LEGAL ISSUE: Determination of fair compensation for land acquisition.
CASE TYPE: Land Acquisition
Case Name: New Okhla Industrial Development Authority vs. Harnand Singh (Deceased) through LRs
[Judgment Date]: 10 July 2024
Introduction
Date of the Judgment: 10 July 2024
Citation: 2024 INSC 509
Judges: Surya Kant, J., K.V. Viswanathan, J.
When the government acquires land for development, how is the compensation determined? The Supreme Court of India recently addressed this question in a case involving the New Okhla Industrial Development Authority (NOIDA) and landowners in Village Chhalera Bangar. The core issue was the fair market value of the acquired land and whether the landowners were entitled to enhanced compensation. The judgment was delivered by a two-judge bench of Justices Surya Kant and K.V. Viswanathan.
Case Background
The case involves land acquisition initiated by the State of Uttar Pradesh/NOIDA on 05 January 1991, for approximately 492 acres in Village Chhalera Bangar for planned industrial development. A notification under Section 4(1) of the Land Acquisition Act, 1894 (the 1894 Act) was issued on this date. Subsequently, on 07 January 1992, a declaration under Section 6, along with an urgency clause under Section 17 of the 1894 Act, was issued. Possession of the land was taken on 30 March 1992, 07 August 1995, and 18 November 1995. The Land Acquisition Officer (LAO) issued an award on 17 August 1996, fixing compensation at INR 110 per sq. yd., relying on a sale deed from 16 December 1988.
Landowners sought enhanced compensation under Section 18 of the 1894 Act. The Reference Court granted compensation at rates of INR 233 and INR 222 per square yard, applying a 40% deduction for development on a market value of INR 390 per sq. yd. Some landowners appealed to the High Court of Judicature at Allahabad. In one set of appeals, the High Court reversed the deductions and directed compensation at INR 297.50 per sq. yd. without deductions, in its judgment dated 14 December 2007. However, in another set of appeals, the High Court refused to enhance compensation in its judgment dated 09 May 2008.
The High Court later clarified its judgment on 19 May 2010, enhancing compensation to INR 340 per sq. yd. Other similar appeals were also allowed, with compensation enhanced to INR 340 per sq. yd. Some landowners then approached the Supreme Court, but their Special Leave Petitions (SLPs) were dismissed on 05 February 2014. However, in a separate case, Bir Singh v. State of Uttar Pradesh, the Supreme Court enhanced compensation to INR 449 per sq. yd. on 09 November 2017, relying on a sale exemplar from 16 December 1988. Review and Curative Petitions against this order were dismissed on 06 March 2018 and 13 March 2019, respectively. Consequently, all pending First Appeals before the High Court were decided in line with Bir Singh, enhancing compensation to INR 449 per sq. yd.
The current appeals before the Supreme Court challenge High Court orders that granted compensation at INR 340 per sq. yd. before the Bir Singh judgment. Landowners seek parity with the INR 449 per sq. yd. rate. NOIDA also filed appeals challenging the enhanced compensation of INR 449 per sq. yd. granted to some landowners. Additionally, some landowners filed Miscellaneous Applications seeking a recall of the dismissal of their SLPs and to restore parity with Bir Singh.
Timeline
Date | Event |
---|---|
05 January 1991 | Notification issued under Section 4(1) of the 1894 Act for land acquisition. |
07 January 1992 | Declaration issued under Section 6, with urgency clause under Section 17 of the 1894 Act. |
30 March 1992, 07 August 1995, 18 November 1995 | Possession of the land taken. |
17 August 1996 | Land Acquisition Officer (LAO) issued an award fixing compensation at INR 110 per sq. yd. |
14 December 2007 | High Court reversed deductions, directed compensation at INR 297.50 per sq. yd. in one set of appeals. |
09 May 2008 | High Court refused to enhance compensation in another set of appeals. |
19 May 2010 | High Court clarified its judgment, enhancing compensation to INR 340 per sq. yd. |
05 February 2014 | Supreme Court dismissed some landowners’ Special Leave Petitions (SLPs). |
09 November 2017 | Supreme Court enhanced compensation to INR 449 per sq. yd. in Bir Singh v. State of Uttar Pradesh. |
06 March 2018 | Review Petitions against the Bir Singh order were dismissed. |
13 March 2019 | Curative Petitions against the Bir Singh order were dismissed. |
08 February 2021 | High Court passed judgment enhancing compensation to INR 449 per sq. yd. in line with Bir Singh. |
22 July 2021 | High Court passed review order in the lead case. |
10 July 2024 | Supreme Court delivered the present judgment. |
Course of Proceedings
The landowners, dissatisfied with the compensation awarded by the Land Acquisition Officer (LAO), sought an enhancement by filing references before the Additional District Judge, Ghaziabad, acting as the Reference Court, under Section 18 of the Land Acquisition Act, 1894. The Reference Court determined the market value of the land to be INR 390 per sq. yd., and after applying a 40% deduction for development, awarded compensation at rates of INR 233 and INR 222 per square yard. Aggrieved by this, some landowners filed appeals before the High Court of Judicature at Allahabad.
