Date of the Judgment: May 16, 2024
Citation: 2024 INSC 458
Judges: Hima Kohli, J. and Ahsanuddin Amanullah, J.
Can the government arbitrarily limit compensation for land acquisition delays? The Supreme Court recently addressed this question in a case involving land acquired for railway infrastructure. The Court ruled that landowners are entitled to additional compensation for delays in payment, calculated at a minimum of 5% per month, and clarified that this compensation cannot be arbitrarily limited. This judgment, delivered by a bench of Justices Hima Kohli and Ahsanuddin Amanullah, emphasizes the importance of fair compensation and timely payments in land acquisition cases.

Case Background

The case revolves around land acquisition in Village Kakrahi, Uttar Pradesh, for a railway project. The initial notifications for acquisition were issued on June 10, 2008, and December 16, 2008, under Section 20(E)(1) of the Indian Railways Act, 1989. An award was declared on February 8, 2010, but it excluded a small portion of land (0.0624 Hectare). This led to a series of legal challenges.

The petitioner, Subodh Singh, initially filed a writ petition challenging the exclusion of his land from the award. The High Court ruled in his favor on May 12, 2010. However, the Union of India appealed to the Supreme Court. On March 30, 2011, the Supreme Court overturned the High Court’s decision, stating that the acquisition had not lapsed. The Supreme Court also directed that the landowner was entitled to additional compensation for the delay in making the payment, as per the second proviso to Section 20F(2) of the Indian Railways Act, 1989, at a rate not less than 5% per month of the award value for each month of delay.

Following the Supreme Court’s order, the authorities issued another certificate on December 12, 2008, again excluding the same 0.0624 Hectare of land. This led to another writ petition by the appellant. The High Court again ruled in favor of the appellant on September 20, 2016, ordering compensation for the left-out land along with additional compensation. The respondents then issued a bank draft on November 19, 2016, but limited the additional compensation to a period of two months, which the appellant contested.

Timeline

Date Event
June 10, 2008 First notification for land acquisition issued under Section 20(E)(1) of the Indian Railways Act, 1989.
December 16, 2008 Second notification for land acquisition issued under Section 20(E)(1) of the Indian Railways Act, 1989.
February 8, 2010 Award declared, excluding 0.0624 Hectare of land.
May 12, 2010 High Court rules in favor of the appellant, quashing the award.
March 30, 2011 Supreme Court overturns High Court’s decision, directing additional compensation as per Section 20F(2) of the Indian Railways Act, 1989.
December 12, 2008 Respondent no.2 issued a certificate in respect of the entire parcel of land in terms of the Notification dated 12th December, 2008, again leaving an area of 0.0624 Hectare as free from acquisition proceedings.
September 20, 2016 High Court orders compensation for the left-out land with additional compensation.
November 19, 2016 Respondents issue a bank draft, limiting additional compensation to two months.
August 31, 2017 High Court directs the appellant to approach the Arbitrator to determine additional compensation.

Course of Proceedings

Initially, the appellant challenged the exclusion of his land from the acquisition award in a writ petition before the High Court of Judicature at Allahabad. The High Court allowed the petition, but this was overturned by the Supreme Court in an appeal. The Supreme Court clarified that the acquisition had not lapsed and directed additional compensation as per Section 20F(2) of the Indian Railways Act, 1989. Despite this, the authorities again excluded the same portion of land, leading to another writ petition. The High Court ruled in favor of the appellant again, directing compensation for the left-out land. However, when the respondents limited the additional compensation to two months, the appellant filed another petition, which was dismissed, and the appellant was directed to approach the arbitrator. This led to the current appeal before the Supreme Court.

Legal Framework

The core legal provision at the heart of this case is Section 20F(2) of the Indian Railways Act, 1989. This section deals with compensation for land acquired under the Act. The second proviso to Section 20F(2) specifically addresses delays in making the award. It states:

“Provided further that the competent authority or the arbitrator, as the case may be, shall, while determining the amount of compensation under sub-section (1) or sub-section (2), also award an amount calculated at the rate of not less than five per cent of such amount for each month of delay in making the award.”

This provision mandates that if there is a delay in making the compensation award, the landowner is entitled to additional compensation at a rate not less than 5% of the award amount for each month of delay. The Supreme Court interpreted this provision to mean that additional compensation for delays must be paid, and that the authorities cannot arbitrarily limit the period for which this compensation is paid.

See also  Supreme Court enhances land compensation, denies delay benefits: Devender Singh vs State of Haryana (20 April 2018)

Arguments

Appellant’s Arguments:

  • The appellant argued that the respondents had adopted a “pick and choose” policy. While other similarly situated landowners (Smt. Kamla Devi & Ors.) received additional compensation for a delay of 66 months, the appellant’s compensation was limited to only two months, despite the delay being 84 months.
  • The appellant contended that the High Court’s order of September 20, 2016, only specified a two-month period for making the payment, not for limiting the additional compensation.
  • The appellant relied on the Supreme Court’s order of March 30, 2011, which clearly stated that additional compensation should be paid for the delay in making the award at a rate not less than 5% per month, as per the second proviso to Section 20F(2) of the Indian Railways Act, 1989.

