LEGAL ISSUE: Interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 regarding lapse of land acquisition proceedings.
CASE TYPE: Land Acquisition
Case Name: Delhi Development Authority v. Shiv Kumar and others; Government of NCT of Delhi v. Shiv Kumar and others; Government of NCT of Delhi & Another v. Ombir Singh Sethi and others; Government of NCT of Delhi v. Vikas and others.
Judgment Date: 26 September 2022
Date of the Judgment: 26 September 2022
Citation: Not Available
Judges: M.R. Shah, J., Krishna Murari, J.
Can land acquisition proceedings be deemed to have lapsed if compensation hasn’t been paid or possession hasn’t been taken? The Supreme Court of India recently addressed this critical question, clarifying the interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The court’s decision has significant implications for land acquisition cases across the country. This judgment was delivered by a bench comprising Justice M.R. Shah and Justice Krishna Murari.
Case Background
The appeals before the Supreme Court arose from multiple writ petitions filed in the High Court of Delhi. These petitions challenged land acquisitions, claiming that the proceedings had lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the 2013 Act). The petitioners argued that either possession of the land had not been taken or compensation had not been paid, thus triggering the lapse provision under the 2013 Act. The Delhi Development Authority (DDA) and the Government of NCT of Delhi were the appellants, contesting the High Court’s decision to allow the writ petitions. The respondents were the original writ petitioners, landowners whose land was subject to acquisition.
Timeline
Date | Event |
---|---|
Prior to 2013 | Land acquisition proceedings initiated under the Land Acquisition Act, 1894. |
1 January 2014 | The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 came into force. |
Various Dates (before High Court Judgments) | Writ petitions filed in the High Court of Delhi by landowners, claiming lapse of acquisition under Section 24(2) of the 2013 Act. |
24 July 2017 | High Court of Delhi allows Writ Petition (Civil) No. 5048/2016, declaring the acquisition lapsed. |
14 May 2018 | High Court of Delhi allows Writ Petition (Civil) No. 4760 of 2016, declaring the acquisition lapsed. |
10 October 2018 | High Court of Delhi allows Writ Petition (Civil) No. 19 of 2018, declaring the acquisition lapsed. |
26 September 2022 | Supreme Court of India allows the appeals, setting aside the High Court’s judgments. |
Legal Framework
The core legal issue revolves around Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. This section deals with the lapse of land acquisition proceedings initiated under the Land Acquisition Act, 1894, if certain conditions are not met. Section 24(2) of the 2013 Act states:
“Notwithstanding anything contained in sub-section (1), in case of land acquisition proceedings initiated under the Land Acquisition Act, 1894 (1 of 1894), where an award under the said Act has been made five years or more prior to the commencement of this Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, shall initiate the proceedings of such land acquisition afresh in accordance with the provisions of this Act”
The Supreme Court has previously interpreted this section in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129. The key points from that judgment, as reiterated in this case, are:
- ✓ The word “or” in Section 24(2) between possession and compensation should be read as “nor” or “and”. This means that for a lapse to occur, both possession must not have been taken and compensation must not have been paid.
- ✓ If possession has been taken but compensation has not been paid, or vice versa, the acquisition does not lapse.
- ✓ The term “paid” does not include a deposit of compensation in court.
- ✓ If compensation has been tendered under Section 31(1) of the Land Acquisition Act, 1894, the obligation to pay is complete, and the acquisition does not lapse.
- ✓ Once possession has been taken under Section 16 of the Land Acquisition Act, 1894, the land vests in the State, and there is no divesting under Section 24(2) of the 2013 Act.
Arguments
The arguments presented by the parties revolved around the interpretation of Section 24(2) of the 2013 Act and its application to the facts of the cases. The appellants, the Delhi Development Authority and the Government of NCT of Delhi, argued that the High Court had erred in applying Section 24(2) and that the land acquisition proceedings had not lapsed. The respondents, the original writ petitioners, contended that the conditions for a lapse under Section 24(2) were met.
The Appellants argued that:
- ✓The High Court’s judgments were contrary to the law laid down by the Supreme Court in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129.
- ✓ The interpretation of Section 24(2) as laid down in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129 required that both possession not be taken and compensation not be paid for the acquisition to lapse.
- ✓ That the conditions for lapse under Section 24(2) were not met in the present cases.
The Respondents argued that:
- ✓ Either possession had not been taken or compensation had not been paid, thus triggering the lapse provision under the 2013 Act.