The High Court, in one set of appeals, reversed the deductions made by the Reference Court and directed the State/NOIDA authorities to recalculate the compensation at INR 297.50 per sq. yd. without deducting development charges. However, in another similar group of appeals, the High Court refused to enhance the compensation. Subsequently, the High Court clarified its earlier judgment and enhanced the compensation to INR 340 per sq. yd. The other alike appeals filed by similarly situated landowners were also allowed in part and the compensation was enhanced to INR 340 per sq. yd.
Some landowners approached the Supreme Court seeking further enhancement, but their Special Leave Petitions (SLPs) were dismissed on 05.02.2014. However, in Civil Appeal Nos. 18620-18623 / 2017 titled Bir Singh v. State of Uttar Pradesh, the Supreme Court further enhanced the compensation to INR 449 per sq. yd., relying on a sale exemplar dated 16.12.1988. The Review and Curative Petitions preferred by the State / NOIDA authorities against this order were dismissed. Consequently, all the First Appeals pending before the High Court, pertaining to the same acquisition came to be allowed in line with Bir Singh (supra), and compensation was accordingly enhanced to INR 449 per sq. yd.
The matters pending before the Supreme Court were categorized into two groups: (i) SLPs, Miscellaneous Applications and Civil Appeals preferred by landowners who had already been granted compensation at INR 340 per sq. yd. and who are now seeking parity with Bir Singh (supra) where compensation was enhanced to INR 449 per sq. yd.; and (ii) Civil Appeals preferred by NOIDA as against the enhanced compensation of INR 449 per sq. yd. granted to some of the landowners.
Legal Framework
The primary legal framework for this case is the Land Acquisition Act, 1894. Section 4(1) of the 1894 Act provides for the issuance of a notification for the acquisition of land. Section 6 allows for the declaration of intended acquisition, and Section 17 includes an urgency clause that allows for immediate possession of the land. Section 11 of the 1894 Act deals with the Land Acquisition Officer (LAO) issuing an award, determining the compensation for the land.
Section 18 of the 1894 Act allows landowners to seek a reference to the Reference Court for enhancement of compensation. Section 23(1) of the 1894 Act outlines the matters to be considered in determining compensation, primarily the market value of the land at the date of the Section 4(1) notification. It states:
“23. Matters to be considered in determining compensation. — (1) In determining the amount of compensation to be awarded for land acquired under this Act, the Court shall take into consideration— first, the market-value of the land at the date of the publication of the notification under Section 4, sub-section (1); secondly, the damage sustained by the person interested, by reason of the taking of any standing crops or trees which may be on the land at the time of the Collector’s taking possession thereof; thirdly, the damage (if any) sustained by the person interested, at the time of the Collector’s taking possession of the land, by reason of severing such land from his other land; fourthly, the damage (if any) sustained by the person interested, at the time of the Collector’s taking possession of the land, by reason of the acquisition injuriously affecting his other property, movable or immovable, in any other manner, or his earnings; fifthly, if, in consequence of the acquisition of the land by the Collector, the person interested is compelled to change his residence or place of business, the reasonable expenses (if any) incidental to such change; and sixthly, the damage (if any) bona fide resulting from diminution of the profits of the land between the time of the publication of the declaration under Section 6 and the time of the Collector’s taking possession of the land.”
Section 28A of the 1894 Act, introduced by the Land Acquisition (Amendment) Act, 1984, allows landowners to seek redetermination of compensation if any other affected person receives enhanced compensation.
