LEGAL ISSUE: Whether a binding contract existed between Karnataka Power Transmission Corporation Limited and JSW Energy Limited regarding electricity tariff before the enactment of the Karnataka Electricity Reforms Act, 1999.
CASE TYPE: Electricity Regulatory/Contract Law
Case Name: Karnataka Power Transmission Corporation Limited vs. JSW Energy Limited
[Judgment Date]: 22 November 2022

Introduction

Date of the Judgment: 22 November 2022
Citation: (2022) INSC 1038
Judges: K.M. Joseph, J., Aniruddha Bose, J., and Hrishikesh Roy, J.

Did a binding agreement on electricity tariffs exist before the Karnataka Electricity Reforms Act of 1999 came into effect? The Supreme Court of India recently addressed this crucial question in a dispute between Karnataka Power Transmission Corporation Limited (KPTCL) and JSW Energy Limited. The core issue was whether a series of communications and a government order constituted a legally binding contract, exempting the parties from the regulatory oversight of the Karnataka Electricity Regulatory Commission.

Case Background

In March 1994, the Government of Karnataka (GoK) permitted JSW Energy Limited (then known as Jindal Thermal Power Company Limited) to establish a 2×130 MW thermal power plant in Bellary. The plant was primarily intended to supply power to Jindal Vijayanagar Steel Limited (JVSL). The Central Electricity Authority granted technical and economic clearance in March 1996. Initially, the plant was approved for 300 MW, later reduced to 260 MW.

Karnataka State Electricity Board (KEB) and JTPCL entered into a heads of terms agreement on 30 September 1995, which included a clause for KEB to purchase excess power from JTPCL, subject to price negotiation. A wheeling and banking agreement followed on 23 January 1996. In 1998, JTPCL sought to sell power to KEB, proposing a tariff based on Government of India norms, with certain exclusions for taxes, inflation, and foreign exchange variations.

Further negotiations led to JTPCL offering to supply 50 MW from Unit 1 and 100 MW from Unit 2 at a rate of Rs. 2.90/KWh, excluding certain costs. KEB expressed willingness to purchase this surplus power in December 1998. KEB then proposed to GoK to purchase power from JTPCL at Rs. 2.60 per unit, with a 5% annual escalation. GoK directed KEB to negotiate a fixed tariff for five years. JTPCL proposed a fixed tariff of Rs. 2.60 per unit with a 5% annual escalation, subject to certain conditions.

On 12 May 1999, GoK issued an order permitting KEB to finalize a power purchase agreement (PPA) with JTPCL at a rate of Rs. 2.60 per unit with a 5% annual increase for five years. The Karnataka Electricity Reforms Act, 1999 came into force on 1 June 1999.

Timeline

Date Event
March 1994 GoK permits JSW Energy to set up a 2×130 MW thermal power plant.
March 1996 Central Electricity Authority grants technical and economic clearance.
30 September 1995 KEB and JTPCL enter into a heads of terms agreement.
23 January 1996 KEB and JTPCL sign a wheeling and banking agreement.
20 October 1998 JTPCL proposes a tariff to KEB based on GOI norms.
21 November 1998 JTPCL offers to sell 50 MW from Unit 1 and 100 MW from Unit 2 to KEB.
1 December 1998 KEB expresses willingness to purchase surplus power from JTPCL.
19 January 1999 KEB proposes to GoK to purchase power from JTPCL at Rs. 2.60 per unit.
5 March 1999 GoK advises KEB to negotiate a fixed tariff with JTPCL.
31 March 1999 JTPCL proposes a fixed tariff of Rs. 2.60 per unit with a 5% annual escalation.
23 April 1999 KEB informs GoK about JTPCL’s tariff offer and other conditions.
12 May 1999 GoK permits KEB to finalize a PPA with JTPCL at Rs. 2.60 per unit with 5% escalation.
1 June 1999 Karnataka Electricity Reforms Act, 1999 comes into force.
4 January 2000 KEB requests JTPCL for a tariff break-up.
6 April 2000 JTPCL requests KPTCL to accept power supply from 12 April 2000.
12 April 2000 KPTCL approves continued power supply, subject to certain conditions.
24 May 2000 KPTCL approves payments to JTPCL at Rs. 2.52 per unit, pending PPA.
17 July 2000 GoK permits KPTCL to purchase power from JTPCL at Rs. 2.60 per unit with 5% annual increase.
7 November 2000 Draft power purchase agreement was made between the appellant and the first respondent.
22 May 2002 Karnataka Electricity Regulatory Commission passes order.
8 July 2002 Karnataka Electricity Regulatory Commission passes second impugned order.
22 November 2022 Supreme Court of India delivers judgment.
See also  Supreme Court Upholds Right to Sue for Declaration of Marital Status: Samar Kumar Roy vs. Jharna Bera (2017)

