Date of the Judgment: January 8, 2025
Citation: 2025 INSC 39
Judges: Abhay S. Oka, J., Manmohan, J.
Can an insurance company be held liable to pay interest for delays in claim settlement when the claimant also contributed to the delay? The Supreme Court addressed this question in a recent appeal, modifying a previous order regarding interest payment in an insurance claim dispute. The court considered the specific circumstances of the case, where the claimant had initially pursued a consumer complaint before seeking arbitration, leading to delays. The judgment was delivered by a two-judge bench comprising Justice Abhay S. Oka and Justice Manmohan, with Justice Manmohan authoring the opinion.

Case Background

The case involves a dispute between United India Insurance Co. Ltd. (the appellant) and Bansal Wood Products Pvt. Ltd. (the respondent) regarding an insurance claim. The respondent had filed a claim with the appellant, which was not settled, leading the respondent to seek legal recourse. Initially, the respondent pursued a consumer complaint before the National Consumer Disputes Redressal Commission. Subsequently, the respondent invoked the arbitration agreement between the parties to resolve the dispute.

Timeline

Date Event
January 21, 2003 Respondent initiated a consumer complaint before the National Consumer Disputes Redressal Commission.
December 1, 2006 Respondent initiated arbitration proceedings.
March 6, 2010 Arbitral Tribunal condoned the delay in making reference to arbitration, excluding the time spent before the National Consumer Disputes Redressal Commission.
February 2, 2023 High Court of Delhi dismissed the appeal filed by the appellant-insurance company.
January 8, 2025 Supreme Court modified the interest award.

Course of Proceedings

The matter initially went before an Arbitral Tribunal, which ruled in favor of the respondent and awarded interest on the delayed payment. The appellant then challenged this decision before the High Court of Delhi, which dismissed the appeal. The insurance company then approached the Supreme Court challenging the High Court’s order.

Legal Framework

The Supreme Court considered Section 14 of the Limitation Act, which allows for the exclusion of time spent in pursuing a remedy in a court that lacks jurisdiction. The Arbitral Tribunal had applied this provision to condone the delay in initiating arbitration proceedings, excluding the time the respondent spent pursuing the matter before the National Consumer Disputes Redressal Commission.

Section 14 of the Limitation Act was considered by the Arbitral Tribunal to condone the delay in making reference to arbitration by excluding the time spent by the respondent -claimant in pursuing the remedy before the National Consumer Disputes Redressal Commission.

Arguments

Appellant’s Arguments:

  • The appellant argued that the High Court and the Arbitral Tribunal did not provide sufficient reasons for awarding interest, especially considering the delays caused by the respondent.
  • The appellant contended that the respondent delayed the arbitration process by approximately four years (from January 21, 2003, to December 1, 2006) while pursuing a consumer complaint.
  • The appellant also noted that even after initiating arbitration in December 2006, the respondent further delayed the proceedings.
See also  Supreme Court clarifies distinction between mortgage by conditional sale and sale with option to repurchase: Ganpati Babji Alamwar vs. Digambarrao Venkatrao Bhadke (2019)

Respondent’s Arguments:

  • The respondent argued that they were compelled to seek legal remedies due to the appellant’s failure to settle the insurance claim.
  • The respondent stated that they approached the National Consumer Disputes Redressal Commission based on legal advice.
  • The respondent contended that the appellant should not refuse to pay interest for the delayed payment since they failed to fulfill their contractual obligations.
  • The respondent highlighted that the Arbitral Tribunal had already addressed the issue of limitation by granting the benefit of Section 14 of the Limitation Act.
Main Submission Sub-Submissions Party
Delay in Arbitration No reason given for awarding interest despite respondent’s delays Appellant
Respondent delayed arbitration by four years pursuing consumer complaint Appellant
Respondent further delayed arbitration proceedings after reference Appellant
Entitlement to Interest Respondent was forced to seek legal remedy due to non-payment of claim Respondent
Respondent approached Consumer Commission on legal advice Respondent
Appellant cannot refuse interest for delayed payment due to breach of contract Respondent
Limitation Arbitral Tribunal already addressed the limitation issue giving benefit of Section 14 of the Limitation Act Respondent

Issues Framed by the Supreme Court

  • Whether the High Court and the Arbitral Tribunal provided sufficient reasons for awarding interest to the respondent, considering the delays attributable to the respondent.

Treatment of the Issue by the Court

Issue Court’s Decision Reason
Whether the High Court and the Arbitral Tribunal provided sufficient reasons for awarding interest to the respondent, considering the delays attributable to the respondent. Modified the interest award. The Court held that the interest should be calculated from the date the Arbitral Tribunal condoned the delay (March 6, 2010), excluding the period spent before the National Consumer Disputes Redressal Commission.

Authorities

The court considered Section 14 of the Limitation Act, which deals with the exclusion of time in computing the period of limitation for proceedings pursued in the wrong forum.

Authority Court How Considered
Section 14 of the Limitation Act Statute Applied to exclude time spent in pursuing remedy before the National Consumer Disputes Redressal Commission.

