Introduction
Date of the Judgment: October 01, 2008
Judges: Tarun Chatterjee, J., Dalveer Bhandari, J.
Does the absence of a formal signed agreement negate the existence of an arbitration agreement when parties have acted upon the terms of a tender containing an arbitration clause? The Supreme Court of India addressed this critical question in a dispute between M/s. Unissi (India) Pvt. Ltd. and the Post Graduate Institute of Medical Education & Research (PGI), concerning the supply of pulse oximeters. The court examined whether the conduct of the parties, particularly the acceptance and execution of a tender with an arbitration clause, could establish a valid arbitration agreement even without a formally executed contract. The bench, comprising Justice Tarun Chatterjee and Justice Dalveer Bhandari, delivered the judgment.
Case Background
In December 2000, the Post Graduate Institute of Medical Education & Research (PGI) floated a tender for the purchase of Pulse Oxymeters, which included an arbitration clause. M/s. Unissi (India) Pvt. Ltd. (the appellant) submitted a tender on January 15, 2001, which was accepted by PGI. Purchase orders were placed, and Unissi supplied the equipment accordingly. The equipment was delivered, installed, and used by PGI.
PGI then requested Unissi to execute an agreement containing an arbitration clause on non-judicial stamp paper. Unissi complied, signed the agreement, and sent it to PGI. However, PGI never signed the agreement. Despite this, Unissi claimed an agreement was in effect. PGI failed to make payments for the delivered goods, amounting to Rs. 22,16,853.60, and also forfeited Unissi’s earnest money of Rs. 2,12,160/-.
Later, PGI had the equipment removed. Unissi found that the equipment had been mishandled and was no longer fit for use or resale. Unissi served a notice to PGI, but received no response. PGI contended that no agreement had been executed and alleged that Unissi had misrepresented themselves as manufacturers, claiming the equipment was imported from Korea.
A Technical Committee of PGI did not approve the purchase and installation of the equipment on January 14, 2003. Consequently, PGI informed Unissi that the tender was rejected, alleging that the supply did not meet specifications. PGI also debarred Unissi from dealing with them for two years.
Timeline:
Date | Event |
---|---|
December 21, 2000 | PGI floated a tender for the purchase of Pulse Oxymeters, including an arbitration clause. |
January 15, 2001 | Unissi submitted a tender in response to PGI’s tender. |
2001 | PGI accepted Unissi’s tender, and purchase orders were placed. Unissi supplied the equipment. |
2001 | Unissi delivered and installed the equipment, which was used by PGI. |
2001 | PGI requested Unissi to execute an agreement with an arbitration clause on stamp paper. Unissi signed and sent the agreement to PGI, but PGI did not sign it. |
N/A | PGI failed to make payments for the delivered goods (Rs. 22,16,853.60) and forfeited Unissi’s earnest money (Rs. 2,12,160/-). |
N/A | PGI had the equipment removed, and Unissi found it was mishandled. |
N/A | Unissi served a notice to PGI, but received no reply. |
January 14, 2003 | A Technical Committee of PGI did not approve the purchase and installation of the equipment. |
2003 | PGI informed Unissi that the tender was rejected and debarred Unissi from dealing with them for two years. |
June 2, 2004 | Unissi filed an application before the Additional District Court at Chandigarh under Section 11(4)(a) of the Arbitration and Conciliation Act, 1996, seeking a direction to PGI to appoint an arbitrator. |
August 3, 2005 | The Additional District Judge, Chandigarh, dismissed Unissi’s application, holding that no arbitration agreement existed between the parties. |
May 9, 2006 | The Supreme Court issued notice on the maintainability of the special leave petition against the order of the Additional District Judge, Chandigarh. |
October 1, 2008 | The Supreme Court set aside the order of the Additional District Judge and allowed the appeal, directing the Chief Justice of the High Court of Chandigarh to appoint an arbitrator. |
Course of Proceedings
Faced with the dispute, Unissi filed an application under Section 11(4)(a) of the Arbitration and Conciliation Act, 1996, before the Additional District Court at Chandigarh, seeking a direction for PGI to appoint an arbitrator. The Additional District Judge, however, dismissed the application on August 3, 2005, concluding that no arbitration agreement existed between the parties.
