LEGAL ISSUE: Whether an arbitral award can be set aside for perversity when the tribunal’s findings are based on a possible interpretation of the evidence, and whether the court can re-evaluate evidence in such cases.

CASE TYPE: International Commercial Arbitration

Case Name: Anglo American Metallurgical Coal Pty Ltd. vs. MMTC Ltd.

[Judgment Date]: 17 December 2020

Introduction

Date of the Judgment: 17 December 2020

Citation: (2020) INSC 957

Judges: Justice Rohinton Fali Nariman and Justice K.M. Joseph

Can a court overturn an arbitrator’s decision simply because it sees the facts differently? The Supreme Court of India recently addressed this crucial question in a dispute between an Australian coal company and an Indian trading corporation. The core issue revolved around whether an arbitral award, based on a possible interpretation of the facts, could be set aside for being “perverse”. The judgment was delivered by a two-judge bench comprising Justice Rohinton Fali Nariman and Justice K.M. Joseph, with Justice Nariman authoring the opinion.

Case Background

Anglo American Metallurgical Coal Pty Ltd. (the Appellant), an Australian company, had a long-term agreement (LTA) with MMTC Ltd. (the Respondent), an Indian company, to supply coking coal. The LTA, dated 07 March 2007, specified the quantity and quality of coal to be supplied over several delivery periods. The dispute arose during the fifth delivery period (1 July 2008 to 30 September 2009, extended by mutual agreement), when the Respondent failed to lift the contracted quantity of coal. The Appellant claimed damages for breach of contract, while the Respondent argued that the Appellant was unable to supply the coal.

The core of the dispute was whether the Appellant was ready to supply the coal at the agreed price of $300 per metric tonne during the Fifth Delivery Period, and whether the Respondent was in breach of contract by not lifting the contracted quantity of 466,000 metric tonnes. The Respondent only lifted 11,966 metric tonnes, leaving a shortfall of 454,034 metric tonnes.

Timeline

Date Event
07 March 2007 Long Term Agreement (LTA) signed between Anglo American Metallurgical Coal Pty Ltd. and MMTC Ltd.
1 July 2008 to 30 June 2009 Fifth Delivery Period as per the LTA
14 August 2008 Fifth Delivery Period extended to 30 September 2009 by mutual agreement
20 November 2008 MMTC confirms the agreed price of US$300 per MT for the Fifth Delivery Period.
30 October 2008 MMTC lifted 2,366 MT of coal.
11 March 2009 Anglo American requests MMTC to propose a Delivery Schedule.
2 July 2009 MMTC requests Anglo American to indicate stem availability for two deliveries.
5 August 2009 MMTC lifted another 9,600 MT of coal.
22 July 2009 Anglo American states it cannot confirm stem availability due to cargo availability.
7 September 2009 Anglo American states it does not have any coal availability for the remainder of the year.
21 September 2009 Anglo American refers to its letter of 11 March 2009 and states that the Fifth Delivery Period has ended.
25 September 2009 MMTC responds to Anglo American’s letter, admitting its obligation but requesting a staggered time frame for lifting the coal.
24 September 2012 Anglo American initiates arbitration proceedings.
12 May 2014 Arbitral Tribunal issues a majority award in favor of Anglo American.
10 July 2015 Single Judge of the Delhi High Court upholds the majority award.
02 March 2020 Division Bench of the Delhi High Court sets aside the single judge’s decision and the majority award.
17 December 2020 Supreme Court of India allows the appeal, setting aside the Division Bench’s judgment and restoring the majority award.

Course of Proceedings

The dispute was initially referred to an Arbitral Tribunal consisting of Mr. Peter Leaver, Justice V.K. Gupta (Retd.), and Mr. Anthony Houghton. The Tribunal delivered a majority award in favor of the Appellant, with Justice Gupta dissenting. The majority found that the Respondent had breached the contract by not lifting the contracted quantity of coal and awarded damages to the Appellant. The Single Judge of the High Court of Delhi upheld the majority award. However, the Division Bench of the High Court set aside the Single Judge’s decision and the majority award, stating that the majority award was based on no evidence and was perverse.

Legal Framework

The case primarily involves the interpretation and application of the Arbitration and Conciliation Act, 1996, specifically Section 34, which deals with setting aside arbitral awards. The court also considered the principles of contract law and the rules of evidence, particularly Sections 92, 94 and 95 of the Indian Evidence Act, 1872, which govern the admissibility of evidence to interpret contracts.

