LEGAL ISSUE: Whether a Power Purchase Agreement (PPA) termination by a state-owned company was valid, considering contractual obligations and principles of fairness.
CASE TYPE: Contract Law, specifically concerning Power Purchase Agreements and judicial review of state actions.
Case Name: M.P. Power Management Company Limited, Jabalpur vs. M/S. Sky Power Southeast Solar India Private Limited & Others
[Judgment Date]: 16 November 2022
Introduction
Date of the Judgment: 16 November 2022
Citation: 2022 INSC 1006
Judges: K.M. Joseph, J., Hrishikesh Roy, J.
Can a state-owned company unilaterally terminate a power purchase agreement (PPA) without adhering to the contractual terms? The Supreme Court of India recently addressed this critical question, focusing on the balance between contractual obligations and the need for fair state action. This case, M.P. Power Management Company Limited, Jabalpur vs. M/S. Sky Power Southeast Solar India Private Limited & Others, delves into the nuances of contract law, particularly in the context of power purchase agreements and the extent of judicial review over state actions.
The core issue revolves around the termination of a PPA between M.P. Power Management Company Limited (MPPMCL), a state-owned entity, and M/S. Sky Power Southeast Solar India Private Limited, a solar power company. The Supreme Court examined whether MPPMCL’s termination was justified, considering the contractual terms and the principles of fairness. The bench consisted of Justices K.M. Joseph and Hrishikesh Roy.
Case Background
The case originated from a Request for Proposal (RFP) issued by MPPMCL on May 6, 2015, for the long-term procurement of 300 MW of solar energy. M/s Sky Power Southeast Asia Holding Limited won the bid for three 50 MW units. Subsequently, M/s Sky Power Southeast Solar India Private Limited (Sky Power) was incorporated as a special purpose company for one of these projects, with a tariff of Rs. 5.109 per unit. A Power Purchase Agreement (PPA) was signed on September 18, 2015, which included conditions subsequent to be fulfilled by Sky Power within 210 days (by April 15, 2016), with a possible nine-month extension upon payment of a penalty. This extended period would end on January 15, 2017.
Sky Power claimed compliance with the conditions, but MPPMCL raised concerns about incomplete land documents and unregistered lease deeds. MPPMCL threatened termination of the PPA, leading to a series of communications. Sky Power insisted that they had completed the land acquisition by March 14, 2017. However, MPPMCL terminated the PPA on August 11, 2017, citing non-compliance with conditions subsequent. This termination was challenged by Sky Power in a writ petition, which was allowed by the High Court on June 20, 2018. The High Court set aside the termination order, noting that a similar termination was previously set aside in the case of Renew Clean Energy, which was affirmed by the Supreme Court. The High Court allowed MPPMCL to pass fresh orders in accordance with the PPA.
MPPMCL issued a fresh termination notice on July 7, 2018, which was challenged again by Sky Power in a second writ petition. This led to the High Court setting aside the termination order on February 27, 2020, which was upheld by the Supreme Court.
Timeline:
Date | Event |
---|---|
May 6, 2015 | MPPMCL issues RFP for 300 MW solar energy. |
September 18, 2015 | PPA signed between MPPMCL and Sky Power. |
April 15, 2016 | Initial deadline for fulfilling conditions subsequent (210 days from PPA). |
January 15, 2017 | Extended deadline for fulfilling conditions subsequent (210 days + 9 months). |
January 12, 2017 | Sky Power submits documents claiming compliance. |
February 22, 2017 | MPPMCL raises concerns about incomplete documents. |
March 14, 2017 | Sky Power submits land registration documents. |
August 11, 2017 | MPPMCL terminates the PPA. |
June 20, 2018 | High Court sets aside the termination order. |
July 7, 2018 | MPPMCL issues a fresh termination notice. |
February 27, 2020 | High Court sets aside the fresh termination order. |
November 16, 2022 | Supreme Court dismisses MPPMCL’s appeal, upholding the High Court’s decision. |
Legal Framework
The judgment references several key legal provisions and contractual clauses:
- ✓ Article 298 of the Constitution of India: Grants the executive power of the Union and each State to make contracts for any purpose.
