Date of the Judgment: 25 January 2022
Citation: Civil Appeal No. 1106 of 2009
Judges: L. Nageswara Rao, J., B.R. Gavai, J., B.V. Nagarathna, J.
Can a real estate developer be held liable for unfair trade practices for delays in handing over possession and for demanding extra charges? The Supreme Court of India addressed this question in a case concerning a group housing project. The Court examined the Monopolies and Restrictive Trade Practices Act, 1969 (MRTP Act) and the Consumer Protection Act, 1986, to determine whether the developer had engaged in unfair trade practices. This judgment was delivered by a three-judge bench comprising Justices L. Nageswara Rao, B.R. Gavai, and B.V. Nagarathna, with the opinion authored by Justice L. Nageswara Rao.
Case Background
In 1993, the appellants applied for the allotment of four apartments in the “Beverly Park-I” project in Gurgaon, developed by DLF Universal Ltd. The project offered a payment scheme where possession was to be given after 40% of the cost was paid within 2.5 years, with the remaining amount payable over the next 7.5 years. The Apartment Buyer Agreement (ABA) was executed on 23 March 1993. The agreement stipulated that possession would be given to the appellants as “Licensees” on a monthly license fee until the full sale price was paid. The basic sale price was set at Rs. 7,525 per sq. meter, with additional charges for External Development Charges (EDC), construction deposit, and a lump sum security.
Timeline
Date | Event |
---|---|
14 January 1993 | Appellants applied for allotment of 4 apartments. |
23 March 1993 | Apartment Buyer Agreement (ABA) was executed. |
January 1996 | Scheduled date for possession of flats (as per appellants’ claim). |
June 1996 | Construction commenced (as per appellants’ claim). |
14 April 1997 | Appellants had paid Rs. 14,62,552 for each flat. |
2 June 1997 | Respondent sent a demand letter for extra charges. |
26 June 1998 | Respondent informed appellants that completion certificate was received. |
12 August 1998 | Appellants sent a letter disputing extra charges and claiming excess payment. |
19 January 1999 | Respondent cancelled the ABA due to non-payment of outstanding dues. |
19 January 2009 | Monopolies and Restrictive Trade Practices Commission, New Delhi dismissed the complaint. |
25 January 2022 | Supreme Court of India disposed of the appeal. |
Course of Proceedings
The appellants filed a complaint with the Monopolies and Restrictive Trade Practices Commission (MRTP Commission) in 1999, alleging unfair and restrictive trade practices by the respondent. They challenged the cancellation of their apartment allotments and the extra charges levied by the respondent. The MRTP Commission dismissed the complaint on 19 January 2009, stating that the delay in handing over possession and the demand for extra costs were in accordance with the ABA. The Commission also noted that the appellants had not been coerced into signing the agreement, and some installments towards extra costs had been paid. The appellants then appealed to the Supreme Court.
Legal Framework
The Supreme Court examined the relevant provisions of the MRTP Act, 1969, particularly Sections 36-A, 36-B(a) and (d), 36-D, and 36-E, which deal with unfair trade practices. Section 36A of the MRTP Act defines unfair trade practice as a practice that adopts any unfair method or deceptive practice to promote the sale, use, or supply of goods or services. The Court also referred to the Consumer Protection Act, 1986, which has a similar definition of unfair trade practice in Section 2(r). The Court noted that the Consumer Protection Act was enacted to provide better protection to consumers and to establish consumer councils and forums for settling consumer disputes.
Arguments
Appellants’ Submissions:
- The appellants argued that the respondent misled them through advertisements and brochures, promising possession within 2.5 to 3 years.
- They contended that the ABA was a one-sided contract favoring the respondent, with clauses that were unconscionable and void.
- The appellants claimed that the demand for extra charges was impermissible and not disclosed at the time of signing the ABA.
- They asserted that the delay in construction and the imposition of extra costs constituted unfair trade practices.
Respondent’s Submissions:
- The respondent argued that the appellants were not coerced into signing the ABA and were aware of its terms.
- The respondent stated that the delay in handing over possession was due to unforeseen reasons, including delays in obtaining government approvals.
- The respondent contended that the ABA allowed for reasonable extensions of time for delivery of possession.
- The respondent maintained that the demand for extra charges was permissible under the terms of the ABA and that the appellants had initially accepted and paid some installments towards these charges.
