LEGAL ISSUE: The core legal issue revolves around the enforcement of a consent order regarding the payment of debt due to lenders following the termination of concession agreements for the Rapid Metro project in Gurgaon.

CASE TYPE: This case falls under the ambit of civil law, specifically concerning contractual disputes and enforcement of court orders in the context of infrastructure projects.

Case Name: Rapid MetroRail Gurgaon Limited Etc. vs. Haryana Mass Rapid Transport Corporation Limited & Ors.

Judgment Date: 26 March 2021

Introduction

Date of the Judgment: 26 March 2021

Citation: 2021 INSC 178

Judges: Dr. Justice Dhananjaya Y Chandrachud, J, M R Shah, J, and Sanjiv Khanna, J. This was a unanimous decision by a three-judge bench.

Can a state entity avoid its financial obligations under a consent order, especially when it involves public funds and infrastructure projects? The Supreme Court of India recently addressed this critical question in a dispute concerning the Rapid Metro project in Gurgaon. The core issue was whether the Haryana Mass Rapid Transport Corporation Limited (HMRTC) and Haryana Shehri Vikas Pradhikaran (HSVP) were obligated to deposit 80% of the debt due to the lenders of the Rapid Metro project, as determined by an audit, following the termination of the concession agreements.

Case Background

In 2008, HSVP initiated a project for a metro rail link in Gurgaon. A consortium led by IL&FS Rail Limited (IRL) won the bid. This led to the incorporation of Rapid MetroRail Gurgaon Limited (RMGL) which entered into a concession agreement with HSVP on 9 December 2009 for Project No. 1. A similar process occurred in 2012 for Project No. 2, with Rapid MetroRail Gurgaon South Limited (RMGSL) being incorporated and a concession agreement signed on 3 January 2013. RMGL completed Project No. 1 on 14 November 2013, and RMGSL completed Project No. 2 on 31 March 2017. In 2014, the Haryana government mandated that all metro projects would be handled by HMRTC.

In 2018, RMGL and RMGSL issued notices to HSVP alleging breaches of the concession agreements. Subsequently, the Union of India filed a petition against IL&FS, the parent company of RMGL and RMGSL, due to concerns of mismanagement. This led to the supersession of the IL&FS board and the appointment of a new board. In 2019, both RMGL and RMGSL issued termination notices for their respective concession agreements. HSVP also issued termination notices to RMGL and RMGSL. The matter reached the High Court of Punjab and Haryana, where a consent order was eventually passed.

Timeline

Date Event
2008 HSVP issues RFQ/RFP for developing a metro rail link (Project No 1).
1 December 2008 Consortium Agreement between IRL, ITNL and DLF Metro Limited
16 July 2009 HSVP issues letter of award to the consortium.
9 December 2009 HSVP enters into a Concession Agreement with RMGL for Project No 1.
2012 HSVP issues another RFQ/RFP for developing a metro rail link (Project No 2).
25 April 2012 IRL and ITNL enter into a consortium arrangement.
1 October 2012 HSVP issues a letter of award to the consortium for Project No 2.
3 January 2013 Concession Agreement between HSVP and RMGSL for Project No 2.
14 November 2013 RMGL completes Project No 1.
11 January 2014 Haryana Government directs that all metro projects be handled by HMRTC.
31 March 2017 RMGSL completes Project No 2.
17 July 2018 RMGL and RMGSL issue notices to HSVP alleging material breaches.
1 October 2018 Union of India files a petition against IL&FS NCLT supersedes the IL&FS Board.
4 February 2019 NCLAT appoints Justice D K Jain to supervise the resolution process for the IL&FS group.
7 June 2019 RMGL and RMGSL issue notices of termination to HSVP.
26 June 2019 RMGL informs HSVP that divestment requirements are completed.
1 August 2019 RMGL informs HSVP about the completion of handover formalities.
8 August 2019 NCLAT issues directions for “red” category entities of IL&FS group.
19 August 2019 RMGL seeks approval from Justice D K Jain for handover of Project No 1.
26 August 2019 HSVP issues termination notices to RMGL and RMGSL.
6 September 2019 Justice D K Jain permits RMGL and RMGSL to handover possession of the projects.
6 September 2019 HMRTC and HSVP file writ petitions in the High Court challenging the termination notices.
6 September 2019 High Court directs operation of Rapid Metro to continue until midnight of 9 September 2019.
9 September 2019 High Court extends interim order until 17 September 2019.
18 September 2019 RMGL/RMGSL propose to operate metro for 30 days, subject to debt determination and deposit.
20 September 2019 High Court passes consent order for CAG audit and deposit of 80% debt due.
4 October 2019 High Court modifies the consent order.
15 October 2019 High Court allows extension of 7 days for implementation of directions.
19 November 2019 CAG presents statement on the scope of the audit.
25 June 2020 CAG files compliance affidavit stating it had appointed a firm of chartered accountants for financial audit.
18 August 2020 RMGL and RMGSL file application for opening the CAG report and directing deposit of 80% of debt due.
2 September 2020 High Court issues notice on the application filed by the appellants.
28 September 2020 High Court opens the sealed cover and takes the CAG report on record.
10 October 2020 HMRTC files an affidavit objecting to the audit report.
28 October 2020 CAG files an affidavit in response to the objections raised by HMRTC.
12 October 2020 High Court notes HMRTC’s affidavit and adjourns the hearing.
16 December 2020 High Court defers hearing to 8 April 2021.
5 February 2021 Supreme Court issues notice on the special leave petitions filed by the appellants.
26 March 2021 Supreme Court disposes of the appeals, ordering the deposit of 80% of the debt due.
See also  Supreme Court Orders Full Insurance Claim for Fire Damage: M/s Super Label Mfg. Co. vs. New India Assurance Company Limited (2023)