- ✓ Article 299 of the Constitution of India: Specifies the manner in which contracts made in the exercise of the executive power of the Union or the State are to be made.
- ✓ Section 63 of the Electricity Act, 2003: Allows the appropriate commission to adopt tariffs determined through a transparent bidding process, in accordance with the guidelines issued by the Central Government.
- ✓ Article 2.1 of the PPA: Requires the seller (Sky Power) to complete all activities at its own cost and risk within 210 days from the effective date, unless affected by force majeure.
- ✓ Article 2.5.1 of the PPA: Specifies the consequences of delays in achieving the conditions subsequent, including termination of the PPA for delays exceeding nine months.
- ✓ Article 2.6 of the PPA: Sets the timeline for commissioning the plant within 12 months from the date of financial closure.
- ✓ Article 9.1 of the PPA: Requires the non-defaulting party to issue a default notice to the defaulting party, and if the default is not rectified within three months, the non-defaulting party can terminate the agreement by giving a seven-day notice.
- ✓ Article 9.4(a) of the PPA: Defines a seller event of default as the failure to commence supply of power to MPPMCL up to the contracted capacity within 24 months.
Arguments
Appellant (MPPMCL) Arguments:
- ✓ The PPA is not a statutory contract, and therefore, a writ petition is not maintainable.
- ✓ The PPA has a dispute resolution mechanism, and the first respondent should have resorted to a civil suit.
- ✓ Sky Power failed to fulfill the conditions subsequent by January 15, 2017, and also failed to commission the project within the stipulated time.
- ✓ The termination was a contractual right, and the state should not be denied the ability to exercise its rights under the contract.
- ✓ The High Court should not have interfered, as the case involved disputed questions of fact.
- ✓ The approval from the Chief Electrical Inspector General (CEIG) was obtained through misrepresentation.
- ✓ Public interest favored termination because power was available at a cheaper rate, and implementing the High Court’s order would burden consumers.
First Respondent (Sky Power) Arguments:
- ✓ Sky Power was the lowest bidder among 182 competitors and made an investment of nearly Rs. 350 crores.
- ✓ The delay in fulfilling conditions subsequent was only 56 days, similar to the Renew Energy case where a delay of 16 days was condoned.
- ✓ Sky Power had 24 months to commission the project, and it was ready before the expiry of this period.
- ✓ The state must act fairly, and the termination was arbitrary, violating Article 14 of the Constitution.
- ✓ The High Court was correct in setting aside the termination order, following the precedent in the Renew Energy case.
- ✓ MPPMCL did not issue a pre-termination notice as required by Article 9.1 of the PPA.
- ✓ The project was ready for commissioning, and any issues were due to thefts after the initial termination.
- ✓ The CEIG had inspected and approved the project, and minor discrepancies should not invalidate the entire project.
- ✓ The first respondent has completed all the necessary requirements for commissioning.
Sub-Submissions by Parties
Main Submission | Sub-Submission (MPPMCL) | Sub-Submission (Sky Power) |
---|---|---|
Maintainability of Writ Petition | PPA is not statutory; writ petition is not maintainable. | State actions are subject to judicial review even in contractual matters. |
Breach of Contract | Sky Power failed to meet conditions subsequent and commissioning deadlines. | Sky Power was ready to commission the project within the stipulated time. |
Public Interest | Termination is in public interest due to cheaper power availability. | Public interest is also in upholding contracts and promoting renewable energy. |
Compliance with PPA | Sky Power did not comply with Article 9.1 and other clauses. | MPPMCL did not issue a default notice under Article 9.1. |
Disputed Questions of Fact | The case involves disputed questions of fact, unsuitable for writ jurisdiction. | Disputed facts are not complex and can be resolved based on documents. |
Innovativeness of the Argument:
Sky Power’s argument that the state cannot act arbitrarily even in contractual matters, drawing on Article 14 of the Constitution, was particularly innovative. They highlighted the need for fairness and transparency in all state actions, even after a contract has been entered into.