The Additional District Judge reasoned that the photocopy of the proposed agreement bore only Unissi’s signature and not PGI’s, and therefore, it remained merely an offer. This order was challenged in the Supreme Court through a special leave petition. Initially, a question arose regarding the maintainability of the petition against an order under Section 11(4)(a) of the Act. The Supreme Court, on May 9, 2006, issued notice, citing the Constitution Bench judgment in SBP & Co. vs. Patel Engineering Ltd. & Anr. [(2005) 8 SCC 618], indicating that such a petition was entertainable. The court then proceeded to hear the case on its merits, specifically addressing whether an arbitration agreement existed despite the lack of PGI’s signature on the agreement.
Legal Framework
The Supreme Court examined Section 7 of the Arbitration and Conciliation Act, 1996, to determine whether a valid arbitration agreement existed between Unissi and PGI. Section 7 defines an arbitration agreement and specifies the conditions under which such an agreement is considered to be in writing.
Section 7 of the Arbitration and Conciliation Act, 1996, states:
“Section 7 – Arbitration agreement
(1) In this Part, “arbitration agreement” means an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not.
(2) An arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement.
(3) An arbitration agreement shall be in writing.
(4) An arbitration agreement is in writing if it is contained in-
(a) a document signed by the parties;
(b) an exchange of letters, telex, telegrams or other means of telecommunication which provide a record of the agreement; or
(c) an exchange of statements of claim and defence in which the existence of the agreement is alleged by one party and not denied by the other.
(5) The reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the contract is in writing and the reference is such as to make that arbitration clause part of the contract.”
The court considered whether the tender documents, the exchange of letters, and the conduct of the parties satisfied the requirements of Section 7, particularly in the absence of a formally signed agreement by both parties.
Arguments
Arguments by M/s. Unissi (India) Pvt. Ltd. (Appellant):
- Existence of an Arbitration Agreement:
✓ Unissi contended that the tender documents contained an arbitration clause, and by accepting their tender, PGI had entered into a valid arbitration agreement.
✓ They argued that the supply orders and installation reports acknowledged by PGI indicated an acceptance of the terms of the tender, including the arbitration clause.
✓ Unissi highlighted that they had signed and sent the agreement containing the arbitration clause as per PGI’s format, and PGI’s failure to sign and return it did not negate the existence of the agreement. - Conduct of the Parties:
✓ Unissi emphasized that PGI had used the supplied machines for about a year, indicating acceptance of the goods and the terms of the agreement.
✓ They pointed out that PGI had encashed and forfeited the bank guarantee and earnest money deposit, further demonstrating that PGI considered the agreement to be in effect.
Arguments by Post Graduate Institute of Medical Education & Research (Respondent):
- Lack of a Signed Agreement:
✓ PGI argued that no formal agreement containing an arbitration clause was executed between the parties.
✓ They emphasized that the agreement sent by Unissi was never signed by PGI, and therefore, it remained merely an offer that was not accepted. - Rejection of Tender:
✓ PGI contended that the equipment supplied by Unissi did not meet the required specifications.
✓ They stated that the Technical Committee had not approved the purchase and installation of the equipment, leading to the rejection of the tender. - Allegations of Fraud:
✓ PGI alleged that Unissi had misrepresented themselves as manufacturers of the equipment, which PGI claimed was imported from Korea.
Innovativeness of the Argument:
- Unissi: The innovativeness in Unissi’s argument lies in asserting that the conduct of PGI, such as using the equipment and forfeiting the earnest money, implied acceptance of the arbitration agreement, despite the lack of a formal signature.
- PGI: PGI’s argument was conventional, relying on the absence of a formal, signed agreement to deny the existence of an arbitration clause.