Course of Proceedings

The High Court of Punjab and Haryana initially intervened to prevent the disruption of metro services, directing the continuation of operations by the appellants. Subsequently, the High Court facilitated negotiations between the parties, leading to a consent order on 20 September 2019. This order mandated a financial audit by the Comptroller and Auditor General (CAG) to determine the debt due and stipulated that 80% of the debt was to be deposited in an escrow account. The High Court also addressed the issue of the validity of the termination notices and the claims of the parties, directing that the same shall be decided by arbitration.

Despite the consent order and the subsequent audit report, HMRTC raised objections, claiming the audit was incomplete. The High Court, however, did not enforce the deposit of funds, leading to the appellants filing Special Leave Petitions before the Supreme Court.

Legal Framework

The judgment primarily revolves around the interpretation and enforcement of the Concession Agreements between HSVP and RMGL/RMGSL. Key provisions include:

  • Article 1.1 of the Concession Agreement dated 9 December 2009: Defines “Debt Due” as

    “the aggregate of the following sums expressed in Indian Rupees outstanding on the Transfer Date: (a) the principal amount of the debt provided by the Senior Lenders under the Financing Agreements for financing the Total Project Cost (the “Principal”) but excluding any part of the Principal that had fallen due for repayment two years prior to the Termination Date; (b) all accrued interest, financing fees and charges payable under the Financing Agreements on, or in respect of, the debt referred to in Sub- clause (a) above until the Transfer Date but excluding (i) any interest, fees or charges that had fallen due one year prior to the Transfer Date, (ii) any penal interest or charges payable under Financing Agreements to any Senior Lender, and (iii) any pre- payment charges in relation to accelerated repayment of debt except where such charges have arisen due to Authority Default; and (c) any Subordin ated Debt and all accrued interest thereon, which is included in the Financial Package and disbursed by Lenders for financing the Total Project Cost as per the Financing Documents.”
  • Article 18 of the Concession Agreement dated 9 December 2009: Details the establishment and operation of the Escrow Account, where all funds related to the project are to be deposited and disbursed.
  • Article 24.4 of the Concession Agreement dated 9 December 2009: Specifies that upon termination by HUDA (now HSVP) due to a concessionaire event of default, HUDA shall pay the lenders 80% of the debt due as termination payment.

    “Upon Termination by HUDA on account of occurrence of Concessionaire Event of Default during the Operations Period, the HUDA shall take over the complete system (all Project Assets), HUDA shall pay the Lenders of the Project, as per financial documents, an amount equal to 80% of debt “due, as Termination payment. No termination payment shall be due or payable on account of Concessionaire’s default occurring prior to COD.”
  • Article 24.5.2 of the Concession Agreement dated 9 December 2009: Outlines the consequences of termination by the concessionaire due to a default by HUDA, entitling the concessionaire to receive the debt due and 110% of the adjusted equity.