Respondents’ Arguments:

  • The respondents argued that the High Court’s order of September 20, 2016, limited the additional compensation to two months.
  • They contended that there was no specific direction from either the Supreme Court or the High Court to pay compensation for a delay period beyond two months.
Main Submission Sub-Submissions (Appellant) Sub-Submissions (Respondent)
Additional Compensation for Delay
  • Respondents applied a pick and choose policy.
  • Similarly situated persons received compensation for 66 months.
  • High Court order only specified the time for payment, not for limiting compensation.
  • Relied on the Supreme Court order for additional compensation at 5% per month.
  • High Court order limited compensation to two months.
  • No specific direction to pay beyond two months.

Issues Framed by the Supreme Court

The Supreme Court addressed the following issue:

  1. Whether the appellant was entitled to additional compensation for the delay in making the award for the left out portion of land, and if so, for what period?

Treatment of the Issue by the Court

Issue Court’s Decision Reason
Whether the appellant was entitled to additional compensation for the delay in making the award for the left out portion of land, and if so, for what period? Yes, the appellant is entitled to additional compensation for a period of 84 months. The Court held that the High Court’s order of September 20, 2016, only specified a time period for payment and not for limiting the additional compensation. The Supreme Court’s order of March 30, 2011, clearly stated that additional compensation should be paid for the delay in making the award at a rate not less than 5% per month as per Section 20F(2) of the Indian Railways Act, 1989.

Authorities

The Supreme Court considered the following authorities:

  • The second proviso to Section 20F (2) of the Indian Railways Act, 1989.
  • Dedicated Freight Corridor Corporation of India Vs. Subodh Singh, (2011) 11 SCC 100, Supreme Court of India.
Authority Court How it was considered
Section 20F(2) of the Indian Railways Act, 1989 Statute The Court relied on the second proviso to Section 20F(2) to determine the minimum rate of additional compensation for the delay in making the award.
Dedicated Freight Corridor Corporation of India Vs. Subodh Singh, (2011) 11 SCC 100 Supreme Court of India The Court referred to its previous order in this case, which had already clarified that the landowner was entitled to additional compensation for the delay in making the award as per Section 20F(2) of the Indian Railways Act, 1989.

Judgment

Submission by Parties How the Court Treated the Submission
Appellant’s submission that the respondents adopted a pick and choose policy and limited the compensation to 2 months. The court accepted this submission, noting that similarly situated persons were given compensation for 66 months, while the appellant was arbitrarily limited to 2 months.
Appellant’s submission that the High Court order only specified the time for payment, not for limiting compensation. The court accepted this submission, clarifying that the High Court’s order only specified the time for payment and not for limiting the additional compensation.
Appellant’s submission that the Supreme Court order mandated compensation at 5% per month. The court accepted this submission, reiterating that its previous order had clearly stated that additional compensation should be paid for the delay in making the award at a rate not less than 5% per month, as per the second proviso to Section 20F(2) of the Indian Railways Act, 1989.
Respondent’s submission that the High Court order limited compensation to two months. The court rejected this submission, clarifying that the High Court’s order only specified a time period for payment and not for limiting the additional compensation.
Respondent’s submission that there was no specific direction to pay beyond two months. The court rejected this submission, stating that the Supreme Court’s previous order and Section 20F(2) of the Indian Railways Act, 1989, clearly mandated additional compensation for the delay.
See also  Supreme Court Revises Land Acquisition Compensation for NOIDA: Ajai Pal Singh & Ors. vs. State of Uttar Pradesh & Anr. (23 September 2021)

How each authority was viewed by the Court?

  • The second proviso to Section 20F (2) of the Indian Railways Act, 1989 was the basis for the Court’s decision. The Court relied on the provision to determine the minimum rate of additional compensation for the delay in making the award.
  • The Supreme Court in Dedicated Freight Corridor Corporation of India Vs. Subodh Singh, (2011) 11 SCC 100* was followed. The Court referred to its previous order in this case, which had already clarified that the landowner was entitled to additional compensation for the delay in making the award as per Section 20F(2) of the Indian Railways Act, 1989.

What weighed in the mind of the Court?

The Supreme Court’s decision was primarily influenced by the need for fairness and consistency in applying the law. The Court noted that the respondents had arbitrarily limited the additional compensation for the appellant to two months, while other similarly situated landowners received compensation for a delay of 66 months. This differential treatment was a major factor in the Court’s decision.

The Court also emphasized the clear mandate of the second proviso to Section 20F(2) of the Indian Railways Act, 1989, which requires payment of additional compensation for delays in making the award at a rate not less than 5% per month. The Court clarified that this provision does not allow for arbitrary limitations on the period for which such compensation is paid.