Section 34 of the Arbitration and Conciliation Act, 1996 allows a court to set aside an arbitral award if it is in conflict with the public policy of India, which includes cases where the award is perverse or based on no evidence. The Indian Evidence Act, 1872, particularly Section 94, states that when the language of a document is plain and applies accurately to existing facts, no evidence can be given to show that it was not meant to apply to those facts. However, proviso (6) to Section 92 of the Evidence Act states that any fact can be proven to show how the language of a document is related to existing facts. Section 95 of the Evidence Act states that when the language used in a document is plain in itself, but is unmeaning in reference to existing facts, evidence may be given to show that it was used in a peculiar sense.

See also  Supreme Court rules User Development Fee not subject to Service Tax: Central GST Delhi vs. Delhi International Airport Ltd. (2023)

Arguments

Appellant’s Arguments:

  • The Appellant argued that the Majority Award was based on a detailed examination of the facts and that the Division Bench erred in cherry-picking three emails while ignoring the overall context of the correspondence.
  • The Appellant contended that it was ready and willing to supply the coal at the agreed price, but the Respondent was unwilling to lift the coal due to a slump in the market.
  • The Appellant emphasized that the Arbitral Tribunal had correctly interpreted the evidence, including the testimony of Mr. Wilcox, and that the Division Bench’s finding of “no evidence” was incorrect.
  • The Appellant relied on its letter dated 11.03.2009 requesting a Delivery Schedule, and the Respondent’s letter dated 25.09.2009 admitting its obligation to lift the coal at the contractual price.

Respondent’s Arguments:

  • The Respondent argued that the Appellant was unable to supply the coal, as evidenced by the emails dated 02.07.2009, 22.07.2009 and 07.09.2009, where the Appellant stated that it had no coal available.
  • The Respondent contended that the Majority Award was perverse as it ignored these clear statements and relied on oral evidence to contradict the plain meaning of the emails.
  • The Respondent argued that there was no evidence to prove the market price of coal at the time of breach, and that the damages were incorrectly calculated.
  • The Respondent relied on clause 7.2 and Annexure IV of the LTA, stating that it was incumbent upon the Appellant to ensure that sufficient quantities of coal were available.

Sub-Submissions Table:

Main Submission Sub-Submission (Appellant) Sub-Submission (Respondent)
Breach of Contract ✓ Respondent breached by not lifting coal despite Appellant’s readiness to supply. ✓ Appellant breached by stating unavailability of coal in emails.
Availability of Coal ✓ Appellant had sufficient coal, supported by Mr. Wilcox’s evidence and distress sales. ✓ Appellant’s emails show lack of coal availability.
Price of Coal ✓ Respondent sought lower prices due to market slump. ✓ No evidence that Respondent sought lower prices, only that Appellant was unable to supply.
Evidence and Interpretation ✓ Majority Award correctly interpreted all correspondence and evidence. ✓ Majority Award cherry-picked evidence and ignored plain meaning of emails.
Damages ✓ Damages were correctly calculated based on market price and contractual price. ✓ No evidence to prove market price of coal at the time of breach.

Issues Framed by the Supreme Court

The Supreme Court framed the following key issues:

  1. Whether the Division Bench of the High Court was correct in setting aside the majority award of the Arbitral Tribunal.
  2. Whether the Majority Award was perverse and based on no evidence.
  3. Whether the Division Bench correctly applied the principles of Sections 92, 94 and 95 of the Indian Evidence Act, 1872.

Treatment of the Issue by the Court

The following table demonstrates as to how the Court decided the issues:

Issue Court’s Decision Brief Reasons
Whether the Division Bench was correct in setting aside the majority award Incorrect The Division Bench erred by cherry-picking three emails and ignoring the overall context of the correspondence and evidence.
Whether the Majority Award was perverse and based on no evidence No The Majority Award was based on a possible interpretation of the evidence and cannot be considered perverse. The tribunal considered all the evidence and came to a possible conclusion.
Whether the Division Bench correctly applied the principles of Sections 92, 94 and 95 of the Indian Evidence Act, 1872 Incorrect The Division Bench misapplied Section 94 by not considering the entire context of the correspondence. The court also stated that Section 95 of the Evidence Act could apply to the facts of the present case.