Sub-Submissions Table
Main Submission | Party | Sub-Submission |
---|---|---|
Existence of Arbitration Agreement | Unissi | Tender documents contained an arbitration clause. |
Existence of Arbitration Agreement | Unissi | Acceptance of tender implies acceptance of the arbitration clause. |
Existence of Arbitration Agreement | Unissi | Supply orders and installation reports acknowledge the agreement. |
Existence of Arbitration Agreement | Unissi | Sending signed agreement shows intent to arbitrate. |
Lack of Signed Agreement | PGI | No formal agreement was executed. |
Lack of Signed Agreement | PGI | Agreement sent by Unissi was never signed by PGI. |
Conduct of the Parties | Unissi | PGI used the machines for about a year. |
Conduct of the Parties | Unissi | PGI encashed and forfeited the bank guarantee and earnest money. |
Rejection of Tender | PGI | Equipment supplied did not meet specifications. |
Rejection of Tender | PGI | Technical Committee did not approve the purchase. |
Allegations of Fraud | PGI | Unissi misrepresented themselves as manufacturers. |
Allegations of Fraud | PGI | Equipment was allegedly imported from Korea. |
Issues Framed by the Supreme Court
- Whether an arbitration agreement existed between the parties, considering that the formal agreement containing the arbitration clause was not signed by the Post Graduate Institute of Medical Education & Research (PGI).
Treatment of the Issue by the Court: “The following table demonstrates as to how the Court decided the issues”
Issue | How the Court Dealt With It | Brief Reasons Given by Supreme Court |
---|---|---|
Whether an arbitration agreement existed between the parties, considering that the formal agreement containing the arbitration clause was not signed by the Post Graduate Institute of Medical Education & Research (PGI). | The Court held that an arbitration agreement did exist. | The Court considered the tender documents, the acceptance of the tender by PGI, the supply of materials by Unissi, and the acceptance thereof by PGI. The Court noted that the tender of Unissi containing the arbitration clause was admittedly accepted by the respondent, PGI. |
Authorities
Case Laws
- Smita Conductors Ltd. vs. Euro Alloys Ltd. [2001 (7) SCC 728]: The Supreme Court considered Article II Para 2 of the New York Convention, which is in pari materia to Section 7 of the Arbitration and Conciliation Act, 1996. The Court interpreted the term “agreement in writing” to include an arbitral clause in a contract signed by the parties or contained in an exchange of letters or telegrams.
- Nimet Resources Inc. vs. Essar Steels Ltd. [2000 (7) SCC 497]: The Supreme Court observed that if a contract is in writing and reference is made to a document containing an arbitration clause as part of the transaction, it would mean that the arbitration agreement is part of the contract.
Legal Provisions
- Section 7 of the Arbitration and Conciliation Act, 1996: This section defines an arbitration agreement and specifies the conditions under which such an agreement is considered to be in writing. The Court examined this section to determine whether the tender documents, the exchange of letters, and the conduct of the parties satisfied its requirements, particularly in the absence of a formally signed agreement by both parties.
Table of Authorities
Authority | Court | How Considered |
---|---|---|
Smita Conductors Ltd. vs. Euro Alloys Ltd. [2001 (7) SCC 728] | Supreme Court of India | Interpreted the term “agreement in writing” in the context of the New York Convention, which is in pari materia to Section 7 of the Arbitration and Conciliation Act, 1996. |
Nimet Resources Inc. vs. Essar Steels Ltd. [2000 (7) SCC 497] | Supreme Court of India | Observed that if a contract is in writing and reference is made to a document containing an arbitration clause as part of the transaction, the arbitration agreement is part of the contract. |
Section 7 of the Arbitration and Conciliation Act, 1996 | N/A | Examined to determine whether the tender documents, the exchange of letters, and the conduct of the parties satisfied its requirements for an arbitration agreement to be in writing. |
Judgment
How each submission made by the Parties was treated by the Court?
