LEGAL ISSUE: Whether an arbitrator can award price escalation beyond the original contract period and grant interest for the pre-reference period under the Arbitration Act, 1940.

CASE TYPE: Arbitration

Case Name: Assam State Electricity Board and Ors. vs. Buildworth Pvt. Ltd.

[Judgment Date]: July 4, 2017

Introduction

Date of the Judgment: July 4, 2017

Citation: Not available in the provided text.

Judges: Jagdish Singh Khehar, CJI, Dr. D.Y. Chandrachud, J, Sanjay Kishan Kaul, J. The judgment was authored by Dr. D.Y. Chandrachud, J.

Can an arbitrator award price escalation for work completed beyond the original contract period, and can interest be awarded for the period before the arbitration reference? The Supreme Court of India recently addressed these questions in a dispute between the Assam State Electricity Board and Buildworth Pvt. Ltd., concerning the supply and installation of a water piping system. The core issue revolved around the validity of an arbitral award that granted price escalation and pre-reference interest to the claimant, Buildworth Pvt. Ltd.

Case Background

On September 6, 1982, the Assam State Electricity Board (the Board) and Buildworth Pvt. Ltd. (the claimant) entered into an agreement for the supply and installation of a circulating water piping system for the Bongaigaon Thermal Power Station. The contract was valued at Rs 86.82 lakhs, with a completion period of 12 months from June 25, 1983. The completion date was later extended to September 6, 1983. However, the work was actually completed on May 28, 1985, with a portion of the work completed on January 31, 1986. During the course of the arbitration, the claimant raised several claims amounting to Rs 77.16 lakhs, including price variation, idling charges, and interest.

Timeline

Date Event
September 6, 1982 Purchase order issued for the water piping system.
June 25, 1983 Original contract completion date.
September 6, 1983 Extended contract completion date.
May 28, 1985 Actual completion of most of the work.
January 31, 1986 Completion of work on TG-IV.
March 7, 1986 Claimant submitted bills, starting point for interest claim.
December 31, 1997 End date for the interest claim by the claimant.
December 31, 1998 Arbitral award issued.
December 22, 2000 Award made a rule of the court by Civil Judge.
November 21, 2006 Gauhati High Court partially upheld the award.
January 15, 2008 Leave granted in proceedings initiated by the Board.
April 20, 1987 Claimant issued legal notice claiming interest.
July 4, 2017 Supreme Court judgment.

Legal Framework

The case was primarily governed by the Arbitration Act, 1940, which was in force at the time of the arbitration. The key provisions of the Arbitration Act, 1940, relevant to this case include the power of the arbitrator to make an award and the court’s power to set aside an award. Additionally, the Interest Act, 1978, particularly Section 3(1)(b), played a crucial role in determining the award of interest on damages.

Section 3(1)(b) of the Interest Act, 1978 states:

“3. (1)(b) if the proceedings do not relate to any such debt, then, from the date mentioned in this regard in a written notice given by the person entitled or the person making the claim to the person liable that interest will be claimed, to the date of institution of the proceedings:”

Arguments

The Assam State Electricity Board (the Board) argued that:

  • Price Escalation: The arbitrator erred in awarding price escalation because Clause 2.3(a)(i) of the purchase order had fixed a ceiling of Rs 9,16,825 for price escalation, which had already been paid.

    The Board contended that the cap of Rs 9.16 lakhs was absolute and no further price escalation was permissible beyond it.
  • Idling Charges: The arbitrator erred in allowing the claim for idling charges of labor and machinery because the arbitrator had also found that the claimant contributed to the delay in the completion of the project.
  • Interest: No interest could be awarded prior to the date of the award, as the claim for damages gets quantified upon adjudication by the arbitrator.
See also  Supreme Court holds Reserve Bank of India not an "establishment" under Contract Labour Act: RBI vs. State (2008)

Buildworth Pvt. Ltd. (the claimant) argued that:

  • Price Escalation: Clause 2.3(a)(i) applied only for the specific period mentioned in the purchase order and not for the extended period of the contract.

