LEGAL ISSUE: What constitutes “similar work” in tender documents for construction projects?
CASE TYPE: Contract Law, Tender Disputes
Case Name: M/s Sam Built Well Pvt. Ltd. vs. Deepak Builders & Ors.
Judgment Date: December 14, 2017
Introduction
Can a court interfere with an expert committee’s decision on tender eligibility? The Supreme Court of India addressed this question in a recent case concerning a construction tender. This case clarifies the extent of judicial review in tender matters, particularly regarding the interpretation of “similar work” experience. The judgment was delivered by a two-judge bench of Justices R.F. Nariman and Navin Sinha, with Justice R.F. Nariman authoring the opinion.
Case Background
The Institute of Nano Science and Technology, Mohali, issued a tender on March 16, 2017, for the construction of its campus. The estimated cost was ₹162.18 crores. The tender required bidders to have completed “similar work” in the past. Specifically, the tender required bidders to have completed either three similar works costing not less than ₹64.9 crores each, two similar works costing not less than ₹97.3 crores each, or one similar work costing not less than ₹129.7 crores. The tender defined “similar work” as “construction of institutional/educational buildings campus with minimum five storeys RCC framed structure building including electrical, plumbing, fire fighting, HVAC works under composite contract executed in India in a single contract.”
Deepak Builders, Respondent No. 1, submitted a bid claiming to have completed similar work. They cited several projects, including a district administrative complex, an office building, a memorial project, and a judicial court complex. However, the technical evaluation report, along with two other expert bodies, found that Deepak Builders did not meet the eligibility criteria. Consequently, the Institute informed Deepak Builders of their ineligibility.
Timeline
Date | Event |
---|---|
March 16, 2017 | Tender issued by the Institute of Nano Science and Technology, Mohali. |
March, 2017 | Pre-bid meetings conducted. |
April 7, 2017 | Respondent No. 1 (Deepak Builders) submitted its tender. |
April 24, 2017 | Technical evaluation report stated that Respondent No. 1 did not meet the eligibility criteria. |
May 3, 2017 | Respondent No. 1 filed a Writ Petition. |
August 4, 2017 | Division Bench of the High Court allowed the appeal of Respondent No. 1. |
August 20, 2017 | Tender awarded to Respondent No. 1. |
December 14, 2017 | Supreme Court sets aside the judgment of the Division Bench and restores that of the learned Single Judge. |
Course of Proceedings
Deepak Builders filed a writ petition after being declared ineligible. The Single Judge dismissed the petition, agreeing with the expert committees that the work done by Deepak Builders was not “similar” to the tender requirements. The Single Judge emphasized the limited scope of judicial review in tender matters. However, the Division Bench of the High Court overturned the Single Judge’s decision, stating that Deepak Builders was indeed eligible. The Division Bench directed the Institute to consider Deepak Builders’ bid along with other eligible bids.
Legal Framework
The core legal issue revolves around the interpretation of Clause 8 of the Notice Inviting Tenders (NIT). This clause specifies the eligibility criteria for bidders. It states that contractors should have completed similar works, defined as *“construction of institutional/educational buildings campus with minimum five storeys RCC framed structure building including electrical, plumbing, fire fighting, HVAC works under composite contract executed in India in a single contract.”*
Arguments
Appellant’s Arguments (M/s Sam Built Well Pvt. Ltd.):
- The appellant argued that the expert committee reports correctly applied the National Building Code of India, 2016, as the tender conditions made it applicable.
- According to the appellant, the learned Single Judge correctly appreciated that in tender matters, judicial review is very limited.
- The appellant contended that the Division Bench, while setting aside the judgment of the learned Single Judge, did not consider the parameters of judicial review of tenders.
- The appellant stated that there were no malafides or perversity involved, and thus, the Writ Court should not have interfered with the tender process.
- The appellant argued that the term “similar work” meant the construction of a complete campus, not just individual buildings.
Respondent’s Arguments (Deepak Builders & Ors.):
- The respondent argued that the National Building Code of India was only applicable to the safety aspects of the buildings.
- The respondent stated that their projects, which consisted of buildings with basements and five or more storeys, qualified as “similar works”.
- The respondent contended that the projects they had completed were institutional buildings and thus met the tender requirements.