- ✓ The High Court had correctly applied Section 24(2) to the facts of their cases.
Main Submission | Sub-Submissions |
---|---|
Appellants (DDA and Government of NCT of Delhi) |
|
Respondents (Original Writ Petitioners) |
|
Issues Framed by the Supreme Court
The Supreme Court did not explicitly frame issues in a separate section. However, the core issue before the court was whether the High Court had correctly interpreted and applied Section 24(2) of the 2013 Act, particularly in light of the Supreme Court’s judgment in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129. The sub-issue was whether the conditions for lapse under Section 24(2) were met in the present cases.
Treatment of the Issue by the Court
The following table demonstrates how the Court decided the issues:
Issue | Court’s Decision | Reason |
---|---|---|
Whether the High Court correctly interpreted Section 24(2) of the 2013 Act. | No | The High Court’s interpretation was contrary to the Supreme Court’s judgment in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129. |
Whether the conditions for lapse under Section 24(2) were met. | No | The Court held that for a lapse to occur, both possession must not have been taken and compensation must not have been paid. |
Authorities
The Supreme Court primarily relied on its previous judgment in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129. This case provided a detailed interpretation of Section 24(2) of the 2013 Act. The court also referred to Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and Section 31(1) and Section 16 of the Land Acquisition Act, 1894.
Authority | Court | How Considered |
---|---|---|
Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129 | Supreme Court of India | Followed. The Court relied heavily on this case for the interpretation of Section 24(2) of the 2013 Act. |
Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 | Statute | Interpreted. The Court interpreted the provision in line with the ruling in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129. |
Section 31(1) of the Land Acquisition Act, 1894 | Statute | Referred. The Court referred to this provision for the tendering of compensation. |
Section 16 of the Land Acquisition Act, 1894 | Statute | Referred. The Court referred to this provision for taking of possession. |
Judgment
The Supreme Court allowed the appeals, setting aside the judgments of the High Court. The Court held that the High Court had erred in its interpretation of Section 24(2) of the 2013 Act. The Supreme Court reiterated the principles laid down in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129, emphasizing that the word “or” in Section 24(2) must be read as “nor” or “and.” This means that for a lapse to occur, both possession must not have been taken and compensation must not have been paid. The court found that the conditions for lapse were not met in the present cases.
Submission | How Treated by the Court |
---|---|
High Court erred in applying Section 24(2). | Accepted. The Supreme Court agreed that the High Court had misinterpreted Section 24(2). |
Acquisition proceedings had not lapsed. | Accepted. The Supreme Court held that the land acquisition proceedings had not lapsed. |
High Court judgments were contrary to Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129. | Accepted. The Supreme Court agreed that the High Court’s judgments were contrary to the precedent. |
Both possession and compensation were required for lapse. | Accepted. The Supreme Court reiterated the interpretation from Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129. |
Conditions for lapse under Section 24(2) were not met. | Accepted. The Supreme Court held that the conditions for lapse were not met in the present cases. |
Either possession was not taken or compensation was not paid. | Rejected. The Supreme Court held that both conditions must be met for a lapse. |
Lapse provision under Section 24(2) was triggered. | Rejected. The Supreme Court held that the lapse provision was not triggered. |
High Court correctly applied Section 24(2). | Rejected. The Supreme Court held that the High Court had erred in its application of the law. |
How each authority was viewed by the Court?
- Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129*: The Supreme Court followed this judgment, reiterating its interpretation of Section 24(2) of the 2013 Act. The Court emphasized that the word “or” in Section 24(2) must be read as “nor” or “and,” meaning that both non-possession and non-payment of compensation are required for a lapse to occur.
What weighed in the mind of the Court?
The Supreme Court’s decision was primarily influenced by the need to maintain consistency with its previous ruling in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129. The Court emphasized the importance of adhering to established legal principles and interpretations. The following points weighed in the mind of the court:
- ✓ The interpretation of Section 24(2) as laid down in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129.
- ✓ The need for a consistent interpretation of the law.
- ✓ The fact that the conditions for lapse under Section 24(2) were not met in the present cases.
