LEGAL ISSUE: Whether a land acquisition lapses under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 if possession is taken, but compensation is not paid, and whether a subsequent purchaser has the locus standi to challenge the acquisition.

CASE TYPE: Land Acquisition

Case Name: Delhi Development Authority vs. Beena Gupta (D) Through LRS. & Ors.

Judgment Date: 16 January 2023

Date of the Judgment: 16 January 2023

Citation: (2023) INSC 30

Judges: M.R. Shah, J. and C.T. Ravikumar, J.

Can a land acquisition be deemed to have lapsed if the authorities have taken possession of the land but haven’t paid compensation? The Supreme Court of India recently addressed this critical question in a case involving the Delhi Development Authority (DDA) and a subsequent purchaser of land. The Court clarified the interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the Act 2013) and also addressed the locus standi of a subsequent purchaser to challenge acquisition proceedings. This judgment clarifies the legal position regarding land acquisition and the rights of subsequent purchasers. The judgment was delivered by a two-judge bench comprising Justice M.R. Shah and Justice C.T. Ravikumar, with the opinion authored by Justice M.R. Shah.

Case Background

The case revolves around a land acquisition initiated by the Delhi Development Authority (DDA) in Village Mundaka. The DDA sought to acquire approximately 200 Bighas of land, including a specific plot of 1 Bigha and 2 Biswas (approximately 0.26 acres) in Khasra No. 65/22/1. This plot was initially purchased by Ashok Kumar and Raj Kumar Sharma on June 17, 2005. Their names were subsequently recorded in the revenue records on August 1, 2005. Later, on May 11, 2010, Raj Kumar Sharma sold 275 square yards of this land to Beena Gupta, the original writ petitioner and respondent No. 1 in this case. This sale occurred after the land acquisition proceedings had begun and the award was declared on May 31, 2007. Beena Gupta, therefore, was a subsequent purchaser of the land.

Timeline

Date Event
17.06.2005 Notification issued under Section 4 of the Land Acquisition Act, 1894 for acquiring land in Village Mundaka.
17.06.2005 Ashok Kumar and Raj Kumar Sharma purchased the land in question.
01.08.2005 Ashok Kumar and Raj Kumar Sharma’s names were mutated in the revenue records.
31.05.2006 Declaration under Section 6 of the Land Acquisition Act, 1894 was issued.
31.05.2007 Award was declared.
15.12.2007 Possession of the land was taken by the authorities.
11.05.2010 Raj Kumar Sharma sold 275 sq. yds. of land to Beena Gupta.
01.11.2018 High Court of Delhi declared the acquisition lapsed under Section 24(2) of the Act, 2013.
16.01.2023 Supreme Court set aside the High Court order.

Course of Proceedings

The original writ petitioner, Beena Gupta, approached the High Court of Delhi seeking a declaration that the land acquisition had lapsed under Section 24(2) of the Act 2013. She argued that compensation for the land had not been paid. The Delhi Development Authority (DDA) countered, stating that possession of the land had been taken on December 15, 2007, and that Beena Gupta, being a subsequent purchaser, had no right to challenge the acquisition. The High Court, however, ruled in favor of Beena Gupta, declaring that the acquisition had lapsed. The DDA then appealed to the Supreme Court.

See also  Supreme Court Directs Restructuring of Dues and Loan Disbursements in Amrapali Case (10 June 2020)

Legal Framework

The case primarily revolves around Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, which states:

“Notwithstanding anything contained in sub-section (1), in case of land acquisition proceedings initiated under the Land Acquisition Act, 1894 (1 of 1894), where an award under the said Act has been made five years or more prior to the commencement of this Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, shall initiate the proceedings of such land acquisition afresh in accordance with the provisions of this Act.”

The Supreme Court also considered the interpretation of this provision as laid down in the Constitution Bench judgment in Indore Development Authority vs. Manoharlal and others (2020) 8 SCC 129.