Course of Proceedings

The Karnataka Electricity Regulatory Commission (Commission) treated a letter from KPTCL as an application for approval of the PPA. JSW Energy contended that the Commission lacked jurisdiction as a contract was already concluded before the Act’s commencement. The Commission held that no concluded contract existed, and directed KPTCL to negotiate a fresh proposal based on a revised tariff. The Commission approved a draft PPA with modifications, reducing the tariff to Rs. 2.36 per unit for the first 657 MU and Rs. 1.88 per unit for excess energy.

JSW Energy challenged the Commission’s orders before the High Court, which set aside the orders, holding that a binding contract existed before the Act’s commencement. The High Court directed KPTCL to comply with the tariff specified in the GoK order dated 12 May 1999.

Legal Framework

The case primarily revolves around the interpretation of Section 27(2) of the Karnataka Electricity Reforms Act, 1999, which deals with tariffs. The proviso to this section states that contracts concluded by the Government of Karnataka or the KEB with generation and transmission companies before the Act’s commencement are deemed approved and must be given effect by the Commission.

Other relevant sections include Section 17, which regulates generating companies and stations, and Section 19, which deals with the grant of licenses by the Commission. Section 14 outlines the reorganization of the Karnataka Electricity Board and the transfer of its assets and liabilities.

Arguments

KPTCL argued that no concluded contract existed before the Act’s commencement because:

  • The offer by JTPCL was subject to approval by its Board and lenders.
  • There was no formal acceptance by KPTCL.
  • Essential clauses like escrow, deemed generation, and auxiliary consumption were not agreed upon.
  • The GoK order was merely an internal approval, not a statutory one.
  • The tariff of Rs. 2.60 was indicative, not final.

JSW Energy contended that a binding contract existed based on the GoK order dated 12 May 1999, which specified the tariff, quantity, and tenure. They argued that the proviso to Section 27(2) protected agreements on tariff made prior to the Act’s commencement. JSW Energy also argued that the PPA was not a pre-condition and that their conduct demonstrated a concluded contract.

KPTCL Submissions JSW Energy Submissions
Offer was subject to Board and lender approval GoK order of 12 May 1999 constituted a binding contract
No formal acceptance by KPTCL PPA not a pre-condition for a concluded contract
Essential clauses not agreed upon Conduct of parties showed a concluded contract
GoK order was internal, not statutory Proviso to Section 27(2) protects pre-Act tariff agreements
Tariff was indicative, not final Tariff, quantity, and tenure were agreed upon before 1 June 1999

Issues Framed by the Supreme Court

The Supreme Court addressed the following key issues:

  1. Whether a binding contract existed between KPTCL and JSW Energy on tariff prior to the commencement of the Karnataka Electricity Reforms Act, 1999.
  2. Whether the status of JSW Energy is that of an IPP or CPP.

Treatment of the Issue by the Court

Issue Court’s Treatment
Existence of a binding contract The Court held that no concluded contract existed before the Act’s commencement, as the parties contemplated a formal PPA with other essential terms.
Status of JSW Energy (IPP or CPP) The Court set aside the High Court’s finding and remitted the matter back to the High Court for reconsideration.

Authorities

The Supreme Court considered various cases and legal provisions including:

