Date of the Judgment: February 17, 2023
Citation: 2023 INSC 124
Judges: M.R. Shah, J., C.T. Ravikumar, J., and Sanjay Karol, J.

Can a land acquisition be deemed to have lapsed if the compensation hasn’t been paid, even if possession has been taken? The Supreme Court addressed this critical question in a recent case concerning the interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The court clarified that if possession of the land has been taken, the acquisition does not lapse even if compensation has not been paid. This judgment has significant implications for landowners and acquisition authorities alike. The judgment was delivered by a three-judge bench comprising Justices M.R. Shah, C.T. Ravikumar, and Sanjay Karol, with Justice M.R. Shah authoring the opinion.

Case Background

The Land and Building Department and the Land Acquisition Collector appealed a decision by the High Court of Delhi. The High Court had ruled that the land acquisition in question had lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the “Act, 2013”). The High Court based its decision on the fact that compensation had not been paid to the landowners, relying on a previous Supreme Court judgment in Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors. However, the appellants argued that possession of the land had been taken on March 28, 2007.

Timeline

Date Event
March 28, 2007 Possession of the land was allegedly taken by the authorities.
2013 The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 came into effect.
2014 The High Court of Delhi declared the acquisition lapsed under Section 24(2) of the 2013 Act.
February 17, 2023 The Supreme Court overturned the High Court’s decision.

Course of Proceedings

The High Court of Delhi ruled in favor of the landowners, stating that the acquisition had lapsed under Section 24(2) of the Act, 2013, because compensation had not been paid. The High Court relied on the Supreme Court’s decision in Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors. The Land and Building Department and the Land Acquisition Collector then appealed to the Supreme Court.

Legal Framework

The case revolves around Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. This section deals with the lapse of land acquisition proceedings if certain conditions are met. The Supreme Court also considered the interpretation of this section in light of its previous judgments, particularly the Constitution Bench decision in Indore Development Authority Vs. Manoharlal and Ors.

Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 states:

“Notwithstanding anything contained in sub-section (1), in case of land acquisition proceedings initiated under the Land Acquisition Act, 1894 (1 of 1894), where an award under the said Act has been made five years or more prior to the commencement of this Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, shall initiate the proceedings of such land acquisition afresh in accordance with the provisions of this Act.”

Arguments

The appellants (Land and Building Department and the Land Acquisition Collector) argued that the High Court erred in applying the decision in Pune Municipal Corporation, which had been overruled by a Constitution Bench in Indore Development Authority. They emphasized that possession of the land had been taken on March 28, 2007, and therefore, the acquisition could not be deemed to have lapsed under Section 24(2) of the Act, 2013. The appellants relied on the interpretation of Section 24(2) as laid down in Indore Development Authority, where it was held that the word “or” between possession and compensation should be read as “nor” or “and.”

See also  Supreme Court settles the issue of Disproportionate Punishment in Departmental Proceedings: Union of India vs. P. Balasubrahmanyam (04 March 2021)

The respondents (Manish Sethi and Ors.) argued that since compensation had not been paid, the acquisition should be deemed to have lapsed under Section 24(2). They relied on the High Court’s decision, which was based on the interpretation of Section 24(2) in Pune Municipal Corporation, where it was held that if either possession was not taken or compensation was not paid, the acquisition would lapse.

Main Submission Sub-Submissions
Appellants (Land and Building Department and Land Acquisition Collector)
  • High Court erred in applying Pune Municipal Corporation.
  • Possession of the land was taken on March 28, 2007.
  • Acquisition cannot lapse under Section 24(2) based on Indore Development Authority.
  • “Or” in Section 24(2) should be read as “nor” or “and.”
Respondents (Manish Sethi and Ors.)
  • Compensation was not paid.
  • Acquisition should lapse under Section 24(2).
  • Relied on High Court’s decision based on Pune Municipal Corporation.
  • If either possession was not taken or compensation was not paid, the acquisition lapses.

Issues Framed by the Supreme Court

The core issue before the Supreme Court was:

  1. Whether the acquisition of land in question is deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, given that possession was taken on March 28, 2007, but compensation was allegedly not paid?

Treatment of the Issue by the Court

The following table demonstrates as to how the Court decided the issues

Issue Court’s Decision
Whether the acquisition of land in question is deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013? The Supreme Court held that the acquisition did not lapse under Section 24(2) of the Act, 2013, because possession of the land had been taken on March 28, 2007. The court relied on the Constitution Bench decision in Indore Development Authority Vs. Manoharlal and Ors., which clarified that the word “or” in Section 24(2) should be read as “nor” or “and.” Therefore, for the acquisition to lapse, both possession must not be taken and compensation must not be paid. Since possession had been taken, the acquisition did not lapse, regardless of whether compensation had been paid.

Authorities

The Supreme Court relied on the following authorities:

Authority Court How it was used Legal Point
Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors. [(2014) 3 SCC 183] Supreme Court of India Overruled Interpretation of Section 24(2) of the Act, 2013.
Indore Development Authority Vs. Manoharlal and Ors. [(2020) 8 SCC 129] Supreme Court of India Relied upon Interpretation of Section 24(2) of the Act, 2013; specifically, that the word “or” should be read as “nor” or “and.”
Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 Statute Interpreted Deemed lapse of land acquisition proceedings.

Judgment

The Supreme Court allowed the appeal, setting aside the High Court’s judgment. The Court held that the acquisition did not lapse under Section 24(2) of the Act, 2013, because possession of the land had been taken on March 28, 2007. The Court emphasized that the word “or” in Section 24(2) should be read as “nor” or “and,” as clarified in Indore Development Authority. Therefore, both non-possession and non-payment of compensation are required for the acquisition to lapse. Because possession was taken, the acquisition did not lapse, regardless of whether compensation was paid.