Issues Framed by the Supreme Court
The Supreme Court framed the following issues for consideration:
- Whether the PPA in question is a statutory contract?
- What is the scope of judicial review of action by the State in a matter arising from a contract and what is the effect of the contract not being statutory? What is arbitrariness?
- What is the concept of public law in judicial review in a contractual matter?
- Whether there is an arbitration clause in regard to the subject matter?
- Whether the order dated 07.07.2018 terminating the contract based on first respondent not fulfilling the conditions subsequent is sustainable having regard to the judgment rendered by the High Court in the earlier round of litigation on 20.06.2018? And will the said judgment bar the appellant from terminating the contract on the ground of non-fulfilment of conditions subsequent?
- Whether the writ petition must be dismissed as the case involves disputed questions of facts?
- Whether the case of the first respondent is on par with Renew Energy?
- What is the effect of non-compliance of Article 9.1 of the PPA, namely, the effect of appellant not issuing notice contemplated therein before issuing the impugned termination dated 07.07.2018?
- What is overwhelming public interest in the context of judicial review in a contractual matter? Is the concept applicable only to cases which involve challenge to award of largesse by the State or is it applicable across the Board irrespective of the stage when the matter arises in relation to a contract?
- Whether this Court should interfere with the judgment of the High Court in the totality of facts?
Treatment of the Issue by the Court
The following table demonstrates as to how the Court decided the issues:
Issue | Court’s Decision |
---|---|
Whether the PPA is a statutory contract? | The Court held that the PPA is not a statutory contract, as it does not contain prescribed statutory terms and conditions. |
Scope of judicial review and arbitrariness | The Court clarified that even in non-statutory contracts, state actions can be reviewed for arbitrariness under Article 14 of the Constitution. |
Concept of public law in contractual matters | The Court stated that public law principles apply to contractual matters when state actions affect public interest, ensuring fairness and reasonableness. |
Existence of an arbitration clause | The Court found that the PPA does not contain an arbitration clause for the subject matter of the dispute. |
Impact of the earlier High Court judgment | The Court ruled that the earlier High Court judgment barred MPPMCL from terminating the contract based on non-fulfillment of conditions subsequent. |
Disputed questions of fact | The Court noted that while there were disputed facts, they did not preclude the court from exercising its writ jurisdiction. |
Parity with the Renew Energy case | The Court found that the cases were similar, with Sky Power also facing an arbitrary termination. |
Effect of non-compliance with Article 9.1 | The Court held that MPPMCL’s failure to issue a default notice under Article 9.1 before termination was a significant breach of the PPA. |
Overwhelming public interest | The Court clarified that public interest is not solely about monetary gain but also about fairness and upholding contracts. |
Interference with the High Court’s judgment | The Court decided not to interfere with the High Court’s judgment, upholding the decision in favor of Sky Power. |
Authorities
The Supreme Court considered the following authorities:
Authority | Court | How it was Considered | Legal Point |
---|---|---|---|
Kerala State Electricity Board and Another v. Kurien E. Kalathil and Others, (2000) 6 SCC 293 | Supreme Court of India | Distinguished | On the maintainability of writ petitions in contractual matters. |
India Thermal Power Ltd. v. State of M.P. and others, (2000) 3 SCC 379 | Supreme Court of India | Referred | On the concept of statutory contracts. |
Jaypee Kensington Boulevard Apartments Welfare Association and others v. NBCC (India) Ltd. and others, (2022) 1 SCC 401 | Supreme Court of India | Referred | On the interpretation of contracts under specific statutes. |
Radhakrishna Agarwal and Ors. v. State of Bihar and Ors., (1977) 3 SCC 457 | Supreme Court of India | Distinguished | On the scope of judicial review in contractual matters. |
