LEGAL ISSUE: Whether the High Court erred in setting aside an arbitral award based on the interpretation of contract clauses and the application of the “patent illegality” principle under Section 34 of the Arbitration and Conciliation Act, 1996, as amended in 2015.
CASE TYPE: Arbitration Law
Case Name: Patel Engineering Ltd. vs. North Eastern Electric Power Corporation Ltd. (NEEPCO)
Judgment Date: 22 May 2020
Introduction
Date of the Judgment: 22 May 2020
Citation: [Not Available in Source]
Judges: R. Banumathi, Indu Malhotra, Aniruddha Bose, JJ.
Can a review petition be entertained if the main judgment has already been upheld by the Supreme Court? The Supreme Court, in this case, addressed the issue of whether the High Court was correct in rejecting a review petition against its earlier judgment regarding an arbitration award. The core issue revolved around the interpretation of contract clauses and whether the High Court correctly applied the principle of “patent illegality” under Section 34 of the Arbitration and Conciliation Act, 1996, as amended in 2015. The Supreme Court upheld the High Court’s decision, emphasizing that the High Court had correctly found the arbitral award to be perverse and irrational.
Case Background
The dispute arose from contracts between Patel Engineering Ltd. and North Eastern Electric Power Corporation Ltd. (NEEPCO) for construction work. The sole arbitrator issued awards on 29 March 2016, in favor of Patel Engineering, concerning extra lead payments for transporting materials. NEEPCO challenged these awards under Section 34 of the Arbitration and Conciliation Act, 1996, before the Additional Deputy Commissioner (Judicial), Shillong, who upheld the awards on 27 April 2018. NEEPCO then appealed to the High Court, which overturned the lower court’s decision on 26 February 2019, setting aside the arbitral awards. Patel Engineering then filed special leave petitions (SLPs) before the Supreme Court, which were dismissed on 19 July 2019. Following this, Patel Engineering filed review petitions before the High Court, which were also dismissed, leading to the current appeal before the Supreme Court.
Timeline
Date | Event |
---|---|
29 March 2016 | Arbitral awards issued by the sole arbitrator in favor of Patel Engineering Ltd. |
27 April 2018 | Additional Deputy Commissioner (Judicial), Shillong, rejected NEEPCO’s challenge and upheld the arbitral awards. |
26 February 2019 | High Court allowed NEEPCO’s appeals and set aside the arbitral awards. |
19 July 2019 | Supreme Court dismissed Patel Engineering’s special leave petitions against the High Court’s judgment. |
10 October 2019 | High Court dismissed Patel Engineering’s review petitions. |
22 May 2020 | Supreme Court dismissed the special leave petitions against the High Court’s order, upholding the High Court’s decision. |
Legal Framework
The case primarily concerns Section 34 of the Arbitration and Conciliation Act, 1996, which deals with setting aside arbitral awards. The 2015 Amendment to the Act introduced Section 34(2A), which provides an additional ground for setting aside a domestic award if it is vitiated by “patent illegality” appearing on the face of the award. The Supreme Court has clarified that “patent illegality” includes cases where the arbitrator’s decision is perverse, irrational, or based on an interpretation of the contract that no reasonable person would make. The court also noted that the amendment was brought in to do away with the wider interpretation of “public policy of India” as laid down in Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. [(2003) 5 SCC 705] and Oil & Natural Gas Corporation Ltd. v. Western Geco International Limited [(2014) 9 SCC 263]. The proviso to Section 34(2A) specifies that an award cannot be set aside merely on the ground of an erroneous application of the law or by re-appreciating evidence.
The relevant extract of Section 34(2A) of the Arbitration and Conciliation Act, 1996 is as follows:
“(2A) An arbitral award arising out of arbitrations other than international commercial arbitrations, may also be set aside by the Court, if the Court finds that the award is vitiated by patent illegality appearing on the face of the award :
Provided that an award shall not be set aside merely on the ground of an erroneous application of the law or by reappreciation of evidence.”