  • India Thermal Power Ltd. v. State of M.P. and others [ (2000) 3 SCC 379 ] – Supreme Court of India
  • All India Power Engineer Federation and others v. Sasan Power Ltd. and others [ (2017) 1 SCC 487 ] – Supreme Court of India
  • K.P. Chowdhary v. State of Madhya Pradesh and others [ (1966) 3 SCR 919 ] – Supreme Court of India
  • West Bengal Electricity Regulatory Commission v. CESC Ltd. [ (2002) 8 SCC 715 ] – Supreme Court of India
  • Ram Narain Sons Ltd. v. Asstt. Commissioner of Sales Tax and others [ AIR 1955 SC 765 ] – Supreme Court of India
  • Dwarka Prasad v. Dwarka Das Saraf [ AIR 1975 SC 1758 ] – Supreme Court of India
  • Mackinnon Mackenzie & Co. Ltd. v. Audrey D’Costa and another [ (1987) 2 SCC 469 ] – Supreme Court of India
  • Alexander Brogden and others and the Directors, & c., of the Metropolitan Railway Company [L.R.] 2 App. Cas. 666 – House of Lords
  • Kollipara Sriramulu (Dead) by His Legal Representative v. T. Aswatha Narayana (Dead) by His Legal Representatives and others [ AIR 1968 SC 1028 ] – Supreme Court of India
  • The Indian Contract Act, 1872
  • The Karnataka Electricity Reforms Act, 1999
  • The Electricity (Supply) Act, 1948
See also  Supreme Court Clarifies Total Disablement Under Employees Compensation Act: Arjun vs. IFFCO Tokio (2022)
Authority Court’s Treatment
India Thermal Power Ltd. v. State of M.P. and others Cited in the context of the need for a formal agreement.
All India Power Engineer Federation and others v. Sasan Power Ltd. and others Cited to emphasize that waiver must be clearly demonstrated, especially in contracts with public interest.
K.P. Chowdhary v. State of Madhya Pradesh and others Cited to support that State Government cannot be bound by an implied contract.
West Bengal Electricity Regulatory Commission v. CESC Ltd. Cited in the context of cross-subsidization.
Ram Narain Sons Ltd. v. Asstt. Commissioner of Sales Tax and others Cited to emphasize the importance of interpreting words in context.
Dwarka Prasad v. Dwarka Das Saraf Cited to explain the interpretation of provisos in statutes.
Mackinnon Mackenzie & Co. Ltd. v. Audrey D’Costa and another Cited to emphasize the importance of interpreting words in context.
Alexander Brogden and others and the Directors, & c., of the Metropolitan Railway Company Distinguished, court held that the facts were different and the parties contemplated a written PPA.
Kollipara Sriramulu (Dead) by His Legal Representative v. T. Aswatha Narayana (Dead) by His Legal Representatives and others Distinguished, court held that the facts were different and the parties contemplated a written PPA.

Judgment

Submission Court’s Treatment
KPTCL’s argument that the offer was subject to approval Court held that the parties did not insist on this condition before supplying power.
KPTCL’s argument that there was no formal acceptance Court held that a contract concluded by GoK is protected by the proviso to Section 27(2).
KPTCL’s argument that essential clauses were not agreed upon Court held that the parties did not consider these clauses essential by their conduct.
JSW Energy’s argument that a binding contract existed based on GoK order Court held that the GoK order did not constitute a concluded contract as the parties contemplated a formal PPA.

The Supreme Court viewed the authorities as follows:

  • India Thermal Power Ltd. v. State of M.P. and others [ (2000) 3 SCC 379 ]: The Court used this case to support its view that the parties intended to have a formal PPA.
  • All India Power Engineer Federation and others v. Sasan Power Ltd. and others [ (2017) 1 SCC 487 ]: The Court relied on this to emphasize that waiver must be clearly demonstrated, especially in contracts with public interest.
  • K.P. Chowdhary v. State of Madhya Pradesh and others [ (1966) 3 SCR 919 ]: The Court used this case to support its view that State Government cannot be bound by an implied contract.
  • West Bengal Electricity Regulatory Commission v. CESC Ltd. [ (2002) 8 SCC 715 ]: The Court referred to this case in the context of cross-subsidization, but did not find it directly applicable.
  • Ram Narain Sons Ltd. v. Asstt. Commissioner of Sales Tax and others [ AIR 1955 SC 765 ]: The Court cited this case to emphasize the importance of interpreting words in context.
  • Dwarka Prasad v. Dwarka Das Saraf [ AIR 1975 SC 1758 ]: The Court used this case to explain the interpretation of provisos in statutes.
  • Mackinnon Mackenzie & Co. Ltd. v. Audrey D’Costa and another [ (1987) 2 SCC 469 ]: The Court cited this case to emphasize the importance of interpreting words in context.
  • Alexander Brogden and others and the Directors, & c., of the Metropolitan Railway Company [L.R.] 2 App. Cas. 666: The Court distinguished this case, holding that the facts were different and the parties contemplated a written PPA.
  • Kollipara Sriramulu (Dead) by His Legal Representative v. T. Aswatha Narayana (Dead) by His Legal Representatives and others [ AIR 1968 SC 1028 ]: The Court distinguished this case, holding that the facts were different and the parties contemplated a written PPA.
See also  Supreme Court Allows Challenge to Criminal Proceedings in Illegal Arrest Warrant Case: Manohar M. Galani vs. State of Gujarat (2019)

What Weighed in the Mind of the Court?