Arguments

The arguments presented before the Supreme Court were as follows:

  • Appellant (Delhi Development Authority):
    • The possession of the land was taken on 15.12.2007.
    • The original writ petitioner, being a subsequent purchaser, had no locus to challenge the acquisition.
    • The High Court erred in declaring that the acquisition had lapsed under Section 24(2) of the Act 2013.
    • Relied on the Constitution Bench judgment in Indore Development Authority vs. Manoharlal and others (2020) 8 SCC 129 to argue that the acquisition could not lapse if possession had been taken.
  • Respondent (Beena Gupta):
    • The compensation for the land was not paid, and therefore, the acquisition should be deemed to have lapsed under Section 24(2) of the Act 2013.
Main Submission Sub-Submissions
Appellant (Delhi Development Authority)
  • Possession of the land was taken on 15.12.2007.
  • Respondent is a subsequent purchaser and lacks locus standi.
  • High Court erred in applying Section 24(2) of the Act 2013.
  • Relied on Indore Development Authority vs. Manoharlal
Respondent (Beena Gupta)
  • Compensation not paid, acquisition lapsed under Section 24(2) of the Act 2013.

Issues Framed by the Supreme Court

The Supreme Court did not explicitly frame issues in the judgment. However, the core issues addressed can be summarized as:

  1. Whether the acquisition of land lapses under Section 24(2) of the Act 2013 if possession has been taken but compensation has not been paid.
  2. Whether a subsequent purchaser of land has the locus standi to challenge the acquisition proceedings.

Treatment of the Issue by the Court

The following table demonstrates as to how the Court decided the issues

Issue Court’s Decision Reasoning
Whether the acquisition of land lapses under Section 24(2) of the Act 2013 if possession has been taken but compensation has not been paid. No lapse. The Supreme Court relied on the Constitution Bench decision in Indore Development Authority vs. Manoharlal, which clarified that the word “or” in Section 24(2) should be read as “nor” or “and.” Therefore, if either possession is taken or compensation is paid, the acquisition does not lapse.
Whether a subsequent purchaser of land has the locus standi to challenge the acquisition proceedings. No locus standi. The Court relied on its previous decisions in Shiv Kumar & Anr. Vs. Union of India & Ors. (2019) 10 SCC 229, Delhi Administration Through Secretary, Land and Building vs. Pawan Kumar & Ors., Civil Appeal No.3646 of 2022, and Delhi Development Authority versus Godfrey Phillips (I) Ltd. & Ors, Civil Appeal No.3073 of 2022, which held that subsequent purchasers have no right to challenge acquisition proceedings.
See also  Supreme Court clarifies procedure for dismissal of appeals due to appellant absence: Prabodh Ch. Das vs. Mahamaya Das (2019) INSC 963

Authorities

The Supreme Court relied on the following authorities:

Authority Court How it was used
Shiv Kumar & Anr. Vs. Union of India & Ors. (2019) 10 SCC 229 Supreme Court of India Established that subsequent purchasers have no locus to challenge acquisition.
Delhi Administration Through Secretary, Land and Building vs. Pawan Kumar & Ors., Civil Appeal No.3646 of 2022 Supreme Court of India Reiterated that subsequent purchasers have no locus to challenge acquisition.
Delhi Development Authority versus Godfrey Phillips (I) Ltd. & Ors, Civil Appeal No.3073 of 2022 Supreme Court of India Reiterated that subsequent purchasers have no locus to challenge acquisition.
Indore Development Authority versus Manoharlal and others (2020) 8 SCC 129 Supreme Court of India Constitution Bench judgment that clarified the interpretation of Section 24(2) of the Act 2013.

Judgment

The Supreme Court allowed the appeal, setting aside the High Court’s judgment. The Court held that the High Court had erred in entertaining the writ petition filed by the subsequent purchaser. Further, the Court reiterated that the acquisition did not lapse under Section 24(2) of the Act 2013, as possession of the land had been taken.

Submission by Parties How it was treated by the Court
The possession of the land was taken on 15.12.2007. Accepted as fact.
The original writ petitioner, being a subsequent purchaser, had no locus to challenge the acquisition. Accepted. The Court held that the High Court erred in entertaining the writ petition of a subsequent purchaser.
The High Court erred in declaring that the acquisition had lapsed under Section 24(2) of the Act 2013. Accepted. The Supreme Court set aside the High Court’s judgment.
The compensation for the land was not paid, and therefore, the acquisition should be deemed to have lapsed under Section 24(2) of the Act 2013. Rejected. The Court held that since possession was taken, the acquisition did not lapse.