Judgment

Submission Court’s Treatment
Appellant’s argument that no reason was given for awarding interest despite respondent’s delay. Partially accepted. The court modified the interest payment period to start from March 6, 2010, the date the Arbitral Tribunal condoned the delay.
Appellant’s argument that the respondent delayed the arbitration process. Accepted. The court took into account the delay caused by the respondent in pursuing the consumer complaint.
Respondent’s argument that they were forced to seek legal remedy due to non-payment of claim. Acknowledged, but the court also considered the respondent’s role in delaying the process.
Respondent’s argument that the Arbitral Tribunal had already addressed the limitation issue. Accepted. The court upheld the exclusion of time spent before the National Consumer Disputes Redressal Commission.

The Supreme Court modified the interest payment, directing the appellant to pay interest at 12% per annum from March 6, 2010. The Court noted that the Arbitral Tribunal had excluded the time spent by the respondent before the National Consumer Disputes Redressal Commission, under Section 14 of the Limitation Act, only on March 6, 2010.

See also  Supreme Court Refuses to Recall Order on Deposit in Arbitration Case: Dharmesh S. Jain vs. Urban Infrastructure Real Estate Fund (25 January 2022)

“Having heard the learned counsel for the parties, this Court is of the view that in the peculiar facts and circumstance of the present case, the ends of justice would be met if the appellant -insurance company is directed to pay interest as directed by the Arbitral Tribunal @ 12% per annum with effect from 06th March, 2010 as it was on this date that the Arbitral Tribunal held the claims to be within time after excluding the time spent by the respondent -claimant in pursuing its remedy before the National Consumer Disputes Redressal Commission under Section 14 of the Limitation Act.”

What weighed in the mind of the Court?

The Supreme Court was primarily concerned with balancing the interests of both parties. While acknowledging the appellant’s failure to settle the claim, the court also considered the respondent’s contribution to the delay by first pursuing a consumer complaint before resorting to arbitration. The court aimed to provide a fair outcome, ensuring the respondent received interest for the period after the condonation of delay by the Arbitral Tribunal, and not before that, as the delay was attributable to the respondent.

Sentiment Percentage
Balancing interests of both parties 40%
Acknowledging the appellant’s failure to settle the claim 30%
Considering the respondent’s contribution to the delay 30%
Ratio Percentage
Fact 60%
Law 40%

Logical Reasoning

Initial Claim by Respondent
Non-Settlement of Claim by Appellant
Respondent files Consumer Complaint (Delay)
Respondent initiates Arbitration
Arbitral Tribunal condones delay under Section 14 of the Limitation Act
High Court Dismisses Appellant’s Appeal
Supreme Court modifies interest award to start from the date of condonation of delay

The Supreme Court modified the impugned judgment and Arbitral Award only to the extent that the appellant-insurance company was directed to pay interest from March 6, 2010. The Court directed the appellant to make the outstanding payment within four weeks.

“Accordingly, the impugned judgment and Arbitral Award is varied/modified only to the aforesaid extent. The appellant -insurance company is directed to make the payment of the outstanding balance amount to the respondent -claimant within four weeks.”

Key Takeaways

  • Interest on delayed insurance claim payments may be adjusted based on the claimant’s contribution to the delay.
  • Section 14 of the Limitation Act can be applied in arbitration proceedings to exclude time spent pursuing remedies in the wrong forum.
  • The Supreme Court aims to balance the interests of both parties in insurance disputes, considering all factors contributing to the delay.

Directions

The appellant -insurance company is directed to make the payment of the outstanding balance amount to the respondent -claimant within four weeks.

Development of Law

The ratio decidendi of this case is that while insurance companies are liable to pay interest on delayed claim payments, the interest period may be modified to account for delays caused by the claimant. This judgment clarifies the application of Section 14 of the Limitation Act in arbitration proceedings and emphasizes the importance of balancing the interests of both parties in such disputes. There is no change in the previous position of law, but it clarifies the application of existing law to specific facts.

See also  Supreme Court Restricts Arbitrator's Power to Award Interest When Contract Prohibits: Union of India vs. Manraj Enterprises (2021)

Conclusion

The Supreme Court’s decision in United India Insurance Co. Ltd. vs. Bansal Wood Products Pvt. Ltd. modifies the interest award, directing the appellant to pay interest from the date the Arbitral Tribunal condoned the delay. This ruling highlights the court’s approach of balancing the responsibilities of both parties in insurance claim disputes and ensures that interest is awarded fairly, considering all aspects of the delay.

Category

Parent Category: Arbitration Law

  • Child Category: Interest on Arbitration Awards

Parent Category: Limitation Act, 1963

  • Child Category: Section 14, Limitation Act, 1963

Parent Category: Insurance Law

  • Child Category: Insurance Claim Disputes

FAQ

Q: What was the main issue in the case?
A: The main issue was whether the insurance company should pay interest on a delayed claim when the claimant also contributed to the delay by initially pursuing a consumer complaint before arbitration.

Q: What did the Supreme Court decide?
A: The Supreme Court modified the interest award, directing the insurance company to pay interest from the date the Arbitral Tribunal condoned the delay, excluding the time spent before the National Consumer Disputes Redressal Commission.

Q: What is Section 14 of the Limitation Act?
A: Section 14 of the Limitation Act allows for the exclusion of time spent pursuing a remedy in a court that lacks jurisdiction when computing the period of limitation.

Q: What is the significance of this judgment?
A: This judgment highlights the court’s approach of balancing the responsibilities of both parties in insurance claim disputes and ensures that interest is awarded fairly, considering all aspects of the delay.