LEGAL ISSUE: Whether land acquisition lapses under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 if possession is taken but compensation is not paid.

CASE TYPE: Land Acquisition

Case Name: Govt. of NCT Delhi & Anr. vs. Dinesh Kumar & Anr.

Judgment Date: 28 April 2023

Date of the Judgment: 28 April 2023
Citation: 2023 INSC 389
Judges: M.R. Shah, J. and C.T. Ravikumar, J.
Can a land acquisition be deemed to have lapsed if the government has taken possession of the land but has not yet paid compensation? The Supreme Court of India addressed this critical question in a recent case, clarifying the interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. This judgment clarifies the conditions under which a land acquisition can be deemed to have lapsed. The bench consisted of Justices M.R. Shah and C.T. Ravikumar, with the judgment authored by Justice M.R. Shah.

Case Background

The case involves a dispute over land acquisition in Delhi. The Government of NCT of Delhi acquired certain land, and the key point of contention was whether the acquisition had lapsed under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (Act, 2013). The High Court of Delhi had ruled in favor of the original writ petitioner, declaring that the acquisition had lapsed because compensation had not been paid, even though possession was taken. The Government of NCT of Delhi appealed this decision to the Supreme Court.

Timeline

Date Event
31.12.2013 Possession of the disputed land was taken by the Government of NCT of Delhi.
01.01.2014 The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 came into effect.
2016 Writ Petition (C) No. 4954 of 2016 filed in the High Court of Delhi.
28.04.2023 The Supreme Court of India passed the judgment in Civil Appeal No. 3151 of 2023.

Course of Proceedings

The High Court of Delhi allowed the writ petition, declaring that the land acquisition had lapsed under Section 24(2) of the Act, 2013. The High Court reasoned that since compensation had not been paid to the original writ petitioner, one of the two conditions for a deemed lapse under Section 24(2) was met. The Government of NCT of Delhi then appealed this decision to the Supreme Court.

Legal Framework

The core of this case revolves around Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. This section deals with the lapse of land acquisition proceedings under certain conditions. The relevant portion of Section 24(2) of the Act, 2013 states:

See also  Supreme Court clarifies criteria for Permanent Secondment in DGQA: Union of India vs. Lt. Col. Sameer Singh (2 December 2019)

“Notwithstanding anything contained in sub-section (1), in case of land acquisition proceedings initiated under the Land Acquisition Act, 1894 (1 of 1894), where an award under the said Act has been made five years or more prior to the commencement of this Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, shall initiate the proceedings of such land acquisition afresh in accordance with the provisions of this Act.”

The Supreme Court has interpreted this provision in previous cases, particularly in Indore Development Authority vs. Manoharlal and Ors., (2020) 8 SCC 129, which established that both conditions—non-payment of compensation and not taking possession—must be met for a deemed lapse of acquisition.

Arguments

Appellant’s Arguments (Govt. of NCT Delhi):

  • The appellant argued that the possession of the land was taken on 31.12.2013.
  • Relying on the Supreme Court’s decision in Indore Development Authority vs. Manoharlal and Ors., the appellant contended that since possession was taken before the Act of 2013 came into force, there could be no deemed lapse of acquisition under Section 24(2) of the Act, 2013.

Respondent’s Arguments (Dinesh Kumar):

  • The respondent argued that only a paper possession was taken and the actual/physical possession remained with the original writ petitioner.
  • The respondent contended that since compensation was not paid, the acquisition should be deemed to have lapsed under Section 24(2) of the Act, 2013.
Main Submission Sub-Submissions
Appellant (Govt. of NCT Delhi)
  • Possession was taken on 31.12.2013.
  • As per Indore Development Authority vs. Manoharlal and Ors., no deemed lapse if possession is taken.
Respondent (Dinesh Kumar)
  • Only paper possession, not actual possession, was taken.
  • No compensation was paid, so acquisition should lapse under Section 24(2) of the Act, 2013.

Issues Framed by the Supreme Court

The Supreme Court did not explicitly frame issues in a separate section, but the core issue it addressed was:

  1. Whether the acquisition of land lapses under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, if the possession of the land has been taken but compensation has not been paid.

Treatment of the Issue by the Court

The following table demonstrates as to how the Court decided the issues

Issue Court’s Decision
Whether the acquisition of land lapses under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, if the possession of the land has been taken but compensation has not been paid. The Court held that the acquisition does not lapse if possession has been taken, even if compensation has not been paid. Both conditions (non-payment of compensation and not taking possession) must be met for a deemed lapse.