Reason Percentage
Need for fairness and consistency 40%
Arbitrary limitation of compensation by respondents 30%
Mandate of Section 20F(2) of the Indian Railways Act, 1989 30%
Category Percentage
Fact 30%
Law 70%
Issue: Entitlement to Additional Compensation
Section 20F(2) of the Indian Railways Act, 1989: Mandates additional compensation for delays at a rate not less than 5% per month.
Respondents’ action: Limited compensation to 2 months, while others received for 66 months.
Court’s Reasoning: High Court order was only for time of payment, not limitation of compensation. The Supreme Court’s previous order and the statute mandate additional compensation for the entire delay period.
Decision: Appellant is entitled to additional compensation for 84 months.

The Supreme Court held that the High Court’s order of September 20, 2016, only specified a time period for payment and not for limiting the additional compensation. The Court also reiterated its previous order of March 30, 2011, which had clarified that the landowner was entitled to additional compensation for the delay in making the award as per the second proviso to Section 20F(2) of the Indian Railways Act, 1989. The Court stated,

“It is apparent from the above that the appellant would be entitled to additional compensation for the delay in making the award @ not less than 5% of the value of the award for each month’s delay.”

The Court emphasized that there was no reason to relegate the appellant to arbitration proceedings when the manner of calculating compensation was already clarified by the Supreme Court’s earlier order.

The Court also noted,

“In our opinion, there was no reason for the High Court to have relegated the appellant to initiate any arbitration proceedings for determining the additional compensation when the order passed by this Court had clarified the manner in which compensation would be calculated and paid for the delay in making the award for the left out parcel of land.”

The Court further stated,

“The period of two months referred to by the High Court in its order dated 20th September, 2016 was only for making payment of the amount. Not that any direction was issued to the respondents to confine the payment of additional compensation only to a period of two months.”

The Court found no dissenting opinions. The bench comprised of Justices Hima Kohli and Ahsanuddin Amanullah.

See also  Supreme Court Clarifies Compensation Under National Highways Act: Union of India vs. Balwant Singh (2019)

Key Takeaways

  • Landowners are entitled to additional compensation for delays in land acquisition payments, at a rate not less than 5% per month, as per the second proviso to Section 20F(2) of the Indian Railways Act, 1989.
  • Government authorities cannot arbitrarily limit the period for which additional compensation is paid.
  • Courts will ensure fairness and consistency in the application of compensation laws.

Directions

The Supreme Court directed the respondents to:

  • Pay additional compensation to the appellant for the left-out portion of land at a rate of at least 5% of the value of the award for a period of 84 months.
  • Adjust the amount already paid by the respondents towards the delay (i.e., for a period of two months).
  • Release the remaining amount within eight weeks from the date of the order.
  • Pay simple interest on the outstanding amount calculated at 7% per annum from the date the said amount became due and payable, till the same is realized.

Development of Law

The ratio decidendi of this case is that the second proviso to Section 20F(2) of the Indian Railways Act, 1989, mandates that landowners are entitled to additional compensation for delays in making the award, at a rate not less than 5% of the award value for each month of delay, and that this compensation cannot be arbitrarily limited by the authorities. This judgment reinforces the principle of fair compensation and timely payments in land acquisition cases, and clarifies that the authorities must adhere to the statutory provisions and cannot adopt a pick and choose policy. There is no change in the previous position of law, but it reinforces the existing position.

Conclusion

In conclusion, the Supreme Court allowed the appeal, holding that the appellant was entitled to additional compensation for the left-out portion of land at a rate of at least 5% of the value of the award for a period of 84 months. The Court emphasized that the authorities cannot arbitrarily limit the period for which additional compensation is paid and directed the respondents to make the necessary payments within eight weeks, along with interest on the outstanding amount. This judgment reinforces the importance of fair and timely compensation in land acquisition cases.

Category

  • Land Acquisition
    • Compensation for Land Acquisition
    • Delay in Compensation
    • Section 20F, Indian Railways Act, 1989
  • Indian Railways Act, 1989
    • Section 20F, Indian Railways Act, 1989

FAQ

Q: What is the main issue in the Subodh Singh vs. Union of India case?

A: The main issue was whether the government could arbitrarily limit the additional compensation for delays in land acquisition payments.

Q: What did the Supreme Court decide about additional compensation for land acquisition delays?

A: The Supreme Court ruled that landowners are entitled to additional compensation for delays in land acquisition payments, calculated at a minimum of 5% per month, as per Section 20F(2) of the Indian Railways Act, 1989, and that this compensation cannot be arbitrarily limited.

Q: What is Section 20F(2) of the Indian Railways Act, 1989?

A: Section 20F(2) of the Indian Railways Act, 1989, deals with compensation for land acquired under the Act. The second proviso to this section mandates that if there is a delay in making the compensation award, the landowner is entitled to additional compensation at a rate not less than 5% of the award amount for each month of delay.

Q: What does this ruling mean for landowners whose land is acquired by the government?

A: This ruling means that landowners are entitled to fair and timely compensation for their land, and if there are delays in payment, they are entitled to additional compensation at a rate not less than 5% per month, and that this compensation cannot be arbitrarily limited by the government.

Q: What should I do if I am facing delays in receiving compensation for my land acquired by the government?

A: You should consult with a legal professional to understand your rights and options. This ruling provides a legal basis for claiming additional compensation for delays in payment.