Arguments
Petitioner’s Arguments (Patel Engineering Ltd.):
- The High Court’s judgment dated 26 February 2019, erroneously applied the provisions of the Arbitration and Conciliation Act, 1996, as they existed before the 2015 Amendment.
- The High Court relied on Saw Pipes Ltd. [(2003) 5 SCC 705] and Western Geco International Limited [(2014) 9 SCC 263], which are no longer good law after the 2015 Amendment.
- The judgment of the High Court suffers from an error apparent on the face of the record, justifying a review.
- The dismissal of the earlier SLP was a non-speaking order and not on merits, hence a review petition was maintainable.
- The Supreme Court has plenary jurisdiction under Article 136 of the Constitution and is not curtailed by the Code of Civil Procedure.
Respondent’s Arguments (NEEPCO):
- The earlier SLP was heard at length, and all arguments, including the effect of the 2015 Amendment, were raised and considered before dismissal.
- The dismissal of the SLP, even if non-speaking, means the petitioner cannot re-agitate the matter through a review petition.
- An appeal is not maintainable against the order rejecting the application for review of judgment.
- The High Court correctly applied the principle of “patent illegality” and found the arbitrator’s award to be perverse and irrational.
- The High Court’s interpretation of the contract clauses was correct, and the arbitrator’s view was not a possible view.
Summary of Submissions
Main Submission | Sub-Submissions of Petitioner (Patel Engineering Ltd.) | Sub-Submissions of Respondent (NEEPCO) |
---|---|---|
Applicability of 2015 Amendment | ✓ High Court erroneously applied pre-amendment provisions. ✓ Relied on overruled judgments (Saw Pipes, Western Geco). ✓ Error apparent on the face of the record. |
✓ All arguments, including the effect of the 2015 Amendment, were considered in the earlier SLP. ✓ The High Court correctly applied the principle of “patent illegality”. |
Maintainability of Review Petition | ✓ Dismissal of earlier SLP was non-speaking and not on merits. ✓ Supreme Court has plenary jurisdiction under Article 136. |
✓ Appeal is not maintainable against the order rejecting the application for review of judgment. ✓ The petitioner cannot re-agitate the matter through a review petition. |
Interpretation of Contract Clauses | ✓ The High Court’s interpretation of the contract clauses was correct. ✓ The arbitrator’s view was perverse and not a possible view. |
Issues Framed by the Supreme Court
The Supreme Court did not explicitly frame issues but dealt with the following points:
- Whether the High Court was correct in rejecting the review petition.
- Whether the High Court correctly applied the principle of “patent illegality” under Section 34(2A) of the Arbitration and Conciliation Act, 1996.
- Whether the High Court’s interpretation of the contract clauses was correct.
- Whether the arbitral award was perverse and irrational.