    The claimant contended that the price escalation clause should not apply to the extended period of the contract.
  • Idling Charges: The claimant was entitled to idling charges due to the Board’s delay in handing over the work front and that additional items of work were required to be carried out which did not form part of the original work.
  • Interest: The arbitrator was correct in awarding interest for the pre-reference period, as there was no prohibition in the contract.

The innovativeness of the arguments was that the claimant argued that the price escalation clause should not apply to the extended period of the contract, which was not explicitly mentioned in the contract.

Summary of Arguments

Main Submission Sub-Submission (Assam State Electricity Board) Sub-Submission (Buildworth Pvt. Ltd.)
Price Escalation Clause 2.3(a)(i) fixed a ceiling of Rs 9,16,825; no further amount could be awarded. Clause 2.3(a)(i) applied only to the original contract period, not the extended period.
Idling Charges Claimant contributed to the delay; hence, no idling charges should be awarded. Additional work required separate mobilization of labor and machinery; claimant was entitled to idling charges.
Interest Interest could not be awarded prior to the date of the award. Arbitrator was correct in awarding interest for the pre-reference period.

Issues Framed by the Supreme Court

The Supreme Court considered the following issues:

  1. Whether the arbitrator committed an error in awarding the claim for price escalation beyond the ceiling fixed in the contract.
  2. Whether the arbitrator erred in allowing the claim for idling charges of labor and machinery, given that the claimant also contributed to the delay.
  3. Whether the arbitrator had the jurisdiction to award interest for the period prior to the reference.

Treatment of the Issue by the Court

The following table demonstrates as to how the Court decided the issues:

Issue Court’s Decision Reason
Price Escalation Upheld the arbitrator’s award. The price escalation clause did not apply to the extended period of the contract.
Idling Charges Upheld the arbitrator’s award. The arbitrator considered the contributory delay by the claimant and the need for separate mobilization for additional work.
Pre-reference Interest Allowed the award of interest. The arbitrator had the power to award interest for the pre-reference period, and the claimant had given a written notice claiming interest.

Authorities

The Supreme Court relied on the following authorities:

Cases

Case Name Court Relevance How the court used the authority
P.M. Paul Vs. Union of India [1989 Supp (1) SCC 368] Supreme Court of India Price escalation in case of delay. The Court cited this case to support the principle that escalation is a normal incident arising from delays and that an arbitrator has jurisdiction to award it. The Court noted that the arbitrator had the jurisdiction to determine whether there was a delay in the execution of the contract and the respondent was liable for the consequence of the delay, namely, an increase in price.
Food Corporation of India Vs. A.M. Ahmed & Co. and Another [(2006) 13 SCC 779] Supreme Court of India Arbitrator’s power to award escalation. The Court cited this case to reiterate that an arbitrator has the jurisdiction to award escalation due to delays caused by the other party. The Court held that the arbitrator did not misconduct himself by awarding wage revision.
K.N. Sathyapalan (Dead) by LRs Vs. State of Kerala and Another [(2007) 13 SCC 43] Supreme Court of India Arbitrator’s power to compensate for extra costs. The Court cited this case to emphasize that an arbitrator can compensate a party for extra costs incurred due to the other party’s failure to fulfill obligations. The Court noted that the principle was recognized in P.M. Paul case.
General Manager, Northern Railway Vs. Sarvesh Chopra [(2002) 4 SCC 45] Supreme Court of India Entitlement to damages for delayed performance. The Court cited this case to support the principle that if a party accepts the belated performance of reciprocal obligations, the other party is entitled to claim damages.
Secretary, Irrigation Department, Government of Orissa and Others Vs. G.C. Roy [(1992) 1 SCC 508] Supreme Court of India Power to award interest pendente lite. The Court relied on this Constitution Bench decision to state that an arbitrator has the power to award interest pendente lite if the agreement does not prohibit it.
Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa and Others Vs. N.C. Budharaj (Deceased) by LRs and Others [(2001) 2 SCC 721] Supreme Court of India Power to award pre-reference interest. The Court relied on this Constitution Bench decision to affirm the arbitrator’s power to award interest for the pre-reference period.
State of Rajasthan Vs. Ferro Concrete Construction Pvt. Ltd. [(2009) 12 SCC 1] Supreme Court of India Interest on damages under the Interest Act, 1978. The Court cited this case to hold that interest on damages can be awarded from the date mentioned in a written notice claiming such interest, as per the Interest Act, 1978.
Union of India Vs. Ambica Construction [(2016) 6 SCC 36] Supreme Court of India Arbitrator’s power to award interest. The Court cited this case to affirm the power of the arbitrator to award interest in the absence of a specific power or prohibition in the contract.
See also  Supreme Court clarifies limitation for counterclaims in banking disputes: Topline Shoes vs. Punjab National Bank (2022)