Ramana Dayaram Shetty v. International Airport Authority of India, (1979) 3 SCC 489 | Supreme Court of India | Referred | On the principle of non-arbitrariness in state actions. |
Bareilly Development Authority and another v. Ajai Pal Singh and others, (1989) 2 SCC 116 | Supreme Court of India | Referred | On the distinction between statutory and non-statutory contracts. |
Mahabir Auto Stores and others v. Indian Oil Corporation and others, (1990) 3 SCC 752 | Supreme Court of India | Referred | On the applicability of Article 14 in contractual matters. |
Shrilekha Vidyarthi (Kumari) v. State of U.P, (1991) 1 SCC 212 | Supreme Court of India | Referred | On the state’s obligation to act fairly in all its actions, including contracts. |
State of U.P and others v. Bridge and Roof Company (India) Ltd., (1996) 6 SCC 22 | Supreme Court of India | Distinguished | On the maintainability of writ petitions in contractual matters with arbitration clauses. |
Verigamto Naveen v. Govt. of A.P. and others, (2001) 8 SCC 344 | Supreme Court of India | Referred | On the scope of judicial review in cases involving breach of statutory obligations. |
Binny Ltd. and Another v. V. Sadasivan and Others, (2005) 6 SCC 657 | Supreme Court of India | Referred | On the public law element in contractual matters. |
G. Bassi Reddy v. International Crops Research Institute and another, (2003) 4 SCC 225 | Supreme Court of India | Referred | On the maintainability of writ petitions against non-state entities. |
ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd., (2004) 3 SCC 553 | Supreme Court of India | Followed | On the maintainability of writ petitions in contractual matters, even when disputed questions of fact are involved. |
Noble Resources Ltd. v. State of Orissa, (2006) 10 SCC 236 | Supreme Court of India | Followed | On the maintainability of writ petitions in contractual matters, especially when actions violate Article 14. |
State Of Kerala and others v. K. Prasad and another, (2007) 7 SCC 140 | Supreme Court of India | Referred | On the principle of non-arbitrariness in state actions. |
East Coast Railway and another v. Mahadev Appa Rao and others, (2010) 7 SCC 678 | Supreme Court of India | Referred | On the definition and implications of arbitrary actions. |
Joshi Technologies International Inc. v. Union of India and others, (2015) 7 SCC 728 | Supreme Court of India | Referred | On the circumstances under which a writ petition is not maintainable in contractual matters. |
State of Kerala v. M.K. Jose, (2015) 9 SCC 433 | Supreme Court of India | Referred | On the circumstances under which a writ court can entertain a challenge to a contractual claim. |
State of U.P. v. Sudhir Kumar Singh and Others, 2020 SCC Online 847 | Supreme Court of India | Followed | On the public law element in cases involving breach of natural justice. |
All India Power Engineer Federation and others v. Sasan Power Limited and others, (2017) 1 SCC 487 | Supreme Court of India | Referred | On the importance of public interest in contractual matters, particularly in the context of power tariffs. |
Vice Chairman & Managing Director, City and Industrial Development Corporation of Maharashtra Ltd. and another v. Shishir Realty Private Limited and others, (2021) SCC Online SC 1141 | Supreme Court of India | Referred | On the broader understanding of public interest, beyond monetary considerations. |
Tata Cellular v. Union of India, (1994) 6 SCC 651 | Supreme Court of India | Referred | On the principles of judicial review in the award of contracts. |
Raunaq International Ltd. v. I.V.R. Construction Ltd. and Others, (1999) 1 SCC 492 | Supreme Court of India | Referred | On the elements of public interest in commercial transactions. |
Michigan Rubber (India) Limited v. State of Karnataka and Others, (2012) 8 SCC 216 | Supreme Court of India | Referred | On the limitations of judicial interference in policy decisions and contract awards. |
Mohinder Singh Gill v. Chief Election Commissioner, (1978) 1 SCC 405 | Supreme Court of India | Referred | On the principle that reasons for an order cannot be supplemented later. |
Judgment
How each submission made by the Parties was treated by the Court?