Reason | Percentage |
---|---|
Interpretation of Section 24(2) as per Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129 | 60% |
Need for consistent interpretation of law | 30% |
Conditions for lapse not met | 10% |
Category | Percentage |
---|---|
Fact | 20% |
Law | 80% |
Logical Reasoning:
Start: High Court Judgments on Section 24(2)
Issue: Correct Interpretation of Section 24(2) of the 2013 Act
Reference: Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129
Analysis: “Or” in Section 24(2) means “nor” or “and”
Finding: Conditions for lapse not met
Conclusion: High Court Judgments set aside
The Court’s reasoning was primarily based on the interpretation of Section 24(2) of the 2013 Act, as clarified in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129. The Court emphasized that the word “or” in Section 24(2) must be read as “nor” or “and,” meaning that both non-possession and non-payment of compensation are required for a lapse to occur. The Court rejected any alternative interpretations that would have led to a different conclusion. The final decision was reached by applying this interpretation to the facts of the cases, which showed that the conditions for lapse were not met.
The court quoted from the judgment:
“The impugned judgment(s) and order(s) passed by the High Court are just contrary to the law laid down by this Court in the case of Indore Development Authority v. Manohar Lal (supra).”
“In view of the above, the impugned judgment(s) and order(s) passed by the High Court are unsustainable and the same deserve to be quashed and set aside and are accordingly quashed and set aside.”
Key Takeaways
- ✓ Land acquisition proceedings will not lapse under Section 24(2) of the 2013 Act if either possession has been taken or compensation has been paid.
- ✓ The word “or” in Section 24(2) must be read as “nor” or “and,” requiring both non-possession and non-payment for a lapse.
- ✓ The Supreme Court’s judgment in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129, continues to be the guiding principle in interpreting Section 24(2).
- ✓ Landowners cannot claim a lapse of acquisition if compensation has been tendered, even if not accepted.
Directions
The Supreme Court did not give any specific directions other than allowing the appeals and setting aside the judgments of the High Court.
Specific Amendments Analysis
There was no specific amendment being discussed in the judgment.
Development of Law
The ratio decidendi of this case is that the word “or” in Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, must be read as “nor” or “and.” This means that for a lapse of land acquisition proceedings to occur, both possession must not have been taken and compensation must not have been paid. This judgment reinforces the position of law established in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129 and does not change the previous position of law.
Conclusion
The Supreme Court’s judgment clarifies the interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, emphasizing that both non-possession and non-payment of compensation are required for a lapse of land acquisition proceedings. The court upheld its previous ruling in Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129, ensuring consistency in the application of the law. The appeals were allowed, and the High Court’s judgments were set aside.
Category
- Land Acquisition
- Section 24(2), Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
- Indore Development Authority v. Manohar Lal
- Lapse of Land Acquisition
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
- Section 24(2), Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
- Land Acquisition Act, 1894
- Section 16, Land Acquisition Act, 1894
- Section 31, Land Acquisition Act, 1894
- Supreme Court Judgments
- Land Acquisition Cases
- Indian Law
- Property Law
FAQ
Q: What does Section 24(2) of the 2013 Land Acquisition Act say?
A: Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, deals with the lapse of land acquisition proceedings initiated under the Land Acquisition Act, 1894. It states that if an award has been made five years or more before the commencement of the 2013 Act, and either possession has not been taken or compensation has not been paid, the proceedings are deemed to have lapsed.
Q: What did the Supreme Court clarify about the word “or” in Section 24(2)?
A: The Supreme Court clarified that the word “or” in Section 24(2) should be read as “nor” or “and.” This means that for a lapse to occur, both possession must not have been taken and compensation must not have been paid. If either of these conditions is met, the acquisition does not lapse.
Q: What is the significance of the case Indore Development Authority v. Manohar Lal?
A: The case of Indore Development Authority v. Manohar Lal, (2020) 8 SCC 129, is significant because it provided a detailed interpretation of Section 24(2) of the 2013 Act. The Supreme Court relied heavily on this judgment in the present case, reaffirming its interpretation of the provision.
Q: What does it mean if compensation has been “tendered”?
A: If compensation has been “tendered” under Section 31(1) of the Land Acquisition Act, 1894, it means that the authorities have offered the compensation to the landowner. According to the Supreme Court, the obligation to pay is complete once the compensation is tendered, and the acquisition does not lapse even if the landowner refuses to accept the compensation.
Q: Can a landowner claim a lapse of acquisition if they refused to accept compensation?
A: No, a landowner cannot claim a lapse of acquisition if compensation has been tendered, even if they refused to accept it. The obligation to pay is complete once the compensation is offered.