Submissions Table
Issue | Appellants’ Submissions | Respondent’s Submissions |
---|---|---|
Misrepresentation and Delay in Possession | ✓ Advertisements promised possession within 2.5 to 3 years. ✓ Delay in construction was a misrepresentation. ✓ Respondent is guilty of unfair trade practice. |
✓ No fixed time for possession; delay due to unforeseen reasons. ✓ Clause 16 of ABA allowed for reasonable extension of time. ✓ Appellants could have terminated the contract if aggrieved by delay. |
Unconscionable Contract | ✓ ABA was a one-sided contract favoring the respondent. ✓ Buyers were made to sign on dotted lines. ✓ Conditions in contract were lopsided and tilted towards the builder. |
✓ Appellants were not coerced and understood the implications of the agreement. ✓ The project is a landmark property in Gurgaon. |
Extra Charges | ✓ Demand for extra charges was impermissible and not disclosed initially. ✓ Details of extra charges were given only after persistent demands. |
✓ Demand of extra cost was permissible according to the terms of the ABA. ✓ Appellants initially accepted the demand and paid some installments. |
Innovativeness of the Argument: The appellants innovatively argued that the ABA was an unconscionable contract, similar to arguments made in consumer cases under the Consumer Protection Act, 1986. This was an attempt to extend the principles of consumer protection to cases under the MRTP Act.
Issues Framed by the Supreme Court
The Supreme Court did not explicitly frame issues in a separate section. However, the core issues addressed by the Court were:
- Whether the respondent engaged in unfair trade practices by misrepresenting the timeline for handing over possession of the apartments.
- Whether the demand for extra charges by the respondent constituted an unfair trade practice.
- Whether the terms of the ABA were unconscionable.
Treatment of the Issue by the Court
Issue | Court’s Decision | Brief Reasons |
---|---|---|
Whether the respondent engaged in unfair trade practices by misrepresenting the timeline for handing over possession of the apartments. | No | The Court found that the ABA allowed for reasonable extensions of time for delivery of possession. The appellants did not terminate the agreement due to delay, indicating that time was not of the essence. |
Whether the demand for extra charges by the respondent constituted an unfair trade practice. | No | The Court held that the demand for extra charges was in accordance with the terms of the ABA and that the appellants had initially paid some installments towards these charges. |
Whether the terms of the ABA were unconscionable. | No specific finding of unconscionability | The Court did not find any specific clause in the ABA that was unconscionable. The Court noted that the appellants were seeking possession of the property without paying the balance amount, which was not a valid ground to declare the contract unconscionable. |
Authorities
The Supreme Court considered the following authorities:
Authority | Court | Legal Point | How it was used by the Court |
---|---|---|---|
M/s Lakhanpal National Limited v. M.R.T.P. Commission & Anr. [1989] 3 SCC 251 | Supreme Court of India | Definition of unfair trade practice under the MRTP Act. | The Court applied the principles to determine whether the respondent’s actions constituted unfair trade practices. The Court stated that the key to determine unfair trade practice is to examine whether it contains a false statement and is misleading and further what is the effect of such a representation made by the manufacturer on the common man? |
M/s Philips Medical System (Cleveland) v. Indian MRI Diagnostic & Research Limited [2008] 10 SCC 227 | Supreme Court of India | Object of the 1984 amendment to the MRTP Act regarding false or misleading advertisements. | The Court referred to this case to highlight that the amendment was intended to prevent consumers from being duped by false representations about goods or services. |
Rajasthan Housing Board v. Parvati Devi [2000] 6 SCC 104 | Supreme Court of India | Delay in delivering possession of a building as an unfair trade practice. | The Court used this case to emphasize that the MRTP Commission must find whether a representation was misleading and whether the buyer was informed in advance about delays and cost increases. |
Bangalore Development Authority v. Syndicate Bank [2007] 6 SCC 711 | Supreme Court of India | Time as the essence of a construction contract. | The Court cited this case to support its conclusion that time was not the essence of the contract in this case, as the ABA allowed for reasonable extensions and the appellants did not terminate the agreement due to delay. |
Colgate Palmolive (India) Ltd. v. MRTP Commission & Ors. [2003] 1 SCC 129 | Supreme Court of India | Ingredients to constitute an offence of unfair trade practice. | The Court applied the five ingredients to determine that the appellants had not substantiated an unfair trade practice. |
Central Inland Water Transport Corporation Ltd. & Anr. v. Brojo Nath Ganguly and Anr. [1986] 3 SCC 156 | Supreme Court of India | Unconscionable terms in a contract. | The Court acknowledged the principle that an unconscionable term in a contract is void under Section 23 of the Indian Contract Act, 1872, but did not find the ABA to be unconscionable. |
Pioneer Urban Land & Infrastructure Limited v. Govindan Raghavan [2019] 5 SCC 725 | Supreme Court of India | One-sided contracts in consumer disputes. | The Court distinguished this case, noting that it pertained to disputes under the Consumer Protection Act and involved refund of amounts due to delay by the builder. |