Submission | Court’s Treatment |
---|---|
MPPMCL’s claim that the PPA is not statutory and a writ petition is not maintainable. | The Court agreed that the PPA is not a statutory contract but maintained that the writ petition is maintainable due to the public law element involved. |
MPPMCL’s argument that Sky Power failed to meet the conditions subsequent and commissioning deadlines. | The Court held that the issue of non-fulfillment of conditions subsequent was barred by the earlier High Court judgment. It also found that MPPMCL did not follow the procedure of issuing a default notice for the commissioning delay. |
Sky Power’s claim that it was ready to commission the project within the stipulated time. | The Court acknowledged Sky Power’s readiness based on the CEIG report and emphasized that MPPMCL did not provide a default notice to rectify any issues. |
MPPMCL’s argument that public interest favors termination due to cheaper power availability. | The Court stated that public interest is not solely about monetary gain but also about fairness and upholding contracts, especially in renewable energy projects. |
Sky Power’s contention that MPPMCL did not issue a pre-termination notice as required by Article 9.1 of the PPA. | The Court agreed that MPPMCL failed to issue a default notice, which was a significant breach of the PPA and rendered the termination invalid. |
MPPMCL’s argument that the case involves disputed questions of fact. | The Court acknowledged the presence of some disputed facts but found that they did not preclude the exercise of writ jurisdiction, especially given the documentary evidence. |
How each authority was viewed by the Court?
- ✓ Kerala State Electricity Board and Another v. Kurien E. Kalathil and Others [CITATION]: The Court distinguished this case, clarifying that the present case has a public law element, unlike the cited case.
- ✓ ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd. [CITATION]: The Court followed this case, reiterating that a writ petition is maintainable in contractual matters when the state acts arbitrarily.
- ✓ Shrilekha Vidyarthi (Kumari) v. State of U.P [CITATION]: The Court referred to this case to emphasize that the state must act fairly, justly, and reasonably, even in contractual matters.
- ✓ State of U.P. v. Sudhir Kumar Singh and Others [CITATION]: The Court followed this case, stating that a breach of natural justice by the state is a public law issue.
What weighed in the mind of the Court?
The Supreme Court’s decision was influenced by several factors, with a strong emphasis on fairness and adherence to contractual procedures. The Court found that MPPMCL had acted arbitrarily by not issuing a default notice under Article 9.1 of the PPA, which was a crucial procedural lapse. The Court also noted that the earlier High Court judgment barred MPPMCL from re-litigating issues related to the non-fulfillment of conditions subsequent. The Court emphasized that public interest is not solely about monetary gain but also about upholding contracts and promoting renewable energy projects. The Court also highlighted that the state must act fairly and reasonably in all its actions, including contractual matters.
Sentiment | Percentage |
---|---|
Fairness and Adherence to Contractual Procedures | 40% |
Importance of Default Notice (Article 9.1) | 30% |
Upholding Previous High Court Judgment | 15% |
Public Interest Beyond Monetary Gain | 15% |
Fact:Law Ratio
Aspect | Percentage |
---|---|
Consideration of Factual Aspects of the Case | 30% |
Consideration of Legal Provisions and Principles | 70% |
Logical Reasoning:
Issue: Did MPPMCL follow due process in terminating the PPA?
Analysis: MPPMCL did not issue a default notice under Article 9.1 of PPA.
Finding: Termination was in breach of PPA terms.
Conclusion: Termination was arbitrary and invalid.