Arguments
Arguments on behalf of NOIDA:
-
NOIDA argued that the Supreme Court’s decision in Bir Singh v. State of Uttar Pradesh, which enhanced compensation to INR 449 per sq. yd., was based on a factual error. The Court had misread a sale exemplar, taking the extent of land (400 sq. yds.) as the value of the land (INR 400 per sq. yd.).
-
The decision in Bir Singh is binding only on the parties to that case and should not be treated as a precedent for other landowners.
-
Landowners cannot invoke Section 28A of the Land Acquisition Act, 1894 for re-determination of market value as this provision is restricted to compensation determined by the Reference Court. Reliance was placed on Ramsingbhai Jerambhai v. State of Gujarat (2018) 16 SCC 445.
-
The sale deeds produced by landowners were of abadi land, whereas the acquired land was agricultural or non-abadi land.
-
The acquired land is a large tract and requires substantial development before it can be used for industrial purposes.
-
A uniform rate of compensation should be fixed for the entire acquisition, rather than individual rates for different parcels of land.
-
The compensation should not be based on the current market value, as rates have increased due to planned development post-acquisition.
-
The circle rate does not accurately reflect the market value of the acquired land, which was an undeveloped agricultural tract.
-
The Miscellaneous Applications seeking to rely on Bir Singh for recalling the orders dismissing the SLPs are not maintainable due to significant delays.
-
The land has already been allocated to third parties, and it is impossible to recover the enhanced compensation amount.
Arguments on behalf of the Landowners:
-
The landowners acknowledged that the decision in Bir Singh was based on a factual error but claimed compensation not less than the rate awarded in Bir Singh.
-
A sale exemplar dated 22 February 1989, showed a plot of 470 sq. yds. sold at INR 446 per sq. yd., which is similar to the sale instance relied upon in Bir Singh.
-
The factors for evaluating the potentiality of land are the same as those used for fixing the circle rate.
-
The circle rate is a crucial piece of evidence for determining market value.
-
The acquired land is situated amidst developed areas, near the Amity Public School, a large golf course, a film city, and developed residential colonies and shopping areas.
-
The acquired land is in the heart of NOIDA, a major industrial and commercial city, and is close to Delhi.
-
Lands in nearby Sector 18 were acquired in 1976 for INR 7,200 to INR 10,200 per bigha, and plots were leased by NOIDA authorities in 1988 at much higher rates.
-
Bir Singh cannot be revisited as the Review and Curative Petitions against it have been dismissed.
-
Parity should be granted with Bir Singh, invoking Section 28A of the 1894 Act.
Submissions of the Parties
Main Submission | Sub-Submissions (NOIDA) | Sub-Submissions (Landowners) |
---|---|---|
Validity of Bir Singh Judgment |
|
|
Applicability of Section 28A |
|
|
Market Value of Land |
|
|
Maintainability of Miscellaneous Applications |
|
|
Issues Framed by the Supreme Court
The Supreme Court framed the following issues for deliberation:
- Should compensation be enhanced, and if so, to what extent? How should the quantum be calculated?
- Are the Miscellaneous Applications maintainable?
- Can the landowners rely upon Section 28A of the 1894 Act to seek parity with Bir Singh (supra)?
