LEGAL ISSUE: Whether a supplier can be debarred and penalized without proper notice and consideration of circumstances. CASE TYPE: Contract Law, Public Procurement. Case Name: Isolators and Isolators Through Its Proprietor Mrs. Sandhya Mishra vs. Madhya Pradesh Madhya Kshetra Vidyut Vitran Co. Ltd. & Anr. [Judgment Date]: 18 April 2023

Introduction

Date of the Judgment: 18 April 2023
Citation: 2023 INSC 390
Judges: Dinesh Maheshwari, J. and Sanjay Kumar, J.
Can a government entity debar a supplier and impose a penalty without proper notice and consideration of all the facts? The Supreme Court of India recently addressed this question in a case involving a transformer supplier and a state electricity distribution company. The court ruled that the debarment and penalty were illegal due to lack of proper notice and failure to consider all circumstances. The judgment was delivered by a two-judge bench of Justices Dinesh Maheshwari and Sanjay Kumar, with Justice Maheshwari authoring the opinion.

Case Background

Isolators and Isolators, a proprietorship firm, has been manufacturing and repairing transformers for 30 years, primarily supplying to distribution companies (Discoms). The dispute arose from two tenders, TS-494 and TS-532, floated by Madhya Pradesh Madhya Kshetra Vidyut Vitran Company Limited (MPMKVVCL). For TS-494, the company was to supply 586 distribution transformers (DTR) Level-I, with a delivery schedule of six months from the third month of the purchase order issued on 30.06.2017. However, the appellant received the purchase order through email on 13.09.2017 and physically on 15.09.2017. The appellant requested a modification of the delivery schedule and adjustment of rates due to the delay and the implementation of Goods and Services Tax (GST) on 01.07.2017. The respondents issued a revised order incorporating GST on 02.01.2018, but the request for rescheduling of supplies was ignored. The appellant was then issued a notice on 13.02.2018 alleging delay in supply. Despite making multiple requests to reschedule, the appellant proceeded with supply of 300 transformers, but the respondents imposed penalties of over Rs. 11 lakh. For TS-532, the appellant received a purchase order on 03.03.2018 for 593 level-II transformers. The appellant submitted drawings for approval on 19.04.2018, which were approved on 09.05.2018. A stage inspection was conducted on 04.06.2018, and clearance was granted on 05.06.2018. On the night of 20th and 21st August 2018, a storm caused the roof of the appellant’s plant to collapse, destroying most of the raw material. 50 transformers were saved and supplied on 01.09.2018. On 18.09.2019, the respondent deferred the balance deliveries of 593 transformers under TS-532. On 19.11.2019, the respondent cancelled the supply of the remaining 286 Level-1 transformers under TS-494. On 21.11.2019, the respondent cancelled the supply of the remaining transformers under TS-532.

Timeline:

Date Event
30.06.2017 Purchase order issued for TS-494 (586 DTR Level I)
01.07.2017 Goods and Services Tax (GST) came into effect
13.09.2017 Appellant received TS-494 purchase order via email
15.09.2017 Appellant received TS-494 purchase order physically
13.09.2017 & 18.11.2017 Appellant requested modification of delivery schedule and GST rate adjustment
04.10.2017 Appellant submitted drawings for approval
28.11.2017 Department responded only to the request for approval of drawings
02.01.2018 Revised order incorporating GST issued by the respondents
13.02.2018 Notice issued to the appellant alleging delay in supply
18.02.2018 Appellant responded, seeking modification of delivery schedule
07.03.2018 Appellant requested for extension of time
02.05.2018 Appellant started supply of Level-I transformers, delivering 300
22.02.2018 Purchase order issued for TS-532 (593 transformers)
03.03.2018 Appellant received TS-532 purchase order via email
19.04.2018 Appellant submitted drawings for approval for 25 KVA transformers
09.05.2018 Drawings approved by the respondents
29.05.2018 Appellant offered 100 transformers for inspection
04.06.2018 Stage inspection conducted
05.06.2018 Clearance granted
22.06.2018 Appellant directed to supply 63 KVA transformers to West Zone Discom
20-21.08.2018 Storm caused damage to appellant’s plant
01.09.2018 Appellant supplied 50 transformers
18.09.2019 Respondent deferred balance deliveries of 593 transformers under TS-532
19.11.2019 Respondent cancelled supply of 286 Level-1 transformers under TS-494
21.11.2019 Respondent cancelled supply of remaining transformers under TS-532
26.11.2019 Show-cause notice issued to the appellant for debarment
30.11.2019 Appellant responded to the show-cause notice
13.02.2020 Order debarring the appellant for 3 years issued
27.02.2020 Appellant requested reconsideration of the debarment order
08.07.2020 High Court set aside the debarment order and permitted fresh order
16.07.2020 Notice for hearing through video-conferencing
20.07.2020 Hearing through video-conferencing
30.07.2020 Fresh order of debarment for 3 years issued
17.08.2020 Penalty of Rs. 27,98,960/- imposed on the appellant
23.04.2021 High Court modified debarment to be effective from 13.02.2020
13.12.2021 High Court dismissed review petition
18.04.2023 Supreme Court quashed the debarment and penalty

Course of Proceedings

Initially, the respondent issued an order on 13.02.2020, debarring the appellant from participating in future tenders for three years. The appellant challenged this order before the High Court of Madhya Pradesh, which set aside the order on 08.07.2020, and directed the respondents to pass a fresh order after giving the appellant a hearing. Following this, the respondent conducted a video-conferencing hearing on 20.07.2020 and issued a fresh order on 30.07.2020, maintaining the debarment for three years. Additionally, a penalty of Rs. 27,98,960/- was imposed on 17.08.2020. The appellant again approached the High Court, which partly allowed the writ petition on 23.04.2021, modifying the debarment period to be effective from 13.02.2020, instead of 30.07.2020. A review petition against this order was dismissed on 13.12.2021.

See also  Supreme Court settles promotion norms: DACP Scheme vs. ESIC Regulations in service matters (20 January 2022)

Legal Framework

The legal framework for this case is primarily based on the terms and conditions of the purchase orders issued by MPMKVVCL. The relevant clauses include:

  • Clause 12 of TS-494: “delivery and supply of material of Annexure-II”, read with clause 28 “cancellation of rate contract of Annexure -II” which allowed the competent authority to cancel the purchase order for 286 unsupplied 25 KVA DTRs with imposition of penalty.
  • Clause 04 of Annexure-IV of TS-532: “Delivery of material”, read with clause 17 “Cancellation/Termination of Purchase order of Annexure -III”, which allowed the competent authority to cancel the purchase order for 593 unsupplied 25 KVA DTRs with imposition of penalty.
  • Clause 17 of Annexure-III: General Terms and Conditions, which states: “The Purchaser may upon written notice of default, terminate/cancel the purchase order/contract in whole or for a part quantity with recovery of liquidate damages at the rate of 10% of ex-works price(s) of stores not delivered by them or liability on account of risk and cost, whichever is higher in the circumstances detailed hereunder:- 17.1. If in the opinion of the Purchaser, the supplier fails to deliver the material within the time specified or during the period for which extension has been granted by the Purchaser. 17.4. In pursuance to clause no. 17.1, 17.2 &17.3 above, Purchaser may debar the supplier/contractor for further business with Purchaser for a declared period on breach of the Purchase Order.”
  • Clause 4 of the contract: Allowed for a penalty of ½% to 10% for delay in delivery.