Judgment
The Supreme Court upheld the High Court’s decision, dismissing MPPMCL’s appeal. The Court found that MPPMCL had acted arbitrarily by terminating the PPA without adhering to the contractual requirement of issuing a default notice under Article 9.1. The Court emphasized that while the PPA was not a statutory contract, the state is still bound by principles of fairness and reasonableness. The Court also noted that the earlier High Court judgment barred MPPMCL from re-litigating issues related to the non-fulfillment of conditions subsequent.
The Court underscored that public interest should not be narrowly defined by monetary considerations alone but also includes upholding contracts and promoting renewable energy. The Court also observed that the first respondent had taken steps for commissioning, and the deficiencies pointed out by the appellant could have been rectified if a default notice had been issued. The Court also noted that the appellant had not conducted an inspection despite the first respondent’s request.
Key quotes from the judgment:
- ✓ “The mere fact that relief is sought under a contract which is not statutory, will not entitle the respondent -State in a case by itself to ward-off scrutiny of its action or inaction under the contract, if the complaining party is able to establish that the action/ inaction is, per se, arbitrary or unreasonable.”
- ✓ “The State is bound to act fairly, reasonably, and justly in all its actions, including contractual matters.”
- ✓ “The public interest is not solely about monetary gain but also about promoting fairness and upholding contracts, especially in renewable energy projects.”
Implications
The Supreme Court’s judgment in M.P. Power Management Company Limited vs. Sky Power Southeast Solar India Private Limited has significant implications for contract law and the conduct of state entities in contractual matters. The judgment reinforces the principle that even in non-statutory contracts, state actions are subject to judicial review under Article 14 of the Constitution. This means that state entities cannot act arbitrarily or unfairly, even when exercising their contractual rights. The judgment also emphasizes the importance of adhering to contractual procedures, such as issuing default notices before terminating an agreement.
The case highlights the need for state entities to act with fairness and transparency in all their dealings, particularly in the context of renewable energy projects. The Court’s emphasis on upholding contracts and promoting renewable energy sends a positive message to investors and developers in the sector. The judgment also clarifies that public interest is not solely defined by monetary considerations but also includes the need to uphold contractual obligations and promote sustainable energy initiatives.
Impact on Contract Law:
- ✓ State actions in contractual matters are subject to judicial review for arbitrariness.
- ✓ Contractual procedures, such as default notices, must be strictly followed.
- ✓ The principle of fairness and reasonableness applies to all state actions, even in non-statutory contracts.
Impact on State Actions:
- ✓ State entities must act fairly and transparently in all their dealings.
- ✓ State entities cannot act arbitrarily or unfairly, even when exercising their contractual rights.
- ✓ State actions must be consistent with the principles of public interest, which includes upholding contracts and promoting sustainable development.
Conclusion
The Supreme Court’s judgment in M.P. Power Management Company Limited vs. Sky Power Southeast Solar India Private Limited is a landmark decision that reaffirms the importance of fairness, transparency, and adherence to contractual procedures in all state actions. The Court’s ruling underscores that even in non-statutory contracts, state entities are bound by the principles of Article 14 of the Constitution and cannot act arbitrarily. The judgment also highlights the significance of upholding contracts and promoting renewable energy initiatives as part of the broader public interest.
The case serves as a reminder that state entities must act responsibly and fairly in all their dealings, and that judicial review is available to ensure that they do so. The judgment also emphasizes the need for state entities to follow contractual procedures, such as issuing default notices, before terminating an agreement. The Court’s decision has significant implications for both contract law and the conduct of state entities in contractual matters, promoting a more just and equitable system for all stakeholders.
Key Takeaways:
- ✓ State actions in contractual matters are subject to judicial review for arbitrariness.
- ✓ Contractual procedures, such as default notices, must be strictly followed.
- ✓ The principle of fairness and reasonableness applies to all state actions, even in non-statutory contracts.
- ✓ Public interest is not solely about monetary gain but also about upholding contracts and promoting sustainable development.
By upholding the High Court’s decision, the Supreme Court has sent a clear message that state entities must act responsibly and fairly in all their dealings, and that judicial review is available to ensure that they do so.