Authorities

The Supreme Court relied on the following authorities:

Authority Legal Point How Considered
Associate Builders v. DDA, (2015) 3 SCC 49 [Supreme Court of India] Parameters of judicial review of arbitral awards Explained the grounds for setting aside an arbitral award, including perversity and public policy.
Renusagar Power Co. Ltd. v. General Electric Co., 1994 Supp (1) SCC 644 [Supreme Court of India] Heads of challenge to arbitral awards Discussed the grounds for challenging an arbitral award, which were further elaborated in later judgments.
ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705 [Supreme Court of India] Patent illegality as a ground for challenge Introduced “patent illegality” as a ground for setting aside arbitral awards.
Smt. Kamala Devi v. Takhatmal and Anr., (1964) 2 SCR 152 [Supreme Court of India] Interpretation of documents and application of Section 94 of the Evidence Act Explained the application of Section 94 of the Evidence Act regarding plain language in documents.
Raghunandan v. Kirtyanand, AIR 1932 PC 131 [Privy Council] Interpretation of ambiguous surety bonds Discussed the interpretation of ambiguous documents in light of surrounding circumstances.
Murlidhar Chiranjilal v. Harishchandra Dwarkadas and Anr., (1962) 1 SCR 653 [Supreme Court of India] Measure of damages for breach of contract Established the method for calculating damages in breach of contract cases.
Sudarsan Trading Co. v. Govt. of Kerala, (1989) 2 SCC 38 [Supreme Court of India] Arbitral tribunal as the final judge of evidence Stated that the arbitral tribunal is the final judge of the quality and quantity of evidence.
Transmission Corpn. of Andhra Pradesh Ltd. v. GMR Vemagiri Power Generation Ltd., (2018) 3 SCC 716 [Supreme Court of India] Interpretation of contracts Emphasized considering surrounding facts and circumstances for interpreting contracts.
Bank of India v. K. Mohandas, (2009) 5 SCC 313 [Supreme Court of India] Construction of contracts Stated that the true construction of a contract depends on the words used, not subsequent conduct.
Zurich Insurance (Singapore) Pte Ltd v B-Gold Interior Design & Construction Pte Ltd, [2008] SGCA 27 [Court of Appeal of Singapore] Interpretation of contracts Discussed the admissibility of extrinsic evidence in interpreting contracts.
MMTC Ltd. v. Vedanta Ltd., (2019) 4 SCC 163 [Supreme Court of India] Scope of interference with arbitral awards Clarified the limited grounds for interfering with arbitral awards under Section 34.
Dyna Technologies Pvt. Ltd. v. Cromptom Greaves Ltd., 2019 SCC Online SC 1656 [Supreme Court of India] Interference with arbitral awards Stated that courts should not interfere with awards unless they are perverse.
Parsa Kente Collieries Ltd. v. Rajasthan Rajya Vidyut Utpadan Nigam Ltd., (2019) 7 SCC 236 [Supreme Court of India] Perversity in arbitral awards Discussed the test for perversity in arbitral awards.
South East Asia Marine Engg. & Constructions Ltd. (SEAMEC LTD.) v. Oil India Ltd., (2020) 5 SCC 164 [Supreme Court of India] Interpretation of contract terms Held that the interpretation of contract terms must be a possible one.
Patel Engg. Ltd. v. North Eastern Electric Power Corpn. Ltd., (2020) 7 SCC 167 [Supreme Court of India] Application of perversity test Applied the test of perversity in the context of contract interpretation.
Section 34, Arbitration and Conciliation Act, 1996 Setting aside arbitral awards Governs the grounds for setting aside arbitral awards.
Sections 92, 94 and 95, Indian Evidence Act, 1872 Admissibility of evidence to interpret contracts Governs the use of extrinsic evidence in interpreting contracts.
See also  Supreme Court Allows Withdrawal of Petitions on NCCF's Status as 'State' in Service Law Matters (07 January 2022)

Judgment

How each submission made by the Parties was treated by the Court?

Submission Court’s Treatment
Appellant’s submission that the Division Bench erred in cherry-picking three emails Accepted. The Supreme Court agreed that the Division Bench had incorrectly focused on three emails without considering the entire context.
Appellant’s submission that the Majority Award was based on a possible interpretation of evidence Accepted. The Supreme Court found that the Majority Award was a possible view based on the evidence and not perverse.
Appellant’s submission that the Division Bench had incorrectly applied Sections 92, 94, and 95 of the Evidence Act Accepted. The Supreme Court agreed that the Division Bench had misapplied Section 94 and that Section 95 was applicable.
Respondent’s submission that the Appellant was unable to supply coal Rejected. The Supreme Court found that the Appellant was ready to supply the coal and that the Respondent’s claim was not supported by the evidence.
Respondent’s submission that the Majority Award was perverse Rejected. The Supreme Court held that the Majority Award was not perverse and was based on a possible interpretation of the evidence.
Respondent’s submission that there was no evidence to prove the market price of coal Rejected. The Supreme Court held that the market price was established through the evidence of Mr. Wilcox and other contemporaneous correspondence.

