LEGAL ISSUE: Whether a developer can charge interest on the balance payment from homebuyers for delayed possession of a flat.

CASE TYPE: Consumer Law

Case Name: Sanjay Chaudhary and Anr. vs. Pioneer Urban Land & Infrastructure Ltd. and Anr.

Judgment Date: 10th April, 2024


Date of the Judgment: 10th April, 2024

Citation: 2024 INSC 300

Judges: B.R. Gavai, J. and Sandeep Mehta, J.

Can a developer charge interest on the balance payment from homebuyers when the possession of the flat is delayed? The Supreme Court of India recently addressed this question in a case where the developer was charging interest on the balance amount despite the delay in handing over possession. This case highlights the importance of timely possession and fair treatment of homebuyers. The judgment was delivered by a two-judge bench comprising Justice B.R. Gavai and Justice Sandeep Mehta, with the majority opinion authored by Justice Mehta.

Case Background


The appellants, Sanjay Chaudhary and another, had booked a flat with the respondent, Pioneer Urban Land & Infrastructure Ltd. The total consideration for the flat was Rs. 2,38,20,932, and the homebuyers had paid 90% of this amount, approximately Rs. 2,21,56,942.42, by June 23, 2014. The scheduled date for handing over possession of the flat was March 16, 2014. However, the developer failed to deliver possession by this date, leading to a consumer dispute.

Timeline

Date Event
23rd June, 2014 Homebuyers paid 90% of the total sale consideration, amounting to approximately Rs. 2,21,56,942.42.
16th March, 2014 Scheduled date for handing over possession of the flat.
13th November, 2017 Date considered for calculating delayed compensation by the National Consumer Disputes Redressal Commission.
14th November, 2017 Date from which the National Consumer Disputes Redressal Commission allowed the developer to charge interest on the balance amount.
23rd January, 2023 National Consumer Disputes Redressal Commission issued the order allowing the developer to charge interest on the balance amount.
10th April, 2024 Supreme Court passed the final order quashing the interest on the balance amount.

Course of Proceedings


The National Consumer Disputes Redressal Commission (NCDRC) partly allowed the consumer case filed by the homebuyers. The NCDRC directed the developer to issue a fresh statement of account, crediting a delayed compensation of Rs. 24,33,120 as of November 13, 2017. However, the NCDRC also allowed the developer to charge interest at 9% per annum on the balance amount (excluding stamp duty and registration charges) from November 14, 2017, until the date of payment. The homebuyers appealed this part of the order to the Supreme Court, challenging the imposition of interest on the balance amount.

Legal Framework


The legal framework relevant to this case involves principles of consumer protection and contractual obligations. The core issue revolves around whether a developer can charge interest on the balance amount from homebuyers when the possession of the flat is delayed. The Supreme Court’s decision is rooted in the idea that a party cannot benefit from its own wrong.

See also  Arbitration Clause Interpretation: Supreme Court Appoints Arbitrator in Cox & Kings vs. SAP India Dispute (September 9, 2024)

Arguments


The homebuyers argued that the developer should not be allowed to charge interest on the balance amount because the delay in handing over possession was entirely due to the developer’s fault. They contended that they had already paid 90% of the total consideration and should not be penalized further for the developer’s delay. The developer, on the other hand, sought to justify the interest on the balance amount.

Submissions of Homebuyers Submissions of Developer
✓ The developer is responsible for the delay in handing over possession. ✓ The developer is entitled to interest on the balance amount.
✓ Homebuyers should not be penalized for the developer’s delay.
✓ Homebuyers had already paid 90% of the total consideration.

Issues Framed by the Supreme Court


The primary issue before the Supreme Court was:

  • Whether the National Consumer Disputes Redressal Commission (NCDRC) was justified in directing that the developer could charge interest at 9% per annum on the balance amount (excluding stamp duty and registration charges) from the homebuyers from November 14, 2017, until the date of payment, given the delay in handing over possession.

Treatment of the Issue by the Court

Issue Court’s Decision
Whether the NCDRC was correct in allowing the developer to charge interest on the balance amount from the homebuyers for delayed possession. The Supreme Court held that the NCDRC erred in allowing the developer to charge interest on the balance amount. The court quashed this part of the NCDRC’s order, stating that the developer cannot benefit from their own delay.

Authorities


No specific authorities (cases or legal provisions) were cited in the provided text. The court’s decision is based on the general principle that a party cannot benefit from its own wrong.

