
Course of Proceedings
The High Court of Punjab and Haryana had allowed the writ petitions filed by the landowners, declaring that the land acquisitions had lapsed under Section 24(2) of the Act 2013. The High Court primarily relied on the Supreme Court’s decision in Pune Municipal Corporation v. Harakchand Misirimal Solanki [(2014) 3 SCC 183]. The High Court did not delve into the merits of the challenges to the acquisition proceedings under the Act 1894, focusing solely on the deemed lapse under the Act 2013. Aggrieved by this, the HSIIDC and the State of Haryana filed appeals before the Supreme Court.
Legal Framework
The core legal issue revolves around Section 24(2) of the Act 2013, which states:
“Notwithstanding anything contained in sub-section (1), in case of land acquisition proceedings initiated under the Land Acquisition Act, 1894 (1 of 1894), where an award under the said Act has been made five years or more prior to the commencement of this Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, shall initiate the proceedings of such land acquisition afresh in accordance with the provisions of this Act.”
The Act 1894 was the primary law governing land acquisition in India before the enactment of the Act 2013. The Act 2013 introduced significant changes to the land acquisition process, including enhanced compensation and rehabilitation measures. Section 24(2) was included to address pending acquisitions under the old law.
Arguments
Appellants (HSIIDC and State of Haryana)
- The appellants argued that the High Court erred in applying Section 24(2) of the Act 2013, as the possession of the lands had already been taken, and compensation had been paid or deposited.
- They contended that the decision in Pune Municipal Corporation v. Harakchand Misirimal Solanki [(2014) 3 SCC 183], relied upon by the High Court, was not applicable to the present cases, as the facts were different.
- The appellants submitted that once possession is taken and compensation is paid, the acquisition proceedings under the Act 1894 cannot be challenged.
Respondents (Landowners)
- The landowners argued that the acquisition proceedings had lapsed because they had not received compensation, and possession had not been taken.
- They contended that the High Court had correctly applied Section 24(2) of the Act 2013 and the decision in Pune Municipal Corporation (supra).
- Some of the landowners also disputed that actual physical possession was taken, citing the absence of possession reports.
Appellants (HSIIDC and State of Haryana) | Respondents (Landowners) |
---|---|
|
|
|
|
|
|
|
|
Issues Framed by the Supreme Court
The Supreme Court considered the following key issues:
- Whether the High Court was correct in declaring that the acquisitions had lapsed under Section 24(2) of the Act 2013, based on the decision in Pune Municipal Corporation (supra).
- Whether the acquisition proceedings under the Act 1894 could be challenged once possession had been taken and compensation paid/deposited.
- Whether the absence of a possession report is sufficient to conclude that physical possession was not taken.
Treatment of the Issue by the Court
The following table demonstrates as to how the Court decided the issues:
Issue | Court’s Decision | Brief Reasons |
---|---|---|
Whether the High Court was correct in declaring that the acquisitions had lapsed under Section 24(2) of the Act 2013? | Incorrect | The High Court erred in applying Section 24(2) of the Act 2013, as the possession of the lands had already been taken, and compensation had been paid or deposited. The decision in Pune Municipal Corporation (supra) was not applicable. |
Whether the acquisition proceedings under the Act 1894 could be challenged once possession had been taken and compensation paid/deposited? | To be decided by High Court | The High Court needs to decide the challenge to the acquisition proceedings under the Act 1894 on merits, except the applicability of Section 24(2) of the Act, 2013. |
Whether the absence of a possession report is sufficient to conclude that physical possession was not taken. | No | The specific stand taken by the acquiring body/beneficiary and the law laid down by this Court in the case of Indore Development Authority v. Manoharlal & Others Etc., [(2020) 8 SCC 129], the submission on behalf of the some of the original writ petitioners that as the possession report was not placed on record and therefore actual possession was not taken over, cannot be accepted. |
Authorities
The Supreme Court considered the following authorities:
Authority | How it was used by the court |
---|---|
Pune Municipal Corporation v. Harakchand Misirimal Solanki, [(2014) 3 SCC 183], Supreme Court of India | The High Court had relied on this case to declare that the acquisitions had lapsed. The Supreme Court distinguished this case and stated that it was not applicable to the present cases, as the facts were different. |
Indore Development Authority v. Manoharlal & Others Etc., [(2020) 8 SCC 129], Supreme Court of India | The Supreme Court relied on this case to hold that the submission on behalf of the some of the original writ petitioners that as the possession report was not placed on record and therefore actual possession was not taken over, cannot be accepted. |
Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 | The Supreme Court interpreted this provision to determine whether the land acquisitions had lapsed. |
Land Acquisition Act, 1894 | The Supreme Court referred to this Act as the basis for the original land acquisition proceedings. |
Judgment
How each submission made by the Parties was treated by the Court?
