LEGAL ISSUE: Whether a power generator is entitled to compensation for the increased costs of procuring coal due to a change in law and whether the unutilized monthly coal quota can be carried forward.

CASE TYPE: Electricity Regulatory Law

Case Name: Maharashtra State Electricity Distribution Company Limited vs. Rattan India Power Limited

Judgment Date: 27 March 2023

Date of the Judgment: 27 March 2023

Citation: 2023 INSC 299

Judges: B.R. Gavai, J. and Vikram Nath, J.

Can a power distribution company deny compensation to a power generator for increased coal procurement costs due to a change in law? The Supreme Court of India addressed this question in a recent case, clarifying the rights of power generators. The core issue revolved around whether a power generator should be compensated for the additional expenses incurred due to changes in coal supply regulations and whether the unutilized coal quota for a particular month can be carried forward to the next month. The judgment was delivered by a two-judge bench consisting of Justice B.R. Gavai and Justice Vikram Nath, with Justice B.R. Gavai authoring the opinion.

Case Background

The case involves a dispute between Maharashtra State Electricity Distribution Company Limited (DISCOM), the appellant, and Rattan India Power Limited, the respondent (Generator). The dispute arose from an order passed by the Appellate Tribunal for Electricity (APTEL) on 13.11.2020, which had directed the Maharashtra Electricity Regulatory Commission (MERC) to reconsider certain issues related to compensation for the generator. The generator sought compensation for the increased costs of procuring coal from alternative sources due to a shortfall in the supply of linkage coal and also for the change in law. The DISCOM, on the other hand, contended that the generator was being unduly benefited as the unutilized monthly coal quota was not being carried forward to the next month.

Timeline:

Date Event
13.11.2020 Appellate Tribunal for Electricity (APTEL) passed an order directing MERC to reconsider certain issues related to compensation for the generator.
27.03.2023 Supreme Court of India disposed of the appeal, upholding the APTEL order.

Course of Proceedings

The Appellate Tribunal for Electricity (APTEL) had set aside the order of the Maharashtra Electricity Regulatory Commission (MERC) dated 03.04.2018. The APTEL directed MERC to reconsider the issues of gross calorific value (GCV) of coal, compensation for change in law beyond 31.03.2017, and the full impact of additional costs incurred in procuring coal from alternative sources. The DISCOM appealed against this order of APTEL before the Supreme Court.

Legal Framework

The judgment references the following case laws:

  • Maharashtra State Electricity Distribution Company Ltd. v. Adani Power Maharashtra Limited and Others, 2023 SCC Online SC 233

  • Energy Watchdog v. Central Electricity Regulatory Commission and Others, (2017) 14 SCC 80

See also  Supreme Court Mandates Basic Toilet Facilities in All Courts: Rajeev Kalita vs. Union of India (2025)

These cases deal with issues related to compensation for power generators due to changes in law and the methodology for calculating such compensation.

Arguments

Arguments by the Distribution Company (DISCOM):

  • The DISCOM argued that the generator gets a specific quantity of coal for a particular month out of the Annual Contracted Quantity (ACQ). If the generator does not utilize the coal in that particular month, it should not be carried forward to the next month. This, according to the DISCOM, would give undue benefit to the generator.

Arguments by the Generator:

  • The generator submitted that the apprehension of the DISCOM was misconceived. They argued that the compensation for monthly coal quantum variation should not be calculated on an annual basis, as demand and offtake of coal changes month to month.
  • The generator explained that if compensation is calculated cumulatively on an annual basis, a surplus in one month might get set off against a shortfall in another month. They illustrated this with an example showing monthly variations in coal assured, coal delivered, and actual generation.
Main Submission Sub-Submissions Party
Monthly Coal Utilization Unutilized monthly coal quota should not be carried forward to the next month DISCOM
Monthly Coal Utilization Compensation for monthly coal variation should not be calculated annually Generator
Monthly Coal Utilization Demand and offtake of coal changes month to month Generator
Monthly Coal Utilization Surplus coal in one month should not be set off against shortfall in another month Generator

Issues Framed by the Supreme Court

The Supreme Court did not explicitly frame issues in this judgment. However, the core issues that the court addressed were:

  1. Whether the Appellate Tribunal for Electricity (APTEL) was correct in directing the Maharashtra Electricity Regulatory Commission (MERC) to reconsider the issues of gross calorific value (GCV) of coal and compensation for change in law.
  2. Whether the unutilized coal quantity for a particular month should be carried forward to the next month.

Treatment of the Issue by the Court

The following table demonstrates as to how the Court decided the issues:

Issue Court’s Decision Reason
Reconsideration of GCV and compensation for change in law Upheld APTEL’s direction to reconsider In line with the Supreme Court’s view in Maharashtra State Electricity Distribution Company Ltd. v. Adani Power Maharashtra Limited and Others (2023 SCC Online SC 233).
Carry forward of unutilized monthly coal quota Upheld that it can be carried forward The generator’s methodology of carrying forward surplus coal from one month to another was found to be reasonable and not detrimental to DISCOM.

Authorities

The Supreme Court relied on the following authorities:

Authority Court How it was used
Maharashtra State Electricity Distribution Company Ltd. v. Adani Power Maharashtra Limited and Others, 2023 SCC Online SC 233 Supreme Court of India Followed the view taken in this case regarding compensation for change in law.
Energy Watchdog v. Central Electricity Regulatory Commission and Others, (2017) 14 SCC 80 Supreme Court of India Followed the law laid down in this case regarding compensation for change in law.