Submission by Parties Treatment by the Court
High Court erred in applying Pune Municipal Corporation. Accepted. The Supreme Court agreed that the High Court’s reliance on Pune Municipal Corporation was incorrect because that decision had been overruled.
Possession of the land was taken on March 28, 2007. Accepted. The Supreme Court noted the appellant’s claim that possession was taken on this date.
Acquisition cannot lapse under Section 24(2) based on Indore Development Authority. Accepted. The Supreme Court agreed that the interpretation of Section 24(2) in Indore Development Authority meant that the acquisition did not lapse.
“Or” in Section 24(2) should be read as “nor” or “and.” Accepted. The Supreme Court reiterated the ruling in Indore Development Authority that “or” should be read as “nor” or “and.”
Compensation was not paid. Not decisive. The Supreme Court clarified that non-payment of compensation alone does not cause the acquisition to lapse if possession has been taken.
Acquisition should lapse under Section 24(2). Rejected. The Supreme Court held that the acquisition did not lapse because possession was taken.
Relied on High Court’s decision based on Pune Municipal Corporation. Rejected. The Supreme Court noted that the High Court’s reliance on Pune Municipal Corporation was incorrect.
If either possession was not taken or compensation was not paid, the acquisition lapses. Rejected. The Supreme Court clarified that both conditions (non-possession and non-payment) must be met for the acquisition to lapse.
See also  Supreme Court Upholds 1934 Constitution in Malankara Church Disputes: K.S. Varghese & Ors. vs. St. Peter’s & Paul’s Syrian Orth. & Ors. (2017)

Authorities Viewed by the Court:

Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors. [(2014) 3 SCC 183]* was overruled by the Constitution Bench of the Supreme Court in Indore Development Authority Vs. Manoharlal and Ors.. The Court stated that the interpretation of Section 24(2) in Pune Municipal Corporation was incorrect.

Indore Development Authority Vs. Manoharlal and Ors. [(2020) 8 SCC 129]* was relied upon by the Court. The Constitution Bench clarified that the word “or” in Section 24(2) should be read as “nor” or “and.” This meant that both non-possession and non-payment of compensation were required for the acquisition to lapse.

What weighed in the mind of the Court?

The Supreme Court’s decision was primarily influenced by the interpretation of Section 24(2) of the Act, 2013, as clarified by the Constitution Bench in Indore Development Authority. The Court emphasized that the word “or” in Section 24(2) should be read as “nor” or “and,” meaning both non-possession and non-payment of compensation are necessary for a deemed lapse. The Court noted that the High Court had incorrectly relied on the overruled decision of Pune Municipal Corporation. The fact that possession had been taken on March 28, 2007, was a crucial factor in the Court’s decision.

Reason Percentage
Correct interpretation of Section 24(2) as per Indore Development Authority 40%
Overruling of Pune Municipal Corporation 30%
Fact of possession being taken on March 28, 2007 30%
Category Percentage
Fact 30%
Law 70%

Issue: Whether acquisition lapsed under Section 24(2) of the 2013 Act?

Question 1: Was possession of the land taken?

Answer: Yes, possession was taken on March 28, 2007.

Question 2: Was compensation paid?

Answer: Not decisive. As per Indore Development Authority, non-payment of compensation alone does not cause the acquisition to lapse if possession has been taken.

Conclusion: Acquisition did not lapse under Section 24(2) of the 2013 Act.

The Court’s reasoning was based on the following:

“The decision of this Court in the case of Pune Municipal Corporation and Anr. (supra) has been overruled by the Constitution Bench of this Court in the case of Indore Development Authority Vs. Manoharlal and Ors. reported in (2020) 8 SCC 129.”

“The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid.”

“In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse.”

Key Takeaways

  • ✓ Land acquisition proceedings will not lapse under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, if possession of the land has been taken, regardless of whether compensation has been paid.
  • ✓ The word “or” in Section 24(2) should be interpreted as “nor” or “and,” as clarified by the Supreme Court in Indore Development Authority Vs. Manoharlal and Ors..
  • ✓ The decision in Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors. has been overruled and cannot be relied upon for interpreting Section 24(2).
See also  Supreme Court Enhances Compensation for Scrap Dealer in Motor Accident Case: Mohd. Sabeer @ Shabir Hussain vs. Regional Manager, U.P. State Road Transport Corporation (2022) INSC 1047 (09 December 2022)

Directions

No specific directions were given by the Supreme Court in this case.

Development of Law

The judgment clarifies the interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. It reinforces the position of law established in Indore Development Authority Vs. Manoharlal and Ors., which overruled Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors.. The ratio decidendi is that for land acquisition proceedings to lapse under Section 24(2), both possession must not be taken and compensation must not be paid. This settles the legal position that non-payment of compensation alone is insufficient for the acquisition to lapse if possession has been taken.

Conclusion

The Supreme Court’s decision in Land and Building Department and Anr. vs. Manish Sethi and Ors. clarifies that land acquisitions do not lapse under Section 24(2) of the 2013 Act if possession has been taken, even if compensation has not been paid. This judgment reaffirms the interpretation of Section 24(2) as laid down in Indore Development Authority, ensuring that the word “or” is read as “nor” or “and.” This ruling has significant implications for land acquisition proceedings, providing clarity on the conditions under which acquisitions can be deemed to have lapsed.