Authorities

The Supreme Court relied on the following authority:

Authority Court How it was used
Indore Development Authority vs. Manoharlal and Ors., (2020) 8 SCC 129 Supreme Court of India The Court followed this case, which held that both conditions—non-payment of compensation and not taking possession—must be met for a deemed lapse under Section 24(2) of the Act, 2013.
See also  Supreme Court Upholds Appointment of Lecturer Despite Procedural Lapses: Ram Chandra vs. State of Uttar Pradesh (2022)

The Supreme Court also considered the following legal provision:

  • Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013: This provision deals with the lapse of land acquisition proceedings if certain conditions are not met.

Judgment

Submission by Parties How the Court Treated the Submission
Appellant’s submission that possession was taken on 31.12.2013 and therefore, there is no lapse of acquisition. The Court accepted this submission, holding that possession was indeed taken, and therefore, one of the twin conditions for lapse under Section 24(2) was not met.
Respondent’s submission that only paper possession was taken and compensation was not paid, thus, the acquisition should lapse. The Court rejected this submission, stating that the mode of taking possession by drawing a punchnama was legal and valid as per Indore Development Authority vs. Manoharlal and Ors.. The Court also reiterated that both conditions of Section 24(2) must be satisfied for a deemed lapse.

How each authority was viewed by the Court?

The Supreme Court relied on Indore Development Authority vs. Manoharlal and Ors., (2020) 8 SCC 129* to state that the two conditions of Section 24(2) of the Act, 2013 have to be satisfied for a deemed lapse of acquisition.

What weighed in the mind of the Court?

The Supreme Court’s decision was primarily influenced by its previous ruling in Indore Development Authority vs. Manoharlal and Ors., which clarified the interpretation of Section 24(2) of the Act, 2013. The Court emphasized that both conditions—non-payment of compensation and not taking possession—must be met for a deemed lapse of acquisition. Since possession was taken on 31.12.2013, the court held that the acquisition did not lapse, irrespective of whether compensation was paid.

Sentiment Percentage
Reliance on precedent 60%
Factual analysis of possession 30%
Interpretation of Section 24(2) 10%
Category Percentage
Fact 30%
Law 70%

Logical Reasoning:

Issue: Does acquisition lapse under Section 24(2) if possession is taken but compensation is not paid?
Court considers Section 24(2) of the Act, 2013 and the Indore Development Authority case.
Indore Development Authority case states both conditions (non-payment and no possession) must be met for lapse.
Court finds possession was taken on 31.12.2013.
Therefore, one condition is not met.
Conclusion: Acquisition does not lapse.

The Court rejected the High Court’s interpretation, stating that the High Court’s reasoning was “just contrary to the law laid -down by this Court in the case of Indore Development Authority (supra).” The Supreme Court emphasized that “for deemed lapse under Section 24(2) of the Act, 2013, twin conditions of not taking possession and not tendering/paying the compensation are required to be satisfied.” The Court further clarified that “if one of the two ingredients of Section 24(2) of the Act, 2013 is not met, there shall not be any deemed lapse of acquisition under Section 24(2) of the Act, 2013.” The Court also held that taking possession by drawing a punchnama was a valid mode of taking possession.

Key Takeaways

  • For a land acquisition to lapse under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, both conditions—non-payment of compensation AND not taking possession—must be satisfied.
  • If possession of the land has been taken, the acquisition will not lapse, even if compensation has not been paid.
  • Taking possession by drawing a punchnama is a legally valid mode of taking possession.
See also  Supreme Court clarifies admissibility of electronic evidence and preliminary inquiries in corruption cases: State By Karnataka Lokayukta Police Station vs. M.R. Hiremath (2019) INSC 421 (01 May 2019)

Directions

The Supreme Court did not give any specific directions, but the effect of the judgment is that the land acquisition by the Government of NCT of Delhi remains valid.

Development of Law

The ratio decidendi of the case is that both conditions of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, i.e., non-payment of compensation and not taking possession, must be satisfied for a deemed lapse of acquisition. This judgment reaffirms the position of law established in Indore Development Authority vs. Manoharlal and Ors., and does not change the previous position of law.

Conclusion

The Supreme Court allowed the appeal by the Government of NCT of Delhi, setting aside the High Court’s judgment. The Supreme Court clarified that a land acquisition does not lapse under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, if possession has been taken, even if compensation has not been paid. This ruling reinforces the importance of adhering to the dual conditions specified in Section 24(2) for a deemed lapse of land acquisition.