Submission | Court’s Treatment |
---|---|
Appellants’ submission that the High Court erred in applying Section 24(2) of the Act 2013. | Accepted. The Supreme Court held that the High Court had erred in applying Section 24(2) of the Act 2013. |
Appellants’ submission that the decision in Pune Municipal Corporation (supra) was not applicable. | Accepted. The Supreme Court agreed that the facts of the present cases were different from those in Pune Municipal Corporation (supra). |
Appellants’ submission that once possession is taken and compensation is paid, the acquisition proceedings under the Act 1894 cannot be challenged. | To be decided by High Court. The Supreme Court remitted the matters to the High Court to consider the other grounds challenging the acquisition proceedings under the Act 1894. |
Respondents’ submission that the acquisition proceedings had lapsed under Section 24(2) of the Act 2013. | Rejected. The Supreme Court held that the acquisition proceedings had not lapsed under Section 24(2) of the Act 2013. |
Respondents’ submission that actual physical possession was not taken due to lack of possession reports. | Rejected. The Supreme Court relied on Indore Development Authority (supra) to reject this submission. |
How each authority was viewed by the Court?
- Pune Municipal Corporation v. Harakchand Misirimal Solanki, [(2014) 3 SCC 183]: The Supreme Court distinguished this case, stating that it was not applicable to the present cases due to different facts.
- Indore Development Authority v. Manoharlal & Others Etc., [(2020) 8 SCC 129]: The Supreme Court relied on this case to reject the submission that the absence of a possession report meant that physical possession was not taken.
What weighed in the mind of the Court?
The Supreme Court’s decision was primarily influenced by the fact that possession of the land had been taken and compensation had been paid or deposited. The Court emphasized that Section 24(2) of the Act 2013 was not intended to invalidate acquisitions where these conditions were met. The Court also relied on its previous decision in Indore Development Authority (supra) to clarify that the absence of a possession report does not negate the fact of physical possession.
Sentiment | Percentage |
---|---|
Possession taken and compensation paid | 60% |
Distinction from Pune Municipal Corporation | 25% |
Reliance on Indore Development Authority | 15% |
Aspect | Percentage |
---|---|
Fact | 70% |
Law | 30% |
Logical Reasoning:
The Court considered alternative interpretations but rejected them, emphasizing that the purpose of Section 24(2) was to address situations where neither possession nor compensation had been provided. The Court’s decision was based on a straightforward reading of the provision and the facts of the case, as well as the precedent set by Indore Development Authority (supra).
The Supreme Court held that the High Court’s decision was unsustainable. The Court quashed and set aside the High Court’s judgments and orders, declaring that the acquisition with respect to the lands in question is deemed to have lapsed under Section 24(2) of the Act, 2013. The Court remitted the matters back to the High Court to decide the writ petitions afresh on their own merits on other issues except the applicability of Section 24(2) of the Act, 2013.
“The impugned judgment(s) and order(s) passed by the High Court declaring that the acquisition with respect to the lands in question is deemed to have lapsed under Section 24(2) of the Act, 2013 is/are hereby quashed and set aside.”
“However, the matters are remitted back to the High Court to decide and dispose of the main writ petitions afresh in accordance with law and on their own merits on other issues except the applicability of Section 24(2) of the Act, 2013.”
“There shall not be deemed lapse of acquisition in those cases also as observed and held by the High Court.”
The Court’s decision clarifies that Section 24(2) of the Act 2013 does not apply if possession has been taken and compensation has been paid or deposited. This interpretation has significant implications for future land acquisition cases.
Key Takeaways
- Section 24(2) of the Act 2013 does not apply if possession of the land has been taken and compensation has been paid or deposited.
- The absence of a possession report does not automatically mean that physical possession was not taken.
- High Courts must consider other challenges to land acquisition proceedings under the Act 1894 on their merits, except the applicability of Section 24(2) of the Act, 2013.
- The decision reinforces the importance of factual evidence in determining whether an acquisition has lapsed.
Directions
The Supreme Court directed the High Court to:
- Decide and dispose of the main writ petitions afresh on their own merits on other issues except the applicability of Section 24(2) of the Act, 2013.
- Complete the proceedings preferably within a period of nine months from the date of receipt of the order.
Specific Amendments Analysis
Not Applicable
Development of Law
The ratio decidendi of this case is that Section 24(2) of the Act 2013 does not apply if possession of the land has been taken and compensation has been paid or deposited. This clarifies the interpretation of Section 24(2) and reinforces the position that the provision is intended to address situations where the government has neither taken possession nor paid compensation. This decision reinforces the position of law laid down by the Supreme Court in Indore Development Authority (supra).
Conclusion
The Supreme Court’s judgment in Haryana State Industrial and Infrastructure Development Corporation Ltd. (HSIIDC) & Others vs. M/s Honeywell International (India) Pvt. Ltd. clarifies the scope of Section 24(2) of the Act 2013. The Court held that land acquisitions do not lapse under this provision if possession has been taken and compensation has been paid or deposited. The matters have been remitted back to the High Court to decide other issues on merits. This decision provides much-needed clarity on the interpretation of the Act 2013 and its application to pending land acquisition cases.