Treatment of the Issue by the Court
Issue | Court’s Decision and Reasoning |
---|---|
Whether the High Court was correct in rejecting the review petition. | The Supreme Court held that the High Court was correct in rejecting the review petition because the main judgment had already been upheld by the Supreme Court. |
Whether the High Court correctly applied the principle of “patent illegality” under Section 34(2A) of the Arbitration and Conciliation Act, 1996. | The Supreme Court agreed that the High Court correctly applied the principle of “patent illegality.” The High Court found the arbitral award to be perverse and irrational, which falls under the ambit of “patent illegality.” |
Whether the High Court’s interpretation of the contract clauses was correct. | The Supreme Court concurred with the High Court’s interpretation, stating that no reasonable person could have interpreted the contract differently. |
Whether the arbitral award was perverse and irrational. | The Supreme Court upheld the High Court’s finding that the arbitral award was indeed perverse and irrational, as the arbitrator had considered irrelevant factors and ignored vital contract clauses. |
Authorities
The Supreme Court considered the following authorities:
Cases
Case Name | Court | How it was used |
---|---|---|
Bussa Overseas and Properties Private Limited and Another v. Union of India and Another [(2016) 4 SCC 696] | Supreme Court of India | Cited to emphasize that the Supreme Court’s plenary jurisdiction under Article 136 is not curtailed by the Code of Civil Procedure, but also to highlight the principle that if the basic judgment is not assailed, a challenge only to the review order is not entertained. |
Durga Shankar Mehta v. Thakur Raghuraj Singh and Others [(1955) 1 SCR 267] | Supreme Court of India | Cited to support the argument that Article 136 of the Constitution confers special powers on the Supreme Court. |
Shanker Motiram Nale v. Shiolalsing Gannusing Rajput [(1994) 2 SCC 753] | Supreme Court of India | Mentioned to highlight that Order 47 Rule 7 of the Code of Civil Procedure does not curtail the Supreme Court’s jurisdiction under Article 136. |
Sandhya Educational Society vs. Union of India [(2014) 7 SCC 701] | Supreme Court of India | Cited to show that once a special leave petition is dismissed, a fresh petition after exhausting the review remedy is not maintainable. |
Vinod Kapoor vs. State of Goa [(2012) 12 SCC 378] | Supreme Court of India | Cited to show that once a special leave petition is dismissed, a fresh petition after exhausting the review remedy is not maintainable. |
State of A.P. v. A.P. Jaiswal [(2001) 1 SCC 748] | Supreme Court of India | Cited to emphasize the importance of consistency in the administration of justice. |
Thungabhadra Industries Ltd. v. Government of Andhra Pradesh Represented by the Deputy Commissioner of Commercial Taxes, Anantapur [(1964) 5 SCR 174] | Supreme Court of India | The Court held that the decision rendered in this case is not correct. |
Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. [(2003) 5 SCC 705] | Supreme Court of India | Discussed as the case that first expounded “patent illegality” as a ground for setting aside a domestic award. The court noted that the expansive interpretation of “public policy of India” in this case was done away with by the 2015 Amendment. |
Associate Builders v. Delhi Development Authority [(2015) 3 SCC 49] | Supreme Court of India | Discussed extensively to define “patent illegality” and its sub-heads. The court reiterated that the construction of the terms of a contract is primarily for an arbitrator to decide, unless the arbitrator construes the contract in a manner that no fair-minded or reasonable person would. |
Board of Control for Cricket in India v. Kochi Cricket Private Limited and Others [(2018) 6 SCC 287] | Supreme Court of India | Cited to establish that the 2015 Amendment applies to Section 34 petitions made after 23 October 2015. |
HRD Corporation (Marcus Oil and Chemical Division) v. GAIL (India) Limted [(2018) 12 SCC 471] | Supreme Court of India | Cited by the petitioner to support their argument that the High Court erred in its judgment. |
Ssangyong Engineering and Construction Company Limited v. National Highways Authority of India (NHAI) [(2019) 15 SCC 131] | Supreme Court of India | Cited to emphasize that the expansive interpretation of “public policy of India” in Saw Pipes and Western Geco International Limited cases has been done away with, and a new ground of “patent illegality” was introduced. Also, the Court reiterated the principles laid down in Associate Builders. |
Oil & Natural Gas Corporation Ltd. v. Western Geco International Limited [(2014) 9 SCC 263] | Supreme Court of India | Discussed as a case where a wider interpretation was given to “public policy of India,” which has been done away with by the 2015 Amendment. |
Angerlehner Structural and Civil Engineering co. v. Municipal Corporation of Greater Mumbai | Bombay High Court | Cited by the High Court to support the view that unjust enrichment of a party at the cost of public funds is against the fundamental policy of Indian law. |
Judgment
How each submission made by the Parties was treated by the Court?