Treatment of the Issue by the Court
The following table demonstrates as to how the Court decided the issues:
Issue | Court’s Decision | Brief Reasons |
---|---|---|
Should compensation be enhanced, and if so, to what extent? How should the quantum be calculated? | Yes, compensation enhanced to INR 403 per sq. yd. | The Court applied the principle of guesstimation due to lack of direct evidence, considering various factors like land characteristics, potentiality, and market sentiment. |
Are the Miscellaneous Applications maintainable? | Yes, the Miscellaneous Applications are maintainable. | The Court invoked Article 142 of the Constitution to do complete justice, noting that denying the applications would be unfair and against the spirit of Article 14. |
Can the landowners rely upon Section 28A of the 1894 Act to seek parity with Bir Singh (supra)? | The issue was rendered academic. | The Court independently revised the compensation rate, making the reliance on Section 28A unnecessary. |
Authorities
The Supreme Court considered the following authorities:
Cases
Case Name | Court | How the authority was used |
---|---|---|
Ramsingbhai Jerambhai v. State of Gujarat (2018) 16 SCC 445 | Supreme Court of India | Cited by NOIDA to argue that Section 28A of the 1894 Act is restricted to compensation determined by the Reference Court. |
Administrator General of W.B. v. Collector, (1988) 2 SCC 150 | Supreme Court of India | Cited to support the relevance of sale exemplars in determining market value. |
Ram Kanwar v. State of Haryana, (2020) 17 SCC 232 | Supreme Court of India | Cited to support the relevance of sale exemplars in determining market value. |
Shaji Kuriakose v. Indian Oil Corpn. Ltd., (2001) 7 SCC 650 | Supreme Court of India | Cited for the criteria of comparability for sale deeds. |
ONGC Ltd. v. Rameshbhai Jivanbhai Patel, (2008) 14 SCC 745 | Supreme Court of India | Cited to highlight that prices of small plots cannot be the basis for evaluating larger tracts of land, and also to support the assumption of 15% annual growth in prices. |
Ravinder Kumar Goel v. State of Haryana and Others, 2023 SCC OnLine SC 147 | Supreme Court of India | Cited to support the consideration of sale exemplars of smaller parcels of land, subject to deductions. |
Atma Singh v. State of Haryana and others, (2008) 2 SCC 568 | Supreme Court of India | Cited for the reasoning behind applying cuts or deductions to smaller plots of land. |
Trishala Jain v. State of Uttaranchal, (2011) 6 SCC 47 | Supreme Court of India | Cited for the principle of guesstimation and its application. |
Krishan Kumar v. Union of India , (2015) 15 SCC 220 | Supreme Court of India | Cited to support the determination of compensation based on the circle rate after a marginal increase. |
State (NCT of Delhi) v. K.L. Rathi Steels Ltd., 2024 SCC OnLine SC 1090 | Supreme Court of India | Cited for the principle that Miscellaneous Applications based on change of law are not maintainable except in exceptional circumstances. |
Mewa Ram v. State of Haryana, (1986) 4 SCC 151 | Supreme Court of India | Cited for the objective of Section 28A of the 1894 Act. |
Babua Ram v. State of U.P, (1995) 2 SCC 689 | Supreme Court of India | Cited for the objective of Section 28A of the 1894 Act. |
Legal Provisions
Provision | Statute | Brief on the provision |
---|---|---|
Section 4(1) | Land Acquisition Act, 1894 | Provides for the issuance of a notification for the acquisition of land. |
Section 6 | Land Acquisition Act, 1894 | Allows for the declaration of intended acquisition. |
Section 17 | Land Acquisition Act, 1894 | Includes an urgency clause that allows for immediate possession of the land. |
Section 11 | Land Acquisition Act, 1894 | Deals with the Land Acquisition Officer (LAO) issuing an award, determining the compensation for the land. |
Section 18 | Land Acquisition Act, 1894 | Allows landowners to seek a reference to the Reference Court for enhancement of compensation. |
Section 23(1) | Land Acquisition Act, 1894 | Outlines the matters to be considered in determining compensation, primarily the market value of the land at the date of the Section 4(1) notification. |
Section 28A | Land Acquisition Act, 1894 | Allows landowners to seek redetermination of compensation if any other affected person receives enhanced compensation. |
Article 142 | Constitution of India | Grants the Supreme Court the power to do complete justice. |
Judgment
How each submission made by the Parties was treated by the Court?
Submission | Party | Court’s Treatment |
---|---|---|
Bir Singh judgment was based on a factual error. | NOIDA & Landowners | Acknowledged as a factual error but not revisited due to practical difficulties. |
Bir Singh judgment is not a precedent. | NOIDA | Agreed that it is not a binding precedent due to its specific factual context. |
Section 28A cannot be invoked. | NOIDA | Issue rendered academic as the Court independently revised the compensation. |
Sale deeds were of abadi land. | NOIDA | Disputed by landowners; Court relied on guesstimation due to lack of direct evidence. |
Compensation should not be based on current market value. | NOIDA | Court considered market value at the time of acquisition, factoring in potential appreciation. |
Miscellaneous Applications are not maintainable. | NOIDA | Rejected, Court invoked Article 142 to do complete justice. |
Compensation should be no less than Bir Singh rate. | Landowners | Partly accepted, compensation enhanced but not to the Bir Singh rate of INR 449 per sq. yd. |
Parity should be granted with Bir Singh. | Landowners | Issue rendered academic as the Court independently revised the compensation. |
Circle rate is a crucial piece of evidence. | Landowners | Considered as one of the factors in guesstimating compensation. |
How each authority was viewed by the Court?