The Supreme Court’s decision was primarily influenced by the following factors:

  • The clear intention of both parties to execute a formal Power Purchase Agreement (PPA).
  • The absence of agreement on essential terms beyond tariff, quantity, and tenure, such as penalty clauses, grid support charges, and other operational details.
  • The statutory mandate of the Karnataka Electricity Reforms Act, 1999, which aimed to regulate tariffs through an independent commission.
  • The need to balance consumer interests with the need for fair charges for electricity supply.
  • The fact that the parties were not ad idem on several aspects, and these issues were expressly left for negotiations as indicated in letter dated 23.04.1999.
Sentiment Percentage
Emphasis on the need for a formal PPA 40%
Importance of statutory compliance 30%
Lack of agreement on essential terms 20%
Balancing consumer and supplier interests 10%
Category Percentage
Fact 40%
Law 60%

Did the parties intend to have a formal PPA?

Were all essential terms agreed upon before 01.06.1999?

Were the parties ad idem on all aspects including penalty clauses, grid support charges etc.?

Was there a concluded contract before the Act’s commencement?

No, there was no concluded contract under the proviso to Section 27(2) of the Act.

The Court reasoned that while a formal PPA was not explicitly required by the proviso, the conduct of the parties and the correspondence showed that they intended to be bound by a written agreement, which included essential terms that were not agreed upon before the Act came into force. The Court emphasized that the proviso to Section 27(2) protected contracts where parties were ad idem on all essential terms, which was not the case here.

The Court made the following key observations:

  • “The proviso to Section 27(2), does not use the words ‘power purchase agreement’.”
  • “The parties clearly contemplated that there should be a PPA whereupon alone a concluded contract would emerge.”
  • “The correspondence in this case establish a completely different factual matrix. Both before 01.06.1999 and thereafter, the parties clearly contemplated the execution of the PPA.”

Key Takeaways

The Supreme Court’s judgment has several practical implications:

  • Contracts related to electricity tariffs must be clearly concluded with all essential terms agreed upon before the enactment of relevant legislation to be protected under the proviso to Section 27(2) of the Act.
  • The intention of the parties, as evidenced by their conduct and correspondence, is crucial in determining the existence of a binding contract.
  • The regulatory oversight of the Karnataka Electricity Regulatory Commission cannot be circumvented by claiming a contract, unless all the essential terms are clearly agreed upon before the Act’s commencement.
  • The mere agreement on tariff, quantity and tenure is not enough to constitute a concluded contract.

Directions

The Supreme Court directed JSW Energy to pay Rs. 50 crores to KPTCL within eight weeks. The final disbursement of this amount will depend on the High Court’s decision after reconsideration. The High Court was directed to reconsider the issues relating to the status of JSW Energy as an IPP or CPP and the perversity of the Commission’s orders.

Development of Law

The ratio decidendi of the case is that a contract, to be protected under the proviso to Section 27(2) of the Karnataka Electricity Reforms Act, 1999, must be fully concluded with all essential terms agreed upon before the Act’s commencement. The Court clarified that the mere agreement on tariff, quantity, and tenure is insufficient, and the parties’ intention to execute a formal PPA must be considered. The Court also held that the parties were not ad idem on all aspects and these issues were expressly left for negotiations as indicated in letter dated 23.04.1999. This ruling clarifies the scope of “concluded contracts” under the Act and emphasizes the importance of formal agreements in such complex transactions. This ruling also sets aside the High Court’s view that a contract could be concluded even without a formal PPA.

Conclusion

The Supreme Court partly allowed the appeal, setting aside the High Court’s judgment that a concluded contract existed between KPTCL and JSW Energy before the enactment of the Karnataka Electricity Reforms Act, 1999. The Court emphasized the need for a formal PPA and the agreement of all essential terms. The case was remitted to the High Court for reconsideration of the status of JSW Energy as an IPP or CPP and the perversity of the Commission’s orders.