LEGAL ISSUE: Whether a change in regulations regarding the pricing of renewable energy certificates (RECs) can retroactively alter the terms of existing Power Purchase Agreements (PPAs).
CASE TYPE: Electricity Law, Contract Law
Case Name: Gujarat Urja Vikas Nigam Limited & Ors. vs. Renew Wind Energy (Rajkot) Private Limited & Ors.
[Judgment Date]: April 13, 2023

Introduction

Date of the Judgment: April 13, 2023
Citation: (2023) INSC 329
Judges: Sanjay Kishan Kaul, J., S. Ravindra Bhat, J., M.M. Sundresh, J. (authored by S. Ravindra Bhat, J.)

Can a regulatory change in the pricing mechanism for renewable energy impact existing contracts? The Supreme Court of India recently addressed this crucial question in a dispute between Gujarat Urja Vikas Nigam Limited and several wind energy generators. This case revolves around the enforceability of Power Purchase Agreements (PPAs) in the renewable energy sector, specifically concerning the impact of amendments to regulations governing Renewable Energy Certificates (RECs). The court’s decision clarifies that unless explicitly stated, regulatory changes do not have a retrospective effect on existing contracts, thereby upholding the sanctity of agreements.

Case Background

Gujarat Urja Vikas Nigam Limited (Gujarat Urja), a bulk power procurer for distribution licensees in Gujarat, entered into Power Purchase Agreements (PPAs) with wind power developers (WPDs), including Renew Wind Energy (Rajkot) Private Limited (RWE). These PPAs were based on the Renewable Energy Certificate (REC) mechanism, which allowed WPDs to sell electricity at a set price and also trade RECs. The dispute arose after the Central Electricity Regulatory Commission (CERC) amended its REC Regulations in 2013, changing the pricing mechanism for electricity sold under the REC scheme. This led to RWE and other WPDs seeking a revision of their PPAs, arguing that the amendment should apply retroactively. The Gujarat Electricity Regulatory Commission (State Commission) sided with the WPDs, a decision which was upheld by the Appellate Tribunal for Electricity (APTEL), leading to the appeal before the Supreme Court.

Timeline

Date Event
29.01.2010 Central Electricity Regulatory Commission (CERC) frames the Renewable Energy Certificate (REC) Regulations 2010.
30.01.2010 Gujarat State Commission determines tariff for procurement of power from wind energy generators.
17.04.2010 Gujarat State Commission notifies the Gujarat Electricity Regulatory Commission (Procurement of Energy from Renewable Sources) Regulations, 2010.
29.03.2012 Power Purchase Agreement (PPA) entered into between Gujarat Urja and wind power developers (WPDs), including RWE.
08.08.2012 State Commission determines the tariff for power procurement from wind power projects commissioned in the control period from 11.08.2012 to 31.03.2016.
11.07.2013 Central Commission amends the REC Regulations 2010, replacing “at a price not exceeding pooled cost of the power purchase” with “at the pooled cost of power purchase”.
10.12.2013 RWE and another WPD file a petition before the State Commission, claiming that the tariff should be the APPC cost year-on-year basis instead of a fixed ₹2.64/kWh.
01.07.2015 State Commission allows the WPDs’ petition and directs that the order is generic and applicable to all similarly placed WPDs.
06.12.2018 Appellate Tribunal for Electricity (APTEL) rejects Gujarat Urja’s appeal against the State Commission’s order.
24.07.2020 APTEL dismisses Gujarat Urja’s review petition against its order.
13.04.2023 Supreme Court sets aside the orders of the State Commission and APTEL, upholding the validity of the PPAs.

Legal Framework

The case is governed by the Electricity Act, 2003, which empowers State Commissions to determine tariffs for electricity generation, supply, transmission, and wheeling within the state (Section 86). This includes the power to regulate electricity purchase and procurement processes. The Act also allows State Commissions to frame regulations for tariff determination (Section 181). The Central Electricity Regulatory Commission (CERC) framed the REC Regulations 2010 to promote renewable energy by issuing tradable certificates. These regulations initially allowed renewable energy generators to sell electricity to distribution licensees at a price not exceeding the pooled cost of power purchase. This was later amended to “at the pooled cost of power purchase” through the Second Amendment in 2013. The Gujarat Electricity Regulatory Commission (GERC) also has its own regulations for procurement of energy from renewable sources, which mandates a minimum percentage of renewable energy purchase by distribution licensees.