The Supreme Court’s view on the authorities:

  • Shiv Kumar & Anr. Vs. Union of India & Ors. (2019) 10 SCC 229: The Court followed this authority to reiterate that a subsequent purchaser has no locus standi to challenge the acquisition.
  • Delhi Administration Through Secretary, Land and Building vs. Pawan Kumar & Ors., Civil Appeal No.3646 of 2022: The Court followed this authority to reiterate that a subsequent purchaser has no locus standi to challenge the acquisition.
  • Delhi Development Authority versus Godfrey Phillips (I) Ltd. & Ors, Civil Appeal No.3073 of 2022: The Court followed this authority to reiterate that a subsequent purchaser has no locus standi to challenge the acquisition.
  • Indore Development Authority versus Manoharlal and others (2020) 8 SCC 129: The Court applied the principles laid down in this Constitution Bench judgment to interpret Section 24(2) of the Act 2013, holding that the word “or” should be read as “nor” or “and.”

What weighed in the mind of the Court?

The Supreme Court’s decision was primarily influenced by the following factors:

  • The interpretation of Section 24(2) of the Act 2013 as clarified in Indore Development Authority vs. Manoharlal, which emphasized that the acquisition does not lapse if either possession is taken or compensation is paid.
  • The established legal principle that subsequent purchasers have no right to challenge land acquisition proceedings, as per the Court’s previous decisions.
Sentiment Percentage
Emphasis on Legal Precedent 40%
Interpretation of Section 24(2) 30%
Locus Standi of Subsequent Purchaser 30%
Ratio Percentage
Fact 30%
Law 70%
Issue: Does acquisition lapse under Section 24(2) if possession is taken, but compensation is not paid?
Court’s Interpretation: “Or” in Section 24(2) is read as “nor” or “and”.
Possession taken on 15.12.2007
Conclusion: Acquisition does not lapse.
Issue: Does a subsequent purchaser have locus standi to challenge the acquisition?
Court’s Reasoning: Relying on Shiv Kumar and other cases, subsequent purchasers have no locus standi.
Conclusion: Subsequent purchaser cannot challenge the acquisition.

The Court emphasized that “the subsequent purchaser had no locus to challenge the acquisition and/or lapsing of the acquisition under the Act, 2013.” The Court also noted that “the word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”.” Furthermore, the Court held that “once possession has been taken there is no lapse under Section 24(2).”

See also  Supreme Court Quashes Conviction Under Section 498A IPC in Matrimonial Dispute After Settlement (3 January 2022)

The Court did not discuss any alternative interpretations or minority opinions.

Key Takeaways

  • A land acquisition does not lapse under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, if possession of the land has been taken, even if compensation has not been paid.
  • Subsequent purchasers of land do not have the legal standing (locus standi) to challenge land acquisition proceedings.
  • The interpretation of Section 24(2) as laid down in Indore Development Authority vs. Manoharlal is crucial for determining whether an acquisition lapses.

Directions

The Supreme Court did not issue any specific directions in this case, other than setting aside the High Court’s judgment and dismissing the writ petition of the respondent.

Development of Law

The ratio decidendi of this case is that a land acquisition does not lapse under Section 24(2) of the Act 2013 if possession has been taken, and a subsequent purchaser has no locus standi to challenge the acquisition. This judgment reinforces the interpretation of Section 24(2) as laid down in the Constitution Bench judgment in Indore Development Authority vs. Manoharlal and reiterates the position on the rights of subsequent purchasers.

Conclusion

The Supreme Court’s judgment in Delhi Development Authority vs. Beena Gupta clarifies that a land acquisition does not lapse under Section 24(2) of the Act 2013 if possession has been taken, regardless of whether compensation has been paid. It also reaffirms that subsequent purchasers of land lack the legal standing to challenge acquisition proceedings. This decision provides clarity on the interpretation of Section 24(2) and the rights of subsequent purchasers in land acquisition matters.

Category

Parent Category: Land Acquisition Law

Child Categories: Section 24(2), Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, Locus Standi, Subsequent Purchaser

Parent Category: Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013

Child Category: Section 24(2), Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013

FAQ

Q: What does this judgment mean for landowners whose land was acquired?
A: This judgment clarifies that if the government has taken possession of your land, the acquisition is valid even if you haven’t received compensation. However, you are still entitled to receive compensation as per the law.

Q: I bought land after the acquisition process started. Can I challenge the acquisition?
A: No, this judgment makes it clear that subsequent purchasers do not have the right to challenge the acquisition process.

Q: What is Section 24(2) of the Right to Fair Compensation Act?
A: Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, deals with the lapse of land acquisition proceedings if certain conditions are not met. This judgment clarifies that the acquisition does not lapse if possession has been taken.