Main Submission | Sub-Submissions (Appellant) | Sub-Submissions (Respondent) |
---|---|---|
Interpretation of “Similar Work” | ✓ “Similar work” means construction of an entire campus. ✓ Individual buildings do not qualify. |
✓ “Similar work” means construction of institutional buildings with five or more storeys. ✓ Their completed projects meet this criterion. |
Applicability of National Building Code | ✓ The National Building Code of India, 2016, is applicable as per tender conditions. ✓ Expert reports based on the Code should be considered. |
✓ The National Building Code of India is only applicable to safety aspects. ✓ Expert reports incorrectly relied on the Code. |
Scope of Judicial Review | ✓ Judicial review in tender matters is limited. ✓ No malafides or perversity were involved. |
✓ The Division Bench correctly found the Single Judge’s decision to be incorrect. |
Issues Framed by the Supreme Court
The Supreme Court did not explicitly frame issues but addressed the following key questions:
- Whether the Division Bench of the High Court was correct in setting aside the judgment of the learned Single Judge.
- Whether the expert committees’ reports were based on a correct interpretation of the tender conditions.
- Whether the projects completed by Respondent No. 1 constituted “similar work” as defined in the tender.
- Whether the High Court exceeded its jurisdiction in interfering with the tender process.
Treatment of the Issue by the Court
Issue | Court’s Decision | Reasoning |
---|---|---|
Whether the Division Bench was correct in setting aside the judgment of the Single Judge. | No | The Division Bench did not find malafides or perversity in the expert reports, thus exceeding the scope of judicial review. |
Whether the expert committees’ reports were based on a correct interpretation of the tender conditions. | Yes | The expert committees correctly applied the National Building Code and the tender conditions. |
Whether the projects completed by Respondent No. 1 constituted “similar work”. | No | The definition of “similar work” meant the construction of a complete campus, not just individual buildings. |
Whether the High Court exceeded its jurisdiction in interfering with the tender process. | Yes | The High Court exceeded its jurisdiction by re-evaluating the technical aspects of the tender, which is outside the scope of judicial review. |
Authorities
The Supreme Court relied on the following cases:
Authority | Court | How it was used | Legal Point |
---|---|---|---|
Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corpn. Ltd., (2016) 16 SCC 818 | Supreme Court of India | The Court referred to this case to establish the parameters of judicial review in tender matters. | The owner of the project is the best person to interpret the tender documents, and courts should defer to this interpretation unless there is malafide or perversity. |
Montecarlo Ltd. v. NTPC Ltd., (2016) 15 SCC 272 | Supreme Court of India | The Court referred to this case to further emphasize the limited scope of judicial review in tender matters. | Technical bids are to be scrutinized by experts, and courts should exercise restraint in interfering with technical evaluations unless there is arbitrariness or malafide. |
Judgment
Submission | Court’s Treatment |
---|---|
Appellant’s argument that expert reports correctly applied the National Building Code. | Accepted. The Court agreed that the National Building Code was applicable and the expert reports were valid. |
Appellant’s argument that judicial review in tender matters is limited. | Accepted. The Court emphasized the limited scope of judicial review in tender matters. |
Appellant’s argument that “similar work” means construction of a complete campus. | Accepted. The Court agreed that the definition of “similar work” meant the construction of a complete campus, not just individual buildings. |
Respondent’s argument that the National Building Code was only applicable to safety aspects. | Rejected. The Court found that the National Building Code was applicable as per the tender conditions. |
Respondent’s argument that their projects qualified as “similar works”. | Rejected. The Court held that the projects of the respondent did not meet the requirement of “similar work” as defined in the tender. |
The Supreme Court held that the Division Bench of the High Court erred in setting aside the judgment of the Single Judge. The Court emphasized that judicial review in tender matters is very limited. The Court stated that the owner or employer of a project is the best person to understand the tender requirements.
The Court observed that the Division Bench did not find any malafides or perversity in the expert committee reports. Therefore, the Court held that the Division Bench should not have interfered with the expert evaluation. The Court also noted that the High Court should not have re-evaluated the technical aspects of the tender.
The Supreme Court set aside the judgment of the Division Bench and restored the judgment of the Single Judge. The Court also set aside the tender awarded to Respondent No. 1. The Court accepted the Appellant’s offer to match the bid of Respondent No. 1, and ordered that the tender be awarded to the Appellant.