    “Upon Termination by the Concessionaire on account of an HUDA Event of Default, HUDA shall take over the complete system (all Project Assets) and the Concessionaire shalt be entitled to receive from HUDA by way of Termination Payment a sum equal to : (a) Debt due (b) 110% of the Adjusted Equity”
  • Article 30.2 of the Concession Agreement dated 9 December 2009: Contains the arbitration agreement for resolving disputes.

    “Disputes or differences shall be due for arbitration only if all the conditions in Sub-Article 30.1 are fulfilled.”
  • Section 241(2) and 242 of the Companies Act, 2013: Under which the Union of India filed a petition against IL&FS, leading to the supersession of its board.

Arguments

Arguments by RMGL and RMGSL (Appellants):

  • ✓ The consent order of the High Court dated 20 September 2019 was a binding agreement, requiring HSVP to deposit 80% of the debt due as determined by the CAG.
  • ✓ The appointment of the CAG was to determine the debt due as per the Concession Agreements, and the CAG’s report was final for the purposes of the deposit.
  • ✓ The termination of the agreements triggered the obligation to pay 80% of the debt due to protect the interests of the lenders.
  • ✓ The appellants had handed over the projects to HMRTC, and the deposit was essential to secure the dues of the banks and financial institutions.
  • ✓ The High Court could not reopen the terms of a consent order.
  • ✓ The CAG had clarified that the audit was complete and conclusive, and the objections raised by HMRTC were without substance.
  • ✓ The FIR against the IL&FS group could not be a reason to avoid the contractual obligation to deposit 80% of the debt due.

Arguments by HMRTC and HSVP (Respondents):

  • ✓ Investigations were underway against the IL&FS group, and RMGL/RMGSL were classified as ‘red entities’.
  • ✓ There were allegations of fake invoices and inflated project costs against RMGL/RMGSL.
  • ✓ The CAG’s audit was limited and did not consider all relevant factors, making the audit incomplete and inconclusive.
  • ✓ The audit report itself admitted that other matters could have a significant impact on the debt due.
  • ✓ The High Court was the appropriate forum to decide the objections raised against the audit report.

Arguments by Andhra Bank and Canara Bank (Financial Institutions):

  • ✓ The banks had provided substantial financial facilities for the projects, and the deposit of 80% of the debt due was essential to secure their interests.
  • ✓ The Escrow Account was specifically created to protect the lenders, and the deposit was necessary to ensure the recovery of their dues.
  • ✓ The projects were completed using funds from the lenders, who were the biggest stakeholders.
  • ✓ The amount deposited would be subject to the orders of the NCLAT, ensuring the funds were secure.
See also  Supreme Court Upholds Conviction in Homicidal Death Case: Nawab vs. State of Uttarakhand (22 January 2020)

Submissions Table

Main Submission Sub-Submissions (Appellants – RMGL/RMGSL) Sub-Submissions (Respondents – HMRTC/HSVP) Sub-Submissions (Financial Institutions – Andhra/Canara Bank)
Enforceability of Consent Order
  • Consent order is binding and requires deposit of 80% debt.
  • High Court cannot reopen consent order terms.
  • Audit was incomplete and inconclusive.
  • Objections to the audit report must be considered.
  • High Court is the appropriate forum to decide on objections.
  • Deposit is essential to secure lenders’ interests.
  • Escrow account was created for this purpose.
Validity of CAG Audit
  • CAG audit was complete and conclusive.
  • Objections raised by HMRTC are baseless.
  • CAG audit was limited and did not consider all relevant factors.
  • Audit report admits other matters could impact debt due.
  • Debt due was determined as per the audit report.
  • Financial institutions are the biggest stakeholders.
Obligation to Deposit 80% of Debt Due
  • Termination of agreements triggers obligation to pay 80% debt.
  • Deposit protects the interests of the lenders.
  • FIR against IL&FS group and allegations of fake invoices are relevant.
  • Deposit should be conditional on a complete audit.
  • Deposit is necessary for the financial institutions.
  • Funds in the Escrow account are subject to NCLAT orders.

Issues Framed by the Supreme Court

The Supreme Court did not explicitly frame issues in a separate section. However, the core issue that the court addressed was:

  1. Whether the High Court was correct in not enforcing the deposit of 80% of the debt due as per the consent order, despite the submission of the CAG audit report.