The Court considered various authorities to arrive at its decision. Here’s how some of them were used:
- Ramsingbhai Jerambhai v. State of Gujarat (2018) 16 SCC 445:* Cited by NOIDA to argue against the applicability of Section 28A, but this argument was not upheld by the court.
- Administrator General of W.B. v. Collector, (1988) 2 SCC 150:* Used to support the importance of sale exemplars in determining market value.
- Ram Kanwar v. State of Haryana, (2020) 17 SCC 232:* Used to support the importance of sale exemplars in determining market value.
- Shaji Kuriakose v. Indian Oil Corpn. Ltd., (2001) 7 SCC 650:* Cited for the criteria of comparability for sale deeds.
- ONGC Ltd. v. Rameshbhai Jivanbhai Patel, (2008) 14 SCC 745:* Used to support the view that small plots cannot be the basis for valuing larger tracts and also to support the assumption of 15% annual growth in prices.
- Ravinder Kumar Goel v. State of Haryana and Others, 2023 SCC OnLine SC 147:* Used to support considering sale exemplars of smaller parcels of land, subject to deductions.
- Atma Singh v. State of Haryana and others, (2008) 2 SCC 568:* Used for the reasoning behind applying cuts or deductions to smaller plots of land.
- Trishala Jain v. State of Uttaranchal, (2011) 6 SCC 47:* Used to define the principle of guesstimation and its application.
- Krishan Kumar v. Union of India, (2015) 15 SCC 220:* Used to support the determination of compensation based on the circle rate after a marginal increase.
- State (NCT of Delhi) v. K.L. Rathi Steels Ltd., 2024 SCC OnLine SC 1090:* Used to highlight that Miscellaneous Applications based on change of law are not maintainable except in exceptional circumstances.
- Mewa Ram v. State of Haryana, (1986) 4 SCC 151:* Cited for the objective of Section 28A of the 1894 Act.
- Babua Ram v. State of U.P, (1995) 2 SCC 689:* Cited for the objective of Section 28A of the 1894 Act.
The Supreme Court, after considering all the facts, arguments, and legal precedents, arrived at the following decisions:
Final Decision
Ratio Decidendi
The ratio decidendi of the judgment can be summarized as follows:
- Guesstimation in Land Compensation: In the absence of direct evidence, the Court can use guesstimation to determine fair compensation, considering various factors like land characteristics, potentiality, and market sentiment.
- Power of the Supreme Court: The Supreme Court can invoke Article 142 of the Constitution to do complete justice, ensuring that no party suffers injustice due to technicalities or procedural delays.
- Fair Compensation: The principle of fair compensation cannot be sacrificed at the altar of procedure or technicalities.
- Section 28A and Parity: The Court’s decision to independently revise the compensation rate rendered the issue of Section 28A academic, highlighting that the Court will not let technicalities come in the way of doing complete justice.
Obiter Dicta
The obiter dicta in this judgment includes the following:
- Factual Errors in Precedent: The Court acknowledged that the judgment in Bir Singh was based on a factual error but did not revisit it due to practical difficulties and the principle of finality of judgments.
- Importance of Sale Exemplars: The Court reiterated the importance of sale exemplars in determining market value, but also acknowledged the limitations of relying on them when direct evidence is lacking.
- Relevance of Circle Rates: The Court acknowledged the relevance of circle rates but emphasized that they are not the sole determinants of market value.
- Need for Uniform Compensation: The Court emphasized that a uniform rate of compensation should be fixed for the entire acquisition, rather than individual rates for different parcels of land.
Flowchart of the Case
Compensation Ratio
The following table illustrates the compensation awarded at different stages:
Stage | Compensation (INR per sq. yd.) |
---|---|
Land Acquisition Officer (LAO) Award | 110 |
Reference Court | 222-233 |
High Court (Initial) | 297.50/340 |
Supreme Court (Bir Singh) | 449 |
Supreme Court (Present Case) | 403 |
Conclusion
In the case of New Okhla Industrial Development Authority vs. Harnand Singh (Deceased) through LRs, the Supreme Court enhanced the compensation for land acquisition to INR 403 per sq. yd., using the principle of guesstimation. The Court invoked Article 142 to ensure complete justice, highlighting the importance of fair compensation over procedural technicalities. This judgment provides valuable insights into the complexities of land acquisition and the determination of fair compensation.