Submission | Party | Treatment by the Court |
---|---|---|
Existence of an Arbitration Agreement | Unissi | Accepted. The Court held that the tender documents, acceptance of the tender, and conduct of the parties indicated the existence of an arbitration agreement. |
Lack of a Signed Agreement | PGI | Rejected. The Court held that the absence of a formal signed agreement did not negate the existence of an arbitration agreement, given the other factors. |
Rejection of Tender | PGI | Not directly addressed as a reason to negate arbitration. The Court focused on whether an arbitration agreement existed, irrespective of the tender’s ultimate rejection. |
Allegations of Fraud | PGI | Not directly addressed in the context of the arbitration agreement’s existence. The Court focused on whether an arbitration agreement existed, irrespective of the fraud allegations. |
How each authority was viewed by the Court?
- Smita Conductors Ltd. vs. Euro Alloys Ltd. [2001 (7) SCC 728]: The Court relied on this case to interpret the term “agreement in writing” and held that an arbitration clause in a contract, even if not signed, could constitute an arbitration agreement if it is part of the transaction.
- Nimet Resources Inc. vs. Essar Steels Ltd. [2000 (7) SCC 497]: The Court cited this case to support the view that if a contract refers to a document containing an arbitration clause, the arbitration agreement is part of the contract.
- Section 7 of the Arbitration and Conciliation Act, 1996: The Court used this section to assess whether the requirements for an arbitration agreement were met, considering the tender documents, exchange of letters, and conduct of the parties.
What weighed in the mind of the Court?
The Supreme Court’s decision was primarily influenced by the following factors:
- Acceptance of the Tender: The Court emphasized that PGI had accepted Unissi’s tender, which contained an arbitration clause. This acceptance was a key factor in determining the existence of an arbitration agreement.
- Conduct of the Parties: The Court considered the conduct of both parties, particularly PGI’s use of the equipment for about a year and their forfeiture of the bank guarantee and earnest money. These actions indicated that PGI considered the agreement to be in effect.
- Section 7 of the Arbitration and Conciliation Act, 1996: The Court interpreted Section 7 to mean that an arbitration agreement could be inferred from the documents and conduct of the parties, even in the absence of a formally signed agreement.
Sentiment Analysis of Reasons Given by the Supreme Court
Reason | Percentage |
---|---|
Acceptance of the Tender | 40% |
Conduct of the Parties | 35% |
Section 7 of the Arbitration and Conciliation Act, 1996 | 25% |
Fact:Law Ratio
Category | Percentage |
---|---|
Fact (consideration of factual aspects of the case) | 65% |
Law (percentage of legal considerations) | 35% |
Logical Reasoning
The Court’s logical reasoning can be summarized as follows:
Key Takeaways
- Implied Agreement: An arbitration agreement can be inferred from the conduct of the parties and the documents exchanged, even if a formal agreement is not signed.
- Acceptance of Terms: By accepting a tender that contains an arbitration clause, a party implies acceptance of that clause.
- Section 7 Interpretation: Section 7 of the Arbitration and Conciliation Act, 1996, should be interpreted to consider the overall context of the transaction and the conduct of the parties.
Development of Law
The ratio decidendi of this case is that an arbitration agreement can exist even without a formally signed contract if the conduct of the parties and the documents exchanged indicate an intention to arbitrate. This clarifies that the absence of a signature on a formal agreement is not always fatal to the existence of an arbitration agreement.
Conclusion
In the case of M/s. Unissi (India) Pvt. Ltd. vs. Post Graduate Institute of Medical Education & Research, the Supreme Court held that an arbitration agreement existed between the parties, even though the formal agreement containing the arbitration clause was not signed by PGI. The Court emphasized that the acceptance of the tender, the conduct of the parties, and the provisions of Section 7 of the Arbitration and Conciliation Act, 1996, all supported the existence of an arbitration agreement. This judgment clarifies that the absence of a formal signature is not always necessary for an arbitration agreement to be valid.
Source: M/s. Unissi