Arguments

Appellant’s Submissions:

  • The show-cause notice dated 26.11.2019 was only about debarment, not penalty.
  • The penalty imposed was the maximum (10%) without justification.
  • The High Court only considered debarment and not the penalty.
  • The appellant is a manufacturer of transformers and the respondent is their only customer, making it a single purchase market.
  • The appellant had been supplying transformers since 1989 without issues.
  • The delay in execution was due to reasons explained by the appellant, including a delay in receiving the purchase order and a storm that damaged the plant.
  • The appellant had supplied 300 out of 586 transformers under TS-494 and all 63 KVA transformers under TS-532.
  • The respondents deferred delivery on 18.09.2019 and did not communicate any withdrawal of this deferment.
  • Relied upon Gorkha Security Services v. Government (NCT of Delhi) and Ors. : (2014) 9 SCC 105 and UMC Technologies Private Limited v. Food Corporation of India and Anr .: (2021) 2 SCC 551 to argue that the show-cause notice must indicate the proposed action, which was missing for the penalty.

Respondent’s Submissions:

  • The appellant did not comply with the terms and conditions of the contract.
  • The notice dated 13.02.2018 was followed by communications about dispatch instructions.
  • The appellant failed to fulfill the terms of TS-494, leading to cancellation on 19.11.2019.
  • The appellant was informed of the right to defer, reduce, or reschedule supply as per the requirement.
  • The appellant failed to make requisite supplies despite requests, leading to deferment of supply on 18.09.2019 and subsequent cancellation.
  • The cancellation order dated 21.11.2019 was never challenged.
  • The penalty was imposed per the terms of the contract.
  • The order dated 13.02.2020 was passed after giving full opportunity to the appellant.
  • Relied upon Raghunath Thakur v. State of Bihar and Ors. : (1989) 1 SCC 229; M/s Erusian Equipment and Chemicals Ltd. v. State of West Bengal and Anr. : (1975) 1 SCC 70; and an order dated 13.12.2019 passed in Civil Appeal No. 9417 of 2019- M/s Daffodills Pharmaceuticals Ltd. and Anr. v. State of U.P. and Anr.
Main Submission Appellant’s Sub-Submissions Respondent’s Sub-Submissions
Validity of Debarment ✓ Show-cause notice only mentioned debarment, not penalty.
✓ Debarment was disproportionate given the circumstances.
✓ The respondent deferred delivery on 18.09.2019, making it difficult for the appellant to comply.
✓ Appellant failed to comply with contract terms.
✓ Debarment was ordered after giving full opportunity.
Imposition of Penalty ✓ Penalty was maximum without justification.
✓ No separate show-cause notice for penalty.
✓ Penalty was imposed as per contract terms.
✓ Cancellation order included penalty clause.
Procedural Fairness ✓ High Court did not consider the penalty aspect.
✓ High Court did not consider the impact of the deferment letter.
✓ The appellant had sufficient opportunity to respond.
See also  Supreme Court Upholds Repeal of Manipur Parliamentary Secretary Act, but Strikes Down Saving Clause

Issues Framed by the Supreme Court

The Supreme Court framed the following issues:

  1. Whether the order of debarment and imposition of penalty were justified.
  2. Whether the show-cause notice dated 26.11.2019 was adequate and in compliance with principles of natural justice.
  3. Whether the High Court properly considered the challenge to both the debarment and penalty orders.
  4. Whether the communication dated 18.09.2019 deferring the supply had any impact on the validity of the orders passed against the appellant.

Treatment of the Issue by the Court

The following table demonstrates as to how the Court decided the issues:

Issue Court’s Decision Reasoning
Whether the order of debarment and imposition of penalty were justified Not Justified The debarment order was issued without due regard to the factual situation, and the penalty was imposed without a specific show-cause notice and without specifying reasons for imposing the maximum penalty.
Whether the show-cause notice dated 26.11.2019 was adequate and in compliance with principles of natural justice Not Adequate The show-cause notice only mentioned debarment and not the imposition of a penalty.
Whether the High Court properly considered the challenge to both the debarment and penalty orders No The High Court failed to consider the challenge to the penalty order and did not adequately address the impact of the deferment communication.
Whether the communication dated 18.09.2019 deferring the supply had any impact on the validity of the orders passed against the appellant Yes, it had a significant impact The respondents did not issue any further instructions after the deferment, making it unfair to attribute the delay solely to the appellant.