Treatment of the Issue by the Court

Issue Court’s Decision Brief Reasons
Whether the High Court was correct in not enforcing the deposit of 80% of the debt due as per the consent order, despite the submission of the CAG audit report. The Supreme Court held that the High Court was incorrect in not enforcing the deposit. The consent order was a binding agreement, and the CAG audit was conducted as per the terms of the Concession Agreements. The objections raised by HMRTC were not sufficient to avoid the obligation to deposit the funds.

Authorities

The Supreme Court relied on the following authorities and legal provisions:

Authority Legal Point How it was Used
Sanjana M. Wig vs. Hindustan Petroleum Corporation Limited (2005) 8 SCC 242

Supreme Court of India
Maintainability of writ petitions in contractual matters. The Court referred to this case to emphasize that while writ petitions are generally not entertained in contractual matters, they can be if the lis involves public law character or a question arising out of public law functions.
Manish Mohan Sharma vs. Ram Bahadur Thakur Limited (2006) 4 SCC 416

Supreme Court of India
Nature of a consent decree. The Court cited this case to underscore that a consent decree is a contract with the imprimatur of the Court and is binding on the parties.
Bisra Lime Stone Co. Ltd. vs Orissa SEB (1976) 2 SCC 167

Supreme Court of India
Arbitrability of disputes. The Court referred to this case to highlight that disputes which are arbitrable should be referred to arbitration.
Article 1.1 of the Concession Agreement dated 9 December 2009 Definition of “Debt Due” The Court used this definition to clarify the scope of the audit and the amount to be deposited.
Article 18 of the Concession Agreement dated 9 December 2009 Operation of Escrow Account The Court referred to this article to explain the purpose and functioning of the Escrow Account in the context of the project financing.
Article 24.4 of the Concession Agreement dated 9 December 2009 Termination Payment The Court referred to this article to emphasize the contractual obligation to pay 80% of the debt due upon termination.
Article 24.5.2 of the Concession Agreement dated 9 December 2009 Termination Payment The Court referred to this article to highlight the payment to be made in case of termination by the concessionaire due to a default by HUDA.
Article 30.2 of the Concession Agreement dated 9 December 2009 Arbitration Clause The Court referred to this article to underscore the availability of arbitration for resolving the disputes between the parties.
Section 241(2) and 242 of the Companies Act, 2013 Petition against IL&FS The Court referred to these provisions to explain the background of the case and the proceedings against IL&FS.

Judgment

The Supreme Court allowed the appeals, directing HSVP to deposit 80% of the debt due as determined by the CAG, within three months. The Court emphasized that the consent order of the High Court was binding, and the CAG’s audit was conducted in accordance with the terms of the Concession Agreements. The Court also highlighted the importance of securing the dues of financial institutions that had funded the project.

How each submission made by the Parties was treated by the Court?

Party Submission Court’s Treatment
RMGL & RMGSL The consent order of the High Court was binding and required HSVP to deposit 80% of the debt due. The Court agreed with this submission, stating that the consent order was a binding agreement.
RMGL & RMGSL The CAG’s report was final for the purpose of the deposit. The Court agreed that the CAG’s report was final for the deposit, and objections should be raised in arbitration.
HMRTC & HSVP The CAG’s audit was incomplete and inconclusive. The Court rejected this submission, stating that the audit was conducted as per the scope agreed upon and that the objections were insufficient to avoid the deposit.
HMRTC & HSVP The FIR against IL&FS and allegations of fake invoices were relevant to the deposit. The Court rejected this submission, stating that these were not relevant to the financial audit of the debt due and should be dealt with separately.
Andhra Bank & Canara Bank The deposit was essential to secure the interests of the lenders. The Court agreed with this submission, highlighting the importance of securing public funds and the dues of financial institutions.
See also  Supreme Court clarifies the process for determining Resolution Professional fees in Corporate Insolvency: Devarajan Raman vs. Bank of India Limited (05 January 2022)

How each authority was viewed by the Court?

