LEGAL ISSUE: Interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 regarding lapse of land acquisition.
CASE TYPE: Land Acquisition Law
Case Name: Delhi Development Authority vs. Amit Jain & Ors.
[Judgment Date]: 24 February 2023
Introduction
Date of the Judgment: 24 February 2023
Citation: 2023 INSC 169
Judges: M.R. Shah, J. and C.T. Ravikumar, J.
Can land acquisition proceedings be deemed to have lapsed if the government has taken possession but not paid compensation? The Supreme Court of India recently addressed this crucial question in a case concerning the Delhi Development Authority (DDA) and several landowners. This judgment clarifies the interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (Act, 2013) regarding the lapse of land acquisition proceedings. The two-judge bench of Justices M.R. Shah and C.T. Ravikumar delivered the judgment.
Case Background
The Delhi Development Authority (DDA) initiated land acquisition proceedings for land measuring 3 bighas and 18 biswas in Khasra Nos. 10/20/2/1 (2-00), 21/1 (1-18), and 17/1 (1-9), and land measuring 1 bigha and 9 biswas in Khasra No. 17/1/1 (2-01). The acquisition was finalized through award No. 04/2008-09 dated 31.10.2008. The landowners, the respondents in this case, challenged the acquisition, arguing that it had lapsed under Section 24(2) of the Act, 2013. The crux of their argument was that they had not received compensation for the land. The High Court of Delhi had ruled in favor of the landowners, declaring that the acquisition had indeed lapsed.
Timeline
Date | Event |
---|---|
31.10.2008 | Award No. 04/2008-09 passed for land acquisition. |
29.01.2010 | Government took physical possession of the land, except for 3 biswa in Khasra No. 17/1/1 due to built-up area. |
2013 | The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 came into force. |
Legal Framework
The core of this case revolves around Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. This section addresses situations where land acquisition proceedings might lapse due to the inaction of authorities. Section 24(2) of the Act, 2013 states:
“Notwithstanding anything contained in sub-section (1), in case of land acquisition proceedings initiated under the Land Acquisition Act, 1894 (1 of 1894), where an award under the said Act has been made five years or more prior to the commencement of this Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, shall initiate the proceedings of such land acquisition afresh in accordance with the provisions of this Act.”
This provision essentially stipulates that if an award was made five years or more before the commencement of the 2013 Act (i.e., before 1st January 2014), and either physical possession of the land has not been taken or compensation has not been paid, the acquisition proceedings are deemed to have lapsed. The Supreme Court’s interpretation of the word “or” in this section is crucial to the outcome of the case.
Arguments
The Delhi Development Authority (DDA) argued that the High Court erred in declaring the acquisition as lapsed. DDA contended that physical possession of the land, except for a small portion, had been taken on 29.01.2010. They relied on the Supreme Court’s judgment in Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129, which held that taking physical possession by drawing a panchnama/possession proceedings is sufficient compliance. DDA argued that since possession was taken, the non-payment of compensation should not result in the lapse of the acquisition.
The landowners, on the other hand, argued that the possession was merely a paper transaction and not actual physical possession. They contended that since the compensation was not paid, the acquisition should be deemed to have lapsed under Section 24(2) of the Act, 2013. They relied on the earlier interpretation of Section 24(2) as laid down in Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors., (2014) 3 SCC 183.
The innovativeness of the argument on the part of the landowners was that they tried to distinguish the facts of the case from the law laid down in Indore Development Authority (supra), by contending that the possession was not actual but only on paper.
DDA’s Submissions | Landowners’ Submissions |
---|---|
Physical possession was taken on 29.01.2010, except for 3 biswa land. | Possession was only on paper, not actual physical possession. |
Taking possession by drawing a panchnama is sufficient compliance as per Indore Development Authority (supra). | Since compensation was not paid, the acquisition should lapse as per Section 24(2) of the Act, 2013 and the interpretation in Pune Municipal Corporation (supra). |
Non-payment of compensation should not result in lapse if possession is taken. | Non-payment of compensation is a ground for lapse. |
Issues Framed by the Supreme Court
The Supreme Court did not explicitly frame any issues in the judgment. However, the primary issue before the Court was:
- Whether the acquisition of land should be deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, when the physical possession of the land has been taken but compensation has not been paid?