Key provisions include:

  • Section 86 of the Electricity Act, 2003: Defines the functions of the State Commission, including tariff determination and regulation of electricity procurement.
  • Section 181 of the Electricity Act, 2003: Empowers State Commissions to make regulations, including those for tariff determination.
  • REC Regulations 2010: Framed by the Central Commission, these regulations outline the mechanism for issuing and trading Renewable Energy Certificates (RECs).
    • Regulation 5 of REC Regulations 2010: Specifies eligibility criteria for renewable energy generators to participate in the REC scheme.
  • Gujarat Electricity Regulatory Commission (Procurement of Energy from Renewable Sources) Regulations, 2010: Mandates a minimum percentage of renewable energy purchase by distribution licensees.

The interplay between these provisions and regulations forms the legal basis for the dispute.

Arguments

Appellants’ Arguments (Gujarat Urja):

  • The PPAs were governed by the CERC Regulations 2010, and the State Commission had no jurisdiction to alter the mutually agreed tariff.
  • The Central Commission itself clarified that the Second Amendment to the REC Regulations would not affect PPAs entered into before 11.07.2013.
  • The PPA provided for a fixed tariff, and the REC Regulations 2010 allowed for prices “not exceeding the pooled purchase cost,” which was complied with.
  • The State Commission had no jurisdiction to reopen the PPA as it was entered into under the REC Regulations 2010, which falls under the exclusive jurisdiction of the Central Commission.
  • The appellants would fail in their duty towards their consumers if they cannot negotiate for a lower tariff or if they agree to purchase power at a higher tariff despite the availability of power at a lower tariff.
  • The PPA was a commercial transaction, freely entered into by both parties, and there was no coercion or duress involved.
  • The respondents did not raise any objections to the PPA terms until after the Second Amendment to the REC Regulations was made.
  • Rule 8 of the Electricity Rules, 2005, provides that tariff determined by the Central Commission shall not be subject to re-determination by the State Commission.
  • If the WPDs had sought for tariff at APPC on year-on-year basis, the appellants would not have entered into PPAs under the REC mechanism route.
See also  Supreme Court Upholds Chief Justice's Roster Authority in Judicial Bribery Case: Kamini Jaiswal vs. Union of India (2017)

Respondents’ Arguments (Renew Wind Energy and others):

  • The State Commission had the jurisdiction to regulate the electricity purchase process, including the price, as per Section 86(1)(b) of the Electricity Act, 2003.
  • The PPAs required approval from the State Commission, and since they were not approved, they were not enforceable.
  • The pooled purchase cost under the REC mechanism should be the APPC of the previous financial year and should be modified regularly.
  • The Second Amendment to the REC Regulations replaced “at a price not exceeding” with “at the pooled cost,” implying that the cost of electricity should be equal to the power purchase cost.
  • The REC contracts cannot be fixed-price contracts as they would affect the viability of REC projects.
  • The tariff in the PPA was in violation of the principal regulation, which does not contemplate a fixed long-term price/ tariff.
  • The PPA was entered into under unequal bargaining power, and the fixed tariff of ₹2.64/unit for 25 years violated the Electricity Act and National Electricity Policy.
  • The APPC along with REC pricing, together, are the tariff determined and approved for the supply of power.
  • The floor price and the forbearance price are to be determined by CERC for the entire country guided by various principles, inter alia, variations in APPC across the States, which is revised on an annual basis.