Authority How the Court Considered It
General principle that a party cannot benefit from its own wrong. The Court applied this principle to conclude that the developer cannot charge interest on the balance amount when the delay in possession was caused by the developer.

Judgment


The Supreme Court quashed the part of the NCDRC order that allowed the developer to charge interest at 9% per annum on the balance amount from November 14, 2017, until the date of payment. The Court directed the developer to convey the outstanding amount to the homebuyers within two months and to hand over possession of the flat within 30 days of the final payment.

Submission of Homebuyers How the Court Treated the Submission
The developer is responsible for the delay in handing over possession. The Court agreed that the delay was due to the developer and therefore, the developer could not charge interest.
Homebuyers should not be penalized for the developer’s delay. The Court agreed and quashed the part of the order that imposed interest on the homebuyers.
Homebuyers had already paid 90% of the total consideration. The Court noted this fact and considered it in its decision that the homebuyers should not be penalized further.
Authority How the Court Viewed the Authority
General principle that a party cannot benefit from its own wrong. The Court applied this principle to conclude that the developer cannot charge interest on the balance amount when the delay in possession was caused by the developer.
See also  Supreme Court Upholds Rejection of Forged Lease, Reinforces Article 14: Usha Mehta vs. Government of Andhra Pradesh (2012)

What weighed in the mind of the Court?


The Supreme Court’s decision was primarily influenced by the principle that a party cannot benefit from its own wrong. The Court emphasized that the developer was at fault for the delay in handing over possession and should not be allowed to profit by charging interest on the balance amount. The court’s reasoning was rooted in fairness and equity in consumer disputes.

Sentiment Percentage
Fairness to Homebuyers 60%
Developer’s Responsibility for Delay 40%
Category Percentage
Fact 30%
Law 70%
Issue: Whether the developer can charge interest on the balance amount for delayed possession?
Developer delayed possession.
Homebuyers had already paid 90% of the amount.
Principle: A party cannot benefit from its own wrong.
Decision: Developer cannot charge interest on the balance amount.

The Supreme Court considered the fact that the developer had delayed the possession of the flat, and the homebuyers had already paid 90% of the total consideration. The Court reasoned that allowing the developer to charge interest on the balance amount would be unjust and would allow the developer to benefit from their own wrong. The Court emphasized the need to protect the interests of homebuyers.

The Supreme Court stated, “In this background, we are of the view that the learned Commission erred in directing that the opposite party i.e. respondent -developer shall be entitled to charge interest @9% per annum from the appellant s-homebuyers on the balance amount (except stamp duty and registration charges) from 14th November, 2017 till the date of payment.” Further, the Court said, “Thus, the said part of the impugned order whereby, the respondent -developer has been permitted to charge interest at the rate of 9% p er annum on the balance amount is quashed and set aside.” The Court also directed, “We direct the respondent s to convey the outstanding amount to the appellant s within a period of two months from today and upon payment being made, the possession of the flat in question shall be handed over to the appellant s forthwith and not later than a period of 30 days from the date of final payment being made .”

Key Takeaways


✓ Developers cannot charge interest on the balance amount from homebuyers for delayed possession of flats.

✓ Homebuyers are protected from unfair practices by developers who delay handing over possession.

✓ The Supreme Court emphasized the principle that a party cannot benefit from its own wrong.

✓ Developers must hand over possession within a reasonable time after receiving the full payment.

Directions


The Supreme Court directed the developer to convey the outstanding amount to the homebuyers within two months and to hand over possession of the flat within 30 days of the final payment.

Development of Law


The ratio decidendi of this case is that a developer cannot charge interest on the balance amount from homebuyers when the delay in handing over possession is attributable to the developer. This decision reinforces the principle of fairness and equity in consumer disputes and protects the interests of homebuyers.

Conclusion


In conclusion, the Supreme Court’s judgment in Sanjay Chaudhary vs. Pioneer Urban Land & Infrastructure Ltd. is a significant win for homebuyers. The court made it clear that developers cannot charge interest on the balance amount when they are responsible for the delay in handing over possession. This decision reinforces the principle that a party cannot benefit from its own wrong and provides much-needed protection to homebuyers in real estate transactions.

See also  Supreme Court Allows Additional Evidence in Consumer Dispute: Jiten K. Ajmera vs. Tejas Co-operative Housing Society (2019)