How each authority was viewed by the Court?

✓The Supreme Court relied on Associate Builders v. DDA, (2015) 3 SCC 49* to define the scope of judicial review of arbitral awards. The court held that the Division Bench had exceeded its jurisdiction by re-evaluating the evidence.

✓The Court used Smt. Kamala Devi v. Takhatmal and Anr., (1964) 2 SCR 152* to explain the application of Section 94 of the Evidence Act. The Court held that the Division Bench had misapplied the principle by not considering the surrounding circumstances.

✓The Court followed Murlidhar Chiranjilal v. Harishchandra Dwarkadas and Anr., (1962) 1 SCR 653* to determine the measure of damages for breach of contract.

✓The Court referred to Transmission Corpn. of Andhra Pradesh Ltd. v. GMR Vemagiri Power Generation Ltd., (2018) 3 SCC 716* to emphasize that the terms of a contract should be interpreted by considering all surrounding facts and circumstances.

✓The Court considered Zurich Insurance (Singapore) Pte Ltd v B-Gold Interior Design & Construction Pte Ltd, [2008] SGCA 27* to understand the modern contextual approach to the interpretation of contracts.

What weighed in the mind of the Court?

The Supreme Court’s decision was heavily influenced by the principle that an arbitral award should not be lightly interfered with, especially when it is based on a possible interpretation of the facts. The Court emphasized that it is not a court of appeal and cannot re-evaluate evidence. The Court also highlighted that the Division Bench had erred by cherry-picking three emails and ignoring the overall context of the correspondence and the oral evidence of Mr. Wilcox. The Supreme Court also found that the Division Bench had misapplied the principles of Sections 92, 94 and 95 of the Indian Evidence Act, 1872.

Sentiment Analysis of Reasons given by the Supreme Court:

See also  Supreme Court directs equitable payment in construction dispute: Rajkamal Builders vs. Ahmedabad Municipal Corporation (2008)
Reason Percentage
Upholding the sanctity of arbitral awards 30%
Correct interpretation of evidence by the arbitral tribunal 25%
Misapplication of the Indian Evidence Act by the Division Bench 20%
The Division Bench’s flawed approach of cherry-picking emails 15%
The need to consider the overall context 10%

Fact:Law Ratio:

Category Percentage
Fact (consideration of factual aspects) 60%
Law (consideration of legal principles) 40%

Logical Reasoning:

Issue: Was the Division Bench correct in setting aside the arbitral award?
Analysis: Did the Division Bench re-evaluate evidence or apply the law incorrectly?
Finding: Division Bench re-evaluated evidence, misapplied Section 94 of the Evidence Act, and ignored the overall context.
Conclusion: Division Bench’s decision was incorrect. Majority Award is upheld.

Key Takeaways

  • Courts should not interfere with arbitral awards merely because they disagree with the arbitrator’s interpretation of facts.
  • The principle of non-interference in arbitral awards must be upheld unless there is a clear case of perversity or illegality.
  • When interpreting contracts, courts must consider the entire context of the correspondence and not just isolated documents.
  • The application of Section 94 of the Indian Evidence Act, 1872, must be done carefully, considering the surrounding circumstances and the peculiar sense in which words are used.
  • Arbitral tribunals are the final judges of the quality and quantity of evidence.

Directions

The Supreme Court set aside the judgment of the Division Bench and restored the majority award of the Arbitral Tribunal and the Single Judge’s judgment.

Development of Law

The ratio decidendi of this case is that a court cannot set aside an arbitral award merely because it disagrees with the arbitrator’s interpretation of facts, especially when the arbitrator’s view is a possible one. This judgment reinforces the principle of minimal judicial interference in arbitral awards and emphasizes that courts must respect the finality of the arbitral process. The Court also clarified the correct application of Sections 92, 94 and 95 of the Indian Evidence Act, 1872, in the context of interpreting contractual documents. There was no change in previous positions of law.

Conclusion

The Supreme Court allowed the appeal, setting aside the Division Bench’s judgment and restoring the majority award of the Arbitral Tribunal. The Court emphasized that the Arbitral Tribunal’s decision was a possible view based on the evidence and that the Division Bench had exceeded its jurisdiction by re-evaluating the evidence and misapplying the law. This judgment reinforces the principle of minimal judicial interference in arbitral awards and the importance of considering the entire context when interpreting contracts.