Legal Provisions

Provision Statute Relevance
Section 29 Arbitration Act, 1940 The High Court relied on this section to deny pre-reference interest, which was overturned by the Supreme Court.
Section 3(1)(b) Interest Act, 1978 The Supreme Court relied on this provision to hold that interest on damages can be awarded from the date mentioned in a written notice claiming such interest.

Judgment

How each submission made by the Parties was treated by the Court?

Submission Party Court’s Treatment
Price escalation was capped by Clause 2.3(a)(i) Assam State Electricity Board Rejected. The Court held that the clause applied only to the original contract period and not the extended period.
Arbitrator erred in awarding idling charges as the claimant also contributed to the delay Assam State Electricity Board Rejected. The Court held that the arbitrator had considered the claimant’s contribution to the delay.
No interest could be awarded prior to the date of the award Assam State Electricity Board Rejected. The Court held that the arbitrator had the power to award pre-reference interest.
Clause 2.3(a)(i) did not apply to the extended period. Buildworth Pvt. Ltd. Accepted. The Court agreed that the price escalation clause did not apply to the extended period of the contract.
Entitled to idling charges due to the Board’s delay and additional work Buildworth Pvt. Ltd. Accepted. The Court upheld the arbitrator’s decision on idling charges.
Arbitrator was correct in awarding interest for the pre-reference period Buildworth Pvt. Ltd. Accepted. The Court held that the arbitrator had the power to award pre-reference interest.

How each authority was viewed by the Court?

Authority Court’s View
P.M. Paul Vs. Union of India [1989 Supp (1) SCC 368]* Followed to support the principle that escalation is a normal incident arising from delays.
Food Corporation of India Vs. A.M. Ahmed & Co. and Another [(2006) 13 SCC 779]* Followed to reiterate that an arbitrator has the jurisdiction to award escalation due to delays.
K.N. Sathyapalan (Dead) by LRs Vs. State of Kerala and Another [(2007) 13 SCC 43]* Followed to emphasize that an arbitrator can compensate a party for extra costs incurred due to the other party’s failure to fulfill obligations.
General Manager, Northern Railway Vs. Sarvesh Chopra [(2002) 4 SCC 45]* Followed to support the principle that if a party accepts the belated performance of reciprocal obligations, the other party is entitled to claim damages.
Secretary, Irrigation Department, Government of Orissa and Others Vs. G.C. Roy [(1992) 1 SCC 508]* Followed to state that an arbitrator has the power to award interest pendente lite if the agreement does not prohibit it.
Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa and Others Vs. N.C. Budharaj (Deceased) by LRs and Others [(2001) 2 SCC 721]* Followed to affirm the arbitrator’s power to award interest for the pre-reference period.
State of Rajasthan Vs. Ferro Concrete Construction Pvt. Ltd. [(2009) 12 SCC 1]* Followed to hold that interest on damages can be awarded from the date mentioned in a written notice claiming such interest, as per the Interest Act, 1978.
Union of India Vs. Ambica Construction [(2016) 6 SCC 36]* Followed to affirm the power of the arbitrator to award interest in the absence of a specific power or prohibition in the contract.
Section 29, Arbitration Act, 1940 Overruled by the Supreme Court’s interpretation of the law.
Section 3(1)(b), Interest Act, 1978 Applied to allow pre-reference interest.
See also  Supreme Court Disposes of Appeal in Disciplinary Proceedings Against E K Narayanan (16 May 2018)

What weighed in the mind of the Court?