Judgment

Submission by Parties Court’s Treatment
DISCOM’s submission that unutilized monthly coal should not be carried forward Rejected. The Court found the generator’s methodology of carrying forward surplus coal to be reasonable.
Generator’s submission that compensation should not be calculated on an annual basis Accepted. The Court agreed that demand and offtake of coal vary monthly, and compensation should be calculated accordingly.
See also  Supreme Court directs fresh maintenance proceedings in domestic dispute: Shalu Ojha vs. Prashant Ojha (23 July 2018)

How each authority was viewed by the Court?

  • Maharashtra State Electricity Distribution Company Ltd. v. Adani Power Maharashtra Limited and Others [2023 SCC Online SC 233]: The Court followed the view taken in this case and held that the direction No. 1 of the APTEL was in line with the view taken in this case.
  • Energy Watchdog v. Central Electricity Regulatory Commission and Others [(2017) 14 SCC 80]: The Court followed the law laid down in this case and held that the direction No. 2 of the APTEL was covered by the judgment of this Court in Adani Power Maharashtra Limited (supra) following the law laid down in this case.

What weighed in the mind of the Court?

The Court was primarily influenced by the need to ensure fair compensation to the power generator for the additional costs incurred due to changes in law and the practicalities of coal supply and demand. The court also found that the generator’s methodology for carrying forward surplus coal was reasonable and did not unduly benefit them.

Sentiment Percentage
Fair Compensation 40%
Practicalities of Coal Supply 30%
Reasonableness of Generator’s Methodology 30%
Ratio Percentage
Fact 60%
Law 40%

Logical Reasoning:

APTEL directs MERC to reconsider compensation issues

DISCOM appeals, arguing against carrying forward unutilized coal

Supreme Court examines generator’s methodology for coal usage

Supreme Court finds generator’s methodology reasonable

Supreme Court upholds APTEL’s order and dismisses DISCOM’s appeal

The court found that the generator’s method of carrying forward surplus coal was reasonable and did not unduly benefit them. The court also noted that the generator’s method of calculating compensation for monthly coal variations was more practical considering the monthly changes in demand and offtake of coal. The court observed:

“The chart itself would show that for the month of February the coal assured was 850 MW, the coal delivered was 800 MW and the actual generation was 700 MW. As such, for the said month the generator had surplus coal for production of 100 MW energy. The same has been carried forward for the month of March.”

The Court further observed:

“If this methodology is adopted by the generator, we do not find that the apprehension of the learned Additional Solicitor General of India would be substantiated.”

The court also relied on its previous judgments in Maharashtra State Electricity Distribution Company Ltd. v. Adani Power Maharashtra Limited and Others and Energy Watchdog v. Central Electricity Regulatory Commission and Others.

Key Takeaways

  • Power generators are entitled to compensation for increased costs of procuring coal due to changes in law.
  • The methodology for calculating compensation should consider monthly variations in coal demand and offtake.
  • Unutilized coal quantities for a particular month can be carried forward to the next month if the generator’s methodology is reasonable.

Directions

The Supreme Court did not provide any specific directions in this judgment. It upheld the directions given by the Appellate Tribunal for Electricity (APTEL).

Development of Law

The ratio decidendi of this case is that power generators are entitled to compensation for increased costs of procuring coal due to changes in law and the methodology for calculating such compensation should consider monthly variations in coal demand and offtake. The court has upheld the view that unutilized coal quantities for a particular month can be carried forward to the next month if the generator’s methodology is reasonable. This reinforces the principles laid down in previous cases such as Maharashtra State Electricity Distribution Company Ltd. v. Adani Power Maharashtra Limited and Others and Energy Watchdog v. Central Electricity Regulatory Commission and Others.

Conclusion

The Supreme Court disposed of the appeal, affirming the Appellate Tribunal’s order. The court held that the generator was entitled to compensation for the increased cost of coal procurement and that the unutilized monthly coal quota can be carried forward. The court found no merit in the apprehension of the DISCOM that the generator was being unduly benefited.

See also  Supreme Court clarifies "consequential benefits" in superannuation cases: K. Ananda Rao vs. Sri S.S. Rawat (2019)

Category

Parent Category: Electricity Law

Child Categories:

  • Compensation for Change in Law
  • Coal Supply
  • Maharashtra Electricity Regulatory Commission
  • Appellate Tribunal for Electricity

Parent Category: Contract Law

Child Categories:

  • Annual Contracted Quantity

Parent Category: Energy Law

Child Categories:

  • Power Generation
  • Power Distribution

FAQ

Q: What was the main issue in the Maharashtra State Electricity Distribution Company Limited vs. Rattan India Power Limited case?

A: The main issue was whether a power generator is entitled to compensation for increased coal procurement costs due to a change in law and whether unutilized monthly coal quota can be carried forward.

Q: What did the Supreme Court decide regarding compensation for increased coal costs?

A: The Supreme Court upheld that power generators are entitled to compensation for increased coal procurement costs due to changes in law.

Q: Can unutilized coal quotas be carried forward to the next month?

A: Yes, the Supreme Court held that unutilized coal quantities for a particular month can be carried forward to the next month if the generator’s methodology is reasonable.

Q: What is the significance of this judgment for power generators?

A: This judgment ensures that power generators are fairly compensated for increased costs due to changes in law and that their operational practicalities are considered in calculating compensation.

Q: What previous cases did the Supreme Court rely on in this judgment?

A: The Supreme Court relied on Maharashtra State Electricity Distribution Company Ltd. v. Adani Power Maharashtra Limited and Others and Energy Watchdog v. Central Electricity Regulatory Commission and Others.