Wing Commander Arifur Rahman Khan And Aleya Sultana & Ors. v. DLF Southern Homes Private Limited [2020] 16 SCC 512 | Supreme Court of India | One-sided contracts in consumer disputes. | The Court distinguished this case, noting that it pertained to disputes under the Consumer Protection Act and involved compensation for delay by the builder. |
Ireo Grace Realtech Private Limited v. Abhishek Khanna & Ors [2021] 3 SCC 241 | Supreme Court of India | Jurisdiction of consumer fora to award just and reasonable compensation. | The Court distinguished this case, noting that it pertained to disputes under the Consumer Protection Act and involved refund of amounts due to delay by the builder. |
Girish Chandra Gupta v. U.P. Industrial Development Corn. Ltd. & Ors. [2012] 13 SCC 452 | Supreme Court of India | Power of the MRTP Commission to grant compensation. | The Court referred to this case to clarify that the MRTP Commission can grant compensation only when loss or damage is caused due to a monopolistic, restrictive, or unfair trade practice. |
Sanjay Singh & Anr. v. U.P. Public Service Commission & Anr. [2007] 3 SCC 720 | Supreme Court of India | Final relief granted by the Court need not be the natural consequences of the ratio decidendi. | The Court cited this case to justify its decision to direct the respondent to handover possession of the flats on payment of a reduced amount, despite upholding the MRTP Commission’s order. |
U.P. Public Service Commission v. Manoj Kumar Yadav & Anr. [2018] 3 SCC 706 | Supreme Court of India | Final relief granted by the Court need not be the natural consequences of the ratio decidendi. | The Court cited this case to justify its decision to direct the respondent to handover possession of the flats on payment of a reduced amount, despite upholding the MRTP Commission’s order. |
Judgment
The Supreme Court upheld the MRTP Commission’s decision, concluding that the respondent had not engaged in unfair trade practices. The Court found that the delay in handing over possession was permissible under the terms of the ABA, which allowed for reasonable extensions of time. The Court also held that the demand for extra charges was in accordance with the ABA and that the appellants had initially paid some installments towards these charges. The Court did not find the terms of the ABA to be unconscionable.
How each submission made by the Parties was treated by the Court?
Submission | Court’s Treatment |
---|---|
Appellants’ claim of misrepresentation regarding possession timeline. | Rejected. The Court found that the ABA allowed for reasonable extensions, and the appellants did not terminate the agreement due to delay. |
Appellants’ claim that the ABA was unconscionable. | Not specifically upheld. The Court did not find any specific clause that was unconscionable and noted that the appellants were seeking possession without paying the balance amount. |
Appellants’ claim that extra charges were impermissible. | Rejected. The Court held that the demand for extra charges was in accordance with the ABA. |
Respondent’s argument that the delay was due to unforeseen reasons. | Accepted. The Court acknowledged that the ABA allowed for reasonable extensions of time. |
Respondent’s argument that extra charges were permissible under the ABA. | Accepted. The Court found that the demand for extra charges was in accordance with the terms of the agreement. |
How each authority was viewed by the Court?
The Court relied on M/s Lakhanpal National Limited v. M.R.T.P. Commission & Anr. [1989] 3 SCC 251* to define unfair trade practice and to examine if the representation made by the respondent was misleading. The Court used M/s Philips Medical System (Cleveland) v. Indian MRI Diagnostic & Research Limited [2008] 10 SCC 227* to understand the intent behind the 1984 amendment to the MRTP Act. The Court referred to Rajasthan Housing Board v. Parvati Devi [2000] 6 SCC 104* to highlight the need to examine if the buyer was informed in advance about delays and cost increases. The Court used Bangalore Development Authority v. Syndicate Bank [2007] 6 SCC 711* to conclude that time was not the essence of the contract. The Court applied the five ingredients of unfair trade practice as laid down in Colgate Palmolive (India) Ltd. v. MRTP Commission & Ors. [2003] 1 SCC 129*. The Court acknowledged the principle of unconscionable contracts as laid down in Central Inland Water Transport Corporation Ltd. & Anr. v. Brojo Nath Ganguly and Anr. [1986] 3 SCC 156* but did not find the ABA to be unconscionable. The Court distinguished the cases of Pioneer Urban Land & Infrastructure Limited v. Govindan Raghavan [2019] 5 SCC 725*, Wing Commander Arifur Rahman Khan And Aleya Sultana & Ors. v. DLF Southern Homes Private Limited [2020] 16 SCC 512* and Ireo Grace Realtech Private Limited v. Abhishek Khanna & Ors [2021] 3 SCC 241* as they pertained to disputes under the Consumer Protection Act. The Court relied on Girish Chandra Gupta v. U.P. Industrial Development Corn. Ltd. & Ors. [2012] 13 SCC 452* to clarify the powers of the MRTP Commission to grant compensation. The Court cited Sanjay Singh & Anr. v. U.P. Public Service Commission & Anr. [2007] 3 SCC 720* and U.P. Public Service Commission v. Manoj Kumar Yadav & Anr. [2018] 3 SCC 706* to justify its decision to direct the respondent to handover possession of the flats on payment of a reduced amount.