The Supreme Court’s decision was primarily influenced by the interpretation of the contract terms, the conduct of the parties, and established legal principles regarding arbitration and interest. The Court emphasized that the price escalation clause was limited to the original contract period and that the arbitrator had the power to award interest for the pre-reference period. The Court also noted that the arbitrator had considered the contributory delay by the claimant in awarding idling charges.

Sentiment Analysis of Reasons

Reason Percentage
Interpretation of Contract Terms 40%
Conduct of the Parties 30%
Established Legal Principles 30%

Fact:Law Ratio

Category Percentage
Fact 40%
Law 60%

Logical Reasoning

Issue 1: Price Escalation

Contract Clause 2.3(a)(i) specifies price ceiling
Claimant argues clause does not apply to extended period
Arbitrator agrees with claimant’s interpretation
Supreme Court upholds arbitrator’s decision

Issue 2: Idling Charges

Claimant seeks idling charges for labor and machinery
Board argues claimant contributed to the delay
Arbitrator considers contributory delay but awards charges for additional work
Supreme Court upholds arbitrator’s decision

Issue 3: Pre-reference Interest

Claimant seeks interest for the period before arbitration
Board argues no interest can be awarded prior to the award
Arbitrator awards interest
Supreme Court upholds arbitrator’s decision based on Interest Act, 1978

The Court rejected the argument that interest could only be awarded after the quantification of damages, citing the Interest Act, 1978, which allows for interest from the date of a written notice claiming such interest. The Court also emphasized that the arbitrator had the power to award interest for the pre-reference period, as there was no prohibition in the contract.

The Supreme Court’s decision was unanimous, with all three judges concurring.

The Court quoted from the judgment:

“The arbitrator has taken the view that the provision for price escalation would not bind the claimant beyond the scheduled date of completion.”

“The arbitrator has power to grant interest on damages under Section 3(1)(b) of the Interest Act, 1978, from the date mentioned in this regard in a written notice claiming such interest.”

“The contract in the present case contains no bar or prohibition against the award of interest.”

Key Takeaways

  • Arbitrators have the power to award price escalation for work done beyond the original contract period if the contract terms do not explicitly prohibit it.
  • Arbitrators can award interest for the pre-reference period if there is no prohibition in the contract, provided a written notice claiming such interest has been given.
  • Contributory delay by a claimant does not necessarily preclude them from receiving idling charges, provided the arbitrator takes this into account.

This judgment reinforces the powers of arbitrators to interpret contracts and award appropriate compensation, including price escalation and interest, in cases of delays and extended contract periods. It also clarifies the applicability of the Interest Act, 1978, in arbitration proceedings. The decision will likely influence future arbitration cases involving similar issues of price escalation and pre-reference interest.

Directions

The Supreme Court modified the rate of interest to 12% per annum from April 20, 1987, to December 31, 1997, and thereafter from the date of the trial court’s decree until payment or realization.

Specific Amendments Analysis

There is no discussion on any specific amendments in the judgment.

Development of Law

The ratio decidendi of this case is that an arbitrator has the power to award price escalation for work done beyond the original contract period if the contract terms do not explicitly prohibit it and can award interest for the pre-reference period if there is no prohibition in the contract, provided a written notice claiming such interest has been given. This decision clarifies the scope of an arbitrator’s powers under the Arbitration Act, 1940, and the applicability of the Interest Act, 1978, in arbitration proceedings. The Supreme Court has upheld the power of the arbitrator to award interest for the pre-reference period, thereby overruling the view taken by the High Court which had relied on Section 29 of the Arbitration Act, 1940.

Conclusion

The Supreme Court allowed the appeal filed by Buildworth Pvt. Ltd. and dismissed the appeal filed by the Assam State Electricity Board. The Court upheld the arbitrator’s award regarding price escalation and idling charges and modified the interest rate to 12% per annum. The judgment clarifies the powers of arbitrators to award price escalation and pre-reference interest, reinforcing the principle that contractual terms must be interpreted in light of the conduct of the parties and established legal principles.