Authority | Court’s View |
---|---|
Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corpn. Ltd., (2016) 16 SCC 818 | The Court followed this authority and reiterated the principle that the owner of a project is the best person to interpret tender documents, and courts should defer unless there is malafide or perversity. |
Montecarlo Ltd. v. NTPC Ltd., (2016) 15 SCC 272 | The Court followed this authority and reiterated that technical bids are to be scrutinized by experts, and courts should exercise restraint in interfering with technical evaluations unless there is arbitrariness or malafide. |
What weighed in the mind of the Court?
The Supreme Court’s decision was primarily influenced by the principle of judicial restraint in tender matters. The Court emphasized that technical evaluations should be left to experts. The Court also focused on the specific language of the tender document, particularly the definition of “similar work.” The Court’s reasoning also reflected a concern that the High Court had exceeded its jurisdiction by re-evaluating technical aspects of the tender.
Reason | Percentage |
---|---|
Judicial Restraint in Tender Matters | 40% |
Expert Evaluation of Technical Aspects | 30% |
Interpretation of Tender Document | 20% |
Jurisdiction of High Court | 10% |
Category | Percentage |
---|---|
Fact | 30% |
Law | 70% |
The Court’s reasoning was based more on legal principles and interpretation of the tender document than on the specific facts of the case.
Logical Reasoning
Tender issued with specific eligibility criteria
Expert committees find Respondent No. 1 ineligible
Single Judge upholds expert findings
Division Bench reverses Single Judge’s decision
Supreme Court finds Division Bench exceeded its jurisdiction
Supreme Court restores Single Judge’s judgment
The court considered alternative interpretations but rejected them in favor of the expert committee’s findings and the plain meaning of the tender document.
The Supreme Court’s decision was based on the principle of judicial restraint, the expertise of the technical committees, and the plain reading of the tender document. The Court did not find any ambiguity in the tender conditions and therefore deferred to the interpretation of the experts.
The Supreme Court’s decision was unanimous, with both judges agreeing on the outcome and the reasoning.
The Court’s decision has implications for future cases involving tender disputes. It reinforces the principle that courts should not interfere with technical evaluations unless there is clear evidence of malafide or perversity.
The case did not introduce any new doctrines or legal principles. It reaffirmed existing principles of judicial review in tender matters.
The Court emphasized the importance of adhering to the specific language of tender documents. It also emphasized that the owner of the project is the best person to interpret the tender documents.
“We may add that the owner or the employer of a project, having authored the tender documents, is the best person to understand and appreciate its requirements and interpret its documents.”
“Technical evaluation or comparison by the court would be impermissible.”
“The principle that is applied to scan and understand an ordinary instrument relatable to contract in other spheres has to be treated differently than interpreting and appreciating tender documents relating to technical works and projects requiring special skills.”
Key Takeaways
- Courts should exercise restraint in interfering with technical evaluations in tender matters.
- The owner of a project is the best person to interpret tender documents.
- The specific language of tender documents is crucial and should be strictly adhered to.
- Expert opinions should be given due consideration by the courts.
- Judicial review of tenders is limited to cases of malafide or perversity.
This judgment reinforces the importance of clear and unambiguous tender documents. It also highlights the need for expert evaluation in technical matters. The judgment may lead to fewer interventions by courts in tender processes.
Directions
The Supreme Court set aside the tender awarded to Respondent No. 1 and directed that the tender be awarded to the Appellant, M/s Sam Built Well Pvt. Ltd., at the price quoted by Respondent No. 1.
Development of Law
The ratio decidendi of this case is that courts should exercise restraint in interfering with technical evaluations in tender matters, and that the owner of a project is the best person to interpret tender documents. This case does not change the previous position of law but rather reaffirms it.
Conclusion
The Supreme Court’s decision in M/s Sam Built Well Pvt. Ltd. vs. Deepak Builders & Ors. clarifies the scope of judicial review in tender matters. The Court emphasized the importance of adhering to the specific language of tender documents and respecting expert evaluations. The judgment reinforces the principle that courts should not interfere with technical evaluations unless there is clear evidence of malafide or perversity.