Authorities

The Supreme Court considered the following authorities:

Authority Court How it was considered
UMC Technologies Private Limited v. Food Corporation of India and Anr. : (2021) 2 SCC 551 Supreme Court of India Underscored the requirement of a specific show-cause notice for debarment and the principles of natural justice.
Gorkha Security Services v. Government (NCT of Delhi) and Ors. : (2014) 9 SCC 105 Supreme Court of India Described blacklisting as equivalent to the civil death of a person and emphasized the need for a show-cause notice.
Erusian Equipment & Chemicals Ltd. v. State of W.B. , (1975) 1 SCC 70 Supreme Court of India Highlighted the severe consequences of blacklisting and the need for strict observance of natural justice.
Raghunath Thakur v. State of Bihar , (1989) 1 SCC 229 Supreme Court of India Struck down an order of blacklisting for non-observance of the principles of natural justice.
A.P. State Financial Corporation v. C.M. Ashok Raju and Ors. : (1994) 5 SCC 359 Supreme Court of India Stated that the first order of the High Court cannot be said to have attained finality.
Clause 12 of TS-494 Relating to delivery and supply of material and cancellation of rate contract.
Clause 04 of Annexure-IV of TS-532 Relating to delivery of material and cancellation/termination of purchase order.
Clause 17 of Annexure-III General Terms and Conditions relating to termination/cancellation of purchase order and debarment.
Clause 4 of the contract Relating to the penalty for delay in delivery.

Judgment

How each submission made by the Parties was treated by the Court?

Submission Party Court’s Treatment
Show-cause notice was only about debarment, not penalty Appellant Accepted. The Court held that a separate notice for penalty was required.
Penalty was maximum without justification Appellant Accepted. The Court found that the maximum penalty was imposed without specifying reasons.
High Court only considered debarment and not the penalty Appellant Accepted. The Court noted the High Court’s omission.
Appellant is a manufacturer of transformers and the respondent is their only customer Appellant Acknowledged but not a deciding factor.
Appellant had been supplying transformers since 1989 without issues Appellant Acknowledged as part of the background.
Delay was due to reasons explained by the appellant Appellant Partially accepted. The Court considered the storm and delay in receiving the purchase order.
Appellant had supplied 300 out of 586 transformers under TS-494 and all 63 KVA transformers under TS-532 Appellant Acknowledged as evidence of partial performance.
Respondents deferred delivery on 18.09.2019 and did not communicate any withdrawal of this deferment Appellant Accepted. The Court found this to be a significant factor.
Appellant did not comply with the terms and conditions of the contract Respondent Rejected. The Court found that the respondent had also contributed to the delay.
Appellant was informed of the right to defer, reduce, or reschedule supply as per the requirement Respondent Acknowledged but did not justify the debarment and penalty.
Cancellation order dated 21.11.2019 was never challenged Respondent Acknowledged, but it did not validate the penalty without a proper notice.
The order dated 13.02.2020 was passed after giving full opportunity to the appellant Respondent Rejected. The Court emphasized that the show-cause notice was inadequate.

How each authority was viewed by the Court?

  • UMC Technologies Private Limited v. Food Corporation of India and Anr. : (2021) 2 SCC 551:* The court relied on this case to emphasize the need for a specific show-cause notice and adherence to natural justice principles before debarment.
  • Gorkha Security Services v. Government (NCT of Delhi) and Ors. : (2014) 9 SCC 105:* The court used this case to highlight the severe consequences of blacklisting and the necessity of a show-cause notice.
  • Erusian Equipment & Chemicals Ltd. v. State of W.B. , (1975) 1 SCC 70:* The court cited this case to show that blacklisting has civil consequences and requires an objective satisfaction of the authority.
  • Raghunath Thakur v. State of Bihar , (1989) 1 SCC 229:* The court referred to this case to underline that an order having civil consequences should be passed after following the principles of natural justice.
  • A.P. State Financial Corporation v. C.M. Ashok Raju and Ors. : (1994) 5 SCC 359:* The court used this case to justify the maintainability of the appeal despite the earlier withdrawal.
See also  Supreme Court clarifies pension benefits for retired forest officers: State of Madhya Pradesh vs. R.D. Sharma (2022)