Submission | How it was treated by the Court |
---|---|
Petitioner’s submission that the High Court erroneously applied pre-amendment provisions. | The Court rejected this submission, noting that the High Court’s decision was based on the principle of “patent illegality,” which is a valid ground under the amended Act. |
Petitioner’s submission that the High Court relied on overruled judgments (Saw Pipes, Western Geco). | The Court acknowledged that while the High Court did refer to these judgments, the ultimate decision was based on the principle of “patent illegality,” which is valid under the amended act, and the High Court had correctly applied the test set out in Associate Builders and reiterated in Ssangyong Engineering. |
Petitioner’s submission that the dismissal of the earlier SLP was non-speaking and not on merits. | The Court did not accept this submission. It held that once the main judgment was upheld by the Supreme Court, a review petition on the same grounds was not maintainable. |
Respondent’s submission that the earlier SLP was heard at length and all arguments were considered. | The Court acknowledged this submission. |
Respondent’s submission that the High Court correctly applied the principle of “patent illegality.” | The Court accepted this submission, stating that the High Court correctly found the arbitral award to be perverse and irrational. |
Respondent’s submission that the High Court’s interpretation of the contract clauses was correct. | The Court agreed with this submission, stating that the High Court’s interpretation was the only possible interpretation. |
How each authority was viewed by the Court?
The Court relied on the following authorities for its reasoning:
- Bussa Overseas and Properties Private Limited and Another v. Union of India and Another [(2016) 4 SCC 696]: The Court used this case to reiterate that while the Supreme Court has plenary jurisdiction, it has also evolved a principle that if the basic judgment is not assailed, the court will not entertain a special leave petition against the order passed in review.
- Associate Builders v. Delhi Development Authority [(2015) 3 SCC 49]: The Court heavily relied on this case to define “patent illegality” and its sub-heads, particularly emphasizing that the construction of the terms of a contract is primarily for an arbitrator to decide, unless the arbitrator construes the contract in a manner that no fair-minded or reasonable person would.
- Ssangyong Engineering and Construction Company Limited v. National Highways Authority of India (NHAI) [(2019) 15 SCC 131]: The Court used this case to highlight that the expansive interpretation given to “public policy of India” in Saw Pipes and Western Geco International Limited cases has been done away with, and a new ground of “patent illegality” was introduced. The court also reiterated the principles laid down in Associate Builders.
- Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. [(2003) 5 SCC 705] and Oil & Natural Gas Corporation Ltd. v. Western Geco International Limited [(2014) 9 SCC 263]: The Court acknowledged that these cases were relied upon by the High Court but clarified that the High Court’s decision was ultimately based on the principle of “patent illegality” as defined in later judgments. The Court also noted that the expansive interpretation of “public policy of India” in these cases has been done away with by the 2015 Amendment.
What weighed in the mind of the Court?
The Supreme Court’s decision was primarily influenced by the following factors:
- The High Court’s correct application of the “patent illegality” principle under Section 34(2A) of the Arbitration and Conciliation Act, 1996.
- The finding that the arbitral award was perverse, irrational, and based on an interpretation of the contract that no reasonable person would make.
- The principle that once the main judgment has been upheld by the Supreme Court, a review petition on the same grounds is not maintainable.
- The need for consistency in the administration of justice.
Ranking of Sentiment Analysis of Reasons
Reason | Percentage |
---|---|
High Court’s correct application of “patent illegality” | 40% |
Perversity and irrationality of the arbitral award | 30% |
Maintainability of review petition | 20% |
Need for consistency in the administration of justice | 10% |
Fact:Law Ratio
Category | Percentage |
---|---|
Fact | 30% |
Law | 70% |
Logical Reasoning
Issue: Was the High Court correct in rejecting the review petition?
Reasoning: The Supreme Court had already dismissed the SLP against the main judgment. Therefore, a review petition on the same grounds was not maintainable.
Conclusion: High Court’s rejection of the review petition was correct.
Issue: Did the High Court correctly apply the principle of “patent illegality”?
Reasoning: The High Court found the arbitral award to be perverse, irrational, and based on an unreasonable interpretation of the contract, which falls under the definition of “patent illegality.”