What weighed in the mind of the Court?
The Supreme Court’s decision was primarily influenced by the terms of the Apartment Buyer Agreement (ABA) and the lack of evidence of misrepresentation or unfair practices by the respondent. The Court noted that the ABA allowed for reasonable extensions of time for delivery of possession and that the appellants did not terminate the agreement due to delay. The Court also observed that the demand for extra charges was in accordance with the ABA and that the appellants had initially paid some installments towards these charges. The Court also took into consideration that the appellants were seeking possession of the property without paying the balance amount, which was not a valid ground to declare the contract unconscionable.
Sentiment | Percentage |
---|---|
Adherence to Contractual Terms | 40% |
Lack of Misrepresentation | 30% |
Appellants’ Conduct | 20% |
Distinction from Consumer Cases | 10% |
Fact:Law
Category | Percentage |
---|---|
Fact | 40% |
Law | 60% |
The Court’s reasoning was based on a careful examination of the facts and the law. The Court considered the factual aspects of the case, such as the terms of the ABA, the timeline of events, and the conduct of the parties. The Court also considered the legal aspects, such as the provisions of the MRTP Act, the Consumer Protection Act, and the relevant case laws. The Court’s analysis of the facts and the law led it to conclude that the respondent had not engaged in unfair trade practices.
Logical Reasoning
The Court considered alternative interpretations of the clauses in the ABA and the conduct of the parties but found no evidence to support the appellants’ claims of unfair trade practices. The Court emphasized that the appellants did not terminate the agreement despite the delay and that they were seeking possession without paying the balance amount. The Court also noted that the extra charges were permissible under the terms of the ABA.
The Court’s decision was based on the following reasons:
- The ABA allowed for reasonable extensions of time for delivery of possession.
- The appellants did not terminate the agreement due to delay.
- The demand for extra charges was in accordance with the ABA.
- The appellants were seeking possession without paying the balance amount.
- No specific clause in the ABA was found to be unconscionable.
- The appellants failed to prove that the respondent had engaged in unfair trade practices.
The Supreme Court quoted the following from the judgment:
- “According to clause 16, the company is entitled for reasonable extension of time for delivery of possession of the premises, in case, possession could not be delivered within 21/2 to 3 (two and half to three) years from the date of booking.”
- “There was no intention on the part of the appellants to insist on time being the essence of contract as they did not terminate the ABA due to delay in handing over possession of the apartments which they could have in accordance with clause 18 of the ABA.”
- “We are convinced that there is no misrepresentation made by the respondent and, therefore, we reject the allegation of unfair trade practice.”
There were no dissenting opinions in this case. The three-judge bench was unanimous in its decision.
The decision has implications for future cases involving similar disputes between real estate developers and buyers. The Court’s emphasis on the terms of the agreement and the conduct of the parties will likely be a key factor in future decisions. The ruling also clarifies the distinction between cases under the MRTP Act and the Consumer Protection Act.
Key Takeaways
- Real estate agreements are binding, and parties must adhere to the terms of the contract.
- Time is not of the essence in construction contracts unless explicitly specified.
- Buyers cannot claim unfair trade practices if they fail to terminate the agreement despite delays.
- Demands for extra charges are permissible if they are in accordance with the terms of the agreement.
- The MRTP Act and the Consumer Protection Act have different scopes and remedies.
This judgment underscores the importance of carefully reviewing real estate agreements before signing them. It also highlights the need for buyers to take timely action if they are aggrieved by the actions of the developer.
Directions
Despite upholding the MRTP Commission’s order, the Supreme Court, in the interest of justice, directed the respondent to hand over possession of the flats to the appellants on payment of Rs. 25,00,000 (Rupees Twenty-Five Lakhs Only) for each flat within four weeks. The respondent was directed to hand over possession within a week of payment.
Development of Law
The ratio decidendi of this case is that in real estate contracts, time is not of the essence unless explicitly stated, and parties are bound by the terms of the agreement. The Court also clarified that unfair trade practices must be substantiated with clear evidence of misrepresentation or deception. There was no change in the previous position of law, but the judgment reinforces the importance of contractual obligations and the limitations of the MRTP Act.
Conclusion
The Supreme Court upheld the MRTP Commission’s decision, finding no unfair trade practices by the respondent. The Court emphasized the importance of contractual terms and the need for buyers to take timely action if they are aggrieved by the actions of the developer. The Court, however, directed the respondent to hand over possession of the flats to the appellants on payment of a reduced amount, balancing the interests of both parties.