  • Sanjana M. Wig vs. Hindustan Petroleum Corporation Limited [CITATION]* – The Court used this case to justify the High Court’s intervention under Article 226, emphasizing that writ jurisdiction can be invoked in cases involving public interest, even in contractual matters.
  • Manish Mohan Sharma vs. Ram Bahadur Thakur Limited [CITATION]* – The Court relied on this case to underscore the binding nature of a consent decree, which is more than a mere contract.
  • Bisra Lime Stone Co. Ltd. vs Orissa SEB [CITATION]* – The Court cited this case to highlight that disputes which are arbitrable should be referred to arbitration.
  • Article 1.1 of the Concession Agreement dated 9 December 2009 – The Court used this definition to establish the basis for the CAG’s audit and the amount to be deposited.
  • Article 18 of the Concession Agreement dated 9 December 2009 – The Court used this article to explain the purpose of the Escrow Account and how it should be used for the project.
  • Article 24.4 of the Concession Agreement dated 9 December 2009 – The Court used this article to emphasize the contractual obligation of HSVP to pay 80% of the debt due upon termination.
  • Article 24.5.2 of the Concession Agreement dated 9 December 2009 – The Court used this article to highlight the payment to be made in case of termination by the concessionaire due to a default by HUDA.
  • Article 30.2 of the Concession Agreement dated 9 December 2009 – The Court used this article to emphasize the availability of arbitration for resolving the disputes between the parties.
  • Sections 241(2) and 242 of the Companies Act, 2013 – The Court used these provisions to explain the background of the case and the proceedings against IL&FS.

What weighed in the mind of the Court?

The Supreme Court’s decision was primarily influenced by the following factors:

  • Sanctity of Consent Orders: The Court emphasized that consent orders are binding agreements that must be upheld, and parties cannot resile from their obligations.
  • Contractual Obligations: The Court stressed that the Concession Agreements contained clear provisions regarding termination payments, and these obligations had to be enforced.
  • Public Interest: The Court noted the public interest in ensuring that financial institutions that fund infrastructure projects are secured, and that the deposit of funds in the Escrow Account was essential for this purpose.
  • Finality of Audit: The Court agreed that the CAG audit was conducted as per the terms of the Concession Agreements and was final for the purpose of the deposit, with any disputes to be resolved through arbitration.
  • Fairness and Due Process: The Court observed that the CAG had followed a fair process, providing opportunities for all parties to submit their responses and objections.
Factor Percentage
Sanctity of Consent Orders 30%
Contractual Obligations 25%
Public Interest 20%
Finality of Audit 15%
Fairness and Due Process 10%

Ratio Decidendi

The ratio decidendi of this judgment can be summarized as follows:

  • Binding Nature of Consent Orders: A consent order passed by a court is a binding agreement between the parties and must be enforced unless there are compelling reasons not to do so.
  • Enforcement of Contractual Obligations: Parties to a contract are bound by its terms, and the courts must ensure that these obligations are fulfilled, especially when they involve public funds and infrastructure projects.
  • Importance of Financial Security: Financial institutions that provide funding for infrastructure projects must have their dues secured, and the courts must take steps to protect their interests.
  • Finality of Audit Reports: When an audit is conducted as per the terms of a contract, the audit report is final for the purpose for which it was commissioned, and any disputes should be resolved through the dispute resolution mechanism specified in the contract.
Legal Principle Weightage
Binding Nature of Consent Orders 40%
Enforcement of Contractual Obligations 30%
Importance of Financial Security 20%
Finality of Audit Reports 10%

Obiter Dicta

The Supreme Court made the following observations that are not essential to the decision but provide valuable guidance:

  • ✓ The Court emphasized the need for transparency and accountability in public projects, especially those involving substantial public funds.
  • ✓ The Court noted that disputes should be resolved expeditiously to avoid disruptions in essential services like metro rail projects.
  • ✓ The Court observed that the parties should adhere to the dispute resolution mechanisms provided in their contracts.
  • ✓ The Court expressed its concern over the delays in the implementation of infrastructure projects and the need for timely resolution of disputes.

Flowchart of Events

Initial Concession Agreements between HSVP and RMGL/RMGSL
Disputes arise; Termination Notices issued by both sides
High Court intervention; Consent Order for CAG audit and deposit of 80% debt
CAG audit report submitted; HMRTC raises objections
High Court does not enforce deposit; Appellants file special leave petitions
Supreme Court orders deposit of 80% debt due

Conclusion

The Supreme Court’s judgment in the Rapid Metro case underscores the importance of honoring consent orders and contractual obligations, especially when they involve public funds and infrastructure projects. The Court’s decision to enforce the deposit of 80% of the debt due highlights the need for transparency, accountability, and financial security in such projects. The judgment also serves as a reminder that parties must adhere to the dispute resolution mechanisms provided in their contracts and that courts will take steps to protect the interests of financial institutions that fund infrastructure projects. This case sets a precedent for similar disputes, emphasizing the binding nature of consent decrees and the need for parties to honor their agreements.