Conclusion: High Court correctly applied the principle of “patent illegality.”
Issue: Was the High Court’s interpretation of the contract clauses correct?
Reasoning: The Supreme Court agreed with the High Court’s interpretation, stating that no reasonable person could have interpreted the contract differently.
Conclusion: High Court’s interpretation of the contract clauses was correct.
Issue: Was the arbitral award perverse and irrational?
Reasoning: The High Court found that the arbitrator had considered irrelevant factors and ignored vital contract clauses, leading to a perverse and irrational award.
Conclusion: The arbitral award was indeed perverse and irrational.
The Supreme Court emphasized that the High Court had correctly applied the principle of “patent illegality” as defined in Associate Builders and reiterated in Ssangyong Engineering. The Court also noted that the High Court’s decision was based on a holistic reading of the contract and that the arbitrator’s view was not a possible view. The Court stated that the High Court’s decision was in line with the fundamental policy of Indian law, which does not allow for unjust enrichment.
The Court quoted from the High Court’s judgment:
“51. …Clause 33(iii) specifically provides that “if the rates for such items of work cannot be determined in the manner as specified in Clause 33(ii), the rates for such items to be executed shall be determined by the Engineer-in-Charge on the basis of actual and analysed cost taking the following into consideration the rates for such items of works as are required to be executed due to deviations as stated in sub-clause shall be payable in the manner as stated hereunder…..”. We are of the firm view that this is the only possible interpretation of Clauses 2.7 and 3.4 of the BoQ and Clauses 32(ii)(a) and 33(iii) of the Conditions of Contract. No reasonable person would arrive at a different conclusion while interpreting Clauses 2.7 and 3.4 of the BoQ and Clauses 32(ii)(a) and 33(iii) of the Conditions of Contract. Any other interpretation of the above clauses would definitely be irrational and defiance of all logic.”
“52. The Arbitral Awards and the findings of the learned Arbitrator suffer from the vice of perversity… The findings of the learned Arbitrator having been arrived at by taking into account irrelevant factors and by ignoring vital clauses, the same suffers from vice of irrationality and perversity.”
“53. …We are of the considered view that payment of Rs. 3.56 Lakh per truck (10 Cubic Metre) of sand or boulder (100 km distance) is definitely a case of unjust enrichment which is contrary to the Fundamental Policy of Indian Law.”
Key Takeaways
- The Supreme Court upheld the High Court’s decision, emphasizing the importance of the “patent illegality” principle in setting aside domestic arbitral awards.
- The judgment clarifies that once a main judgment is upheld by the Supreme Court, a review petition on the same grounds is not maintainable.
- The decision reinforces that arbitrators must interpret contracts reasonably, and their decisions should not be perverse or irrational.
- The ruling highlights the need for consistency in the administration of justice and the importance of adhering to established legal principles.
Directions
No specific directions were given by the Supreme Court in this case.
Specific Amendments Analysis
Not Applicable.
Development of Law
The ratio decidendi of this case is that a review petition is not maintainable if the main judgment has already been upheld by the Supreme Court. It also reinforces the principle that a domestic arbitral award can be set aside if it is vitiated by “patent illegality,” which includes perversity, irrationality, and an unreasonable interpretation of the contract. This case clarifies the application of Section 34(2A) of the Arbitration and Conciliation Act, 1996, as amended in 2015, and reiterates the principles laid down in Associate Builders and Ssangyong Engineering. The judgment also underscores that the expansive interpretation of “public policy of India” as laid down in Saw Pipes and Western Geco International Limited is no longer valid.
Conclusion
The Supreme Court dismissed the special leave petitions, thereby upholding the High Court’s decision to set aside the arbitral awards. The Court emphasized that the High Court had correctly applied the principle of “patent illegality” and that the arbitral award was indeed perverse and irrational. The judgment reinforces the importance of consistency in the judicial process and clarifies the limitations on filing review petitions after the main judgment has been upheld by the Supreme Court.