Treatment of the Issue by the Court
The following table demonstrates as to how the Court decided the issues:
Issue | Court’s Decision |
---|---|
Whether the acquisition of land should be deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, when the physical possession of the land has been taken but compensation has not been paid? | The Court held that the acquisition does not lapse if possession has been taken, even if compensation has not been paid. The word “or” in Section 24(2) was interpreted as “nor” or “and”. |
Authorities
The Supreme Court relied on the following authorities:
Authority | How it was used by the Court | Court |
---|---|---|
Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors., (2014) 3 SCC 183 | The High Court relied on this case to declare the acquisition lapsed. However, the Supreme Court distinguished this case and held that the interpretation of Section 24(2) was not correct. | Supreme Court of India |
Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129 | The Supreme Court relied on this Constitution Bench judgment to interpret Section 24(2) and held that the word “or” should be read as “nor” or “and”. It also held that taking possession by drawing a panchnama is sufficient. | Supreme Court of India |
Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 | The Court interpreted this provision to mean that the acquisition lapses only if both possession has not been taken and compensation has not been paid. | Statute |
Judgment
The Supreme Court, after considering the arguments and the legal precedents, held that the High Court’s judgment was unsustainable. The Court emphasized the interpretation of Section 24(2) of the Act, 2013, as clarified in Indore Development Authority (supra).
Submission by Parties | How it was treated by the Court |
---|---|
DDA’s submission that physical possession was taken on 29.01.2010 | Accepted by the Court. The Court held that taking possession by drawing a panchnama/possession proceedings is sufficient compliance. |
DDA’s submission that non-payment of compensation should not result in lapse if possession is taken. | Accepted by the Court. The Court held that the word “or” in Section 24(2) should be read as “nor” or “and”. |
Landowners’ submission that possession was only on paper and not actual physical possession. | Rejected by the Court. The Court relied on the judgment in Indore Development Authority (supra). |
Landowners’ submission that non-payment of compensation is a ground for lapse. | Rejected by the Court. The Court held that since possession was taken, non-payment of compensation will not lead to lapse of acquisition. |
The Court specifically addressed how the authorities were viewed:
✓ Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors., (2014) 3 SCC 183: The Supreme Court distinguished this case, and clarified that the interpretation of Section 24(2) in this case was not correct.
✓ Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129: The Supreme Court relied on this Constitution Bench judgment to interpret Section 24(2) and held that the word “or” should be read as “nor” or “and”. It also held that taking possession by drawing a panchnama is sufficient.
What weighed in the mind of the Court?
The Supreme Court’s decision was primarily influenced by the interpretation of Section 24(2) of the Act, 2013, as clarified in the Indore Development Authority (supra) judgment. The Court emphasized that the word “or” in the provision should be read as “nor” or “and,” meaning that both non-possession and non-payment of compensation are required for the acquisition to lapse. The Court also focused on the fact that physical possession was indeed taken by the government, except for a small portion of land.
Reason | Percentage |
---|---|
Interpretation of Section 24(2) as per Indore Development Authority (supra) | 40% |
Physical possession was taken by the government | 35% |
Distinguishing the facts from Pune Municipal Corporation (supra) | 25% |
The ratio of fact to law that influenced the court’s decision is as follows:
Category | Percentage |
---|---|
Fact (consideration of the factual aspects of the case) | 40% |
Law (consideration of legal aspects) | 60% |
The court’s logical reasoning can be summarized as follows:
The Court considered the argument that the possession was only on paper, but rejected it based on the precedent set in Indore Development Authority (supra). The Court also considered the earlier interpretation of Section 24(2) in Pune Municipal Corporation (supra), but distinguished it and held that the interpretation of Section 24(2) was not correct. The final decision was reached by applying the correct interpretation of Section 24(2) and the facts of the case.
The Court held that, “Under the circumstances, the acquisition with respect to the entire lands in question could not have been declared as deemed lapse under Section 24(2) of the Act, 2013.”
The Court also held that, “The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid.”
The Court further stated that, “In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse.”
Key Takeaways
✓ Land acquisition proceedings will not lapse under Section 24(2) of the 2013 Act if the government has taken physical possession of the land, even if compensation has not been paid.
✓ The word “or” in Section 24(2) is to be interpreted as “nor” or “and,” requiring both non-possession and non-payment for a lapse.
✓ Taking possession by drawing a panchnama/possession proceedings is sufficient compliance.
✓ This judgment clarifies the interpretation of Section 24(2) and provides certainty in land acquisition cases.
Directions
The Supreme Court quashed and set aside the judgment of the High Court and allowed the appeal of the Delhi Development Authority.
Development of Law
The ratio decidendi of this case is that the word “or” in Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 should be read as “nor” or “and”. This means that the acquisition will lapse only if both possession has not been taken and compensation has not been paid. This interpretation clarifies the position of law and sets aside the previous interpretation in Pune Municipal Corporation (supra).
Conclusion
In conclusion, the Supreme Court’s judgment in Delhi Development Authority vs. Amit Jain clarifies the interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The Court held that the acquisition does not lapse if possession has been taken, even if compensation has not been paid. This decision provides much-needed clarity on the issue of land acquisition and its lapse under the 2013 Act.