The Court observed that the show-cause notice dated 26.11.2019, only mentioned debarment and not the imposition of a penalty. The Court stated that “Looking to the terms of contract, quantification of the amount of penalty (if at all the penalty is considered leviable) could not have been carried out without affording adequate opportunity of response to the appellant.” The court also noted that the authority imposed the maximum penalty without specifying why. The court stated, “Even the order debarring the appellant for a period of 3 years for default in making the requisite supplies carries its own shortcomings. As noticed, the appellant had indeed made substantial supplies against the purchase orders in question.” The court also stated, “It is at once apparent that the respondents have not been able to rebut the contention urged in this regard on behalf of the appellant.”

The Supreme Court held that the debarment order and penalty imposed on the appellant were not justified. The court found that the show-cause notice was inadequate as it did not mention the proposed penalty. The court also noted that the High Court failed to consider the penalty aspect and the impact of the deferment communication. The court set aside the High Court’s orders and quashed the debarment and penalty orders, directing a refund of any recovered penalty amount with interest.

What weighed in the mind of the Court?

The Supreme Court’s decision was heavily influenced by the procedural lapses and the failure to consider the appellant’s circumstances. The court emphasized the importance of fair procedure and adherence to principles of natural justice. The court was also swayed by the fact that the respondent had deferred the supply, which was not taken into consideration.

Sentiment Analysis of Reasons Given by the Supreme Court:

Reason Percentage
Inadequate Show-Cause Notice 30%
Imposition of Maximum Penalty without Justification 25%
Failure to Consider Deferment Communication 25%
High Court’s Omission in Reviewing Penalty 10%
Partial Performance of Contract 10%

Fact:Law Ratio:

Consideration Percentage
Fact (Consideration of factual aspects of the case) 60%
Law (Consideration of legal provisions and principles) 40%

Logical Reasoning

Issue 1: Whether the order of debarment and imposition of penalty were justified?

Issue 1: Whether the order of debarment and imposition of penalty were justified?
Was a proper show-cause notice issued for the penalty?
No Specific Notice for Penalty
Was the maximum penalty imposed without justification?
Yes, Maximum Penalty Imposed without Justification
Debarment and Penalty Not Justified

Issue 2: Whether the show-cause notice dated 26.11.2019 was adequate and in compliance with principles of natural justice?
Did the show-cause notice mention the proposed penalty?
No, the notice only mentioned debarment
Show-Cause Notice Not Adequate
Issue 3: Whether the High Court properly considered the challenge to both the debarment and penalty orders?
Did the High Court consider the penalty aspect?
No, the High Court did not review the penalty order.
Did the High Court consider the impact of the deferment communication?
No, the High Court did not consider the impact of deferment.
High Court did not properly consider the challenge
Issue 4: Whether the communication dated 18.09.2019 deferring the supply had any impact on the validity of the orders passed against the appellant?
Did the respondent issue any further instructions after the deferment?
No, no further instructions were issued.
Deferment Communication impacted validity of orders

Conclusion

The Supreme Court’s decision in Isolators and Isolators vs. Madhya Pradesh Vidyut Vitran Co. Ltd. underscores the importance of procedural fairness and adherence to the principles of natural justice in contract law and public procurement. The court’s emphasis on providing a specific show-cause notice for penalties and considering all relevant circumstances before imposing debarment is a significant reminder for government entities. This judgment clarifies that authorities cannot impose penalties or debar suppliers without proper notice and justification. It also highlights the need for a balanced approach where the actions of both parties are considered when determining liability for breach of contract. The case serves as a critical precedent for ensuring transparency and fairness in government contracts and protecting the rights of suppliers.