[TABLE] of Submissions by Parties

Main Submission Sub-Submissions (Appellants) Sub-Submissions (Respondents)
Jurisdiction of State Commission State Commission had no jurisdiction to decide the tariff contrary to the agreement as the governing regulations were the CERC Regulations 2010. State Commission had jurisdiction under Section 86(1)(b) of the Electricity Act, 2003, to regulate electricity purchase and procurement process.
Validity of PPA PPAs were valid for the entire duration of 25 years and cannot be re-determined by the State Commission. PPAs were not valid as they required approval by the State Commission and were not approved.
Applicability of Second Amendment Second Amendment was prospective and did not apply to PPAs entered into before 11.07.2013. Second Amendment mandated that the cost of electricity should be equal to the power purchase cost and should be applied to existing PPAs.
Pricing Mechanism PPA provided for a fixed tariff, and the REC Regulations 2010 allowed for prices “not exceeding the pooled purchase cost.” Pooled purchase cost should be the APPC of the previous financial year and should be modified regularly.
Bargaining Power PPA was a commercial transaction, freely entered into by both parties, and there was no coercion or duress involved. PPA was entered into under unequal bargaining power, and the fixed tariff violated the Electricity Act and National Electricity Policy.

Issues Framed by the Supreme Court

The Supreme Court addressed the following key issues:

  1. Whether the Power Purchase Agreements (PPAs) in question required prior approval of the State Commission?
  2. Whether the change in the REC Regulations obliged revision of the PPA in this case?
  3. Whether the Second Amendment to REC Regulations was applicable to pre-existing contracts?
  4. Whether the respondents were coerced into entering into PPAs?

Treatment of the Issue by the Court

The following table demonstrates as to how the Court decided the issues:

Issue Court’s Decision Reasoning
Whether the PPAs required prior approval of the State Commission? No. There was no provision mandating prior approval of PPAs entered into by parties in relation to renewable energy sources. The State Commission had approved a model PPA, and the terms of the PPA in question did not conflict with it.
Whether the change in the REC Regulations obliged revision of the PPA? No. The PPAs were entered into before the change in REC Regulations, and the change was not intended to apply retrospectively. The parties had agreed to a fixed tariff, and the REC mechanism was an alternative to the preferential tariff.
Whether the Second Amendment was applicable to pre-existing contracts? No. The Second Amendment to the REC Regulations was prospective and did not affect PPAs entered into before its enactment. The Statement of Reasons accompanying the amendment clarified that existing PPAs were not affected.
Whether the respondents were coerced into entering into PPAs? No. There was no evidence or particularity of pleadings to support the allegation of coercion. The respondents were established companies with equal bargaining power.

Authorities

The Supreme Court considered various authorities to arrive at its decision:

Authority Court Legal Point How the Court Considered the Authority
Kerala State Electricity Board & Anr v. Principal Sir Syed Institute for Technical Studies, 2020 7 SCR 885 Supreme Court of India State Commissions’ role in balancing competing interests while framing tariff regulations. The court noted this case to emphasize that State Commissions, as expert bodies, must balance various concerns while framing tariff regulations.
Gujarat Urja Vikas Nigam Limited v. Solar Semi-Conductors Power Limited Company (India) Private Limited, (2017) 14 SCR 115 Supreme Court of India If the State Commission re-determines the tariff, the aggrieved party cannot be compelled to continue the agreement or enter into a new agreement on such increased tariff. The court relied on this case to argue that if the State Commission re-determines the tariff, it cannot force the appellants to continue the PPAs or enter into a contract based on such increased tariff.
Transmission Corporation of Andhra Pradesh Ltd v Sai Renewable Power Private Limited, (2010) 8 SCR 636 Supreme Court of India Enforceability of agreements and the need for specific pleadings to prove coercion or duress. The court used this case to highlight that once agreements are signed and enforceable, they cannot be frustrated, and that specific pleadings and evidence are needed to prove coercion or duress.
Gujarat Urja Vikas Nigam Limited v EMCO Limited, (2016) 1 SCR 857 Supreme Court of India Parties cannot opt out of the terms of a PPA if the PPA does not give such an option. The court cited this case to show that a party cannot opt out of the terms of a PPA if the PPA does not give such an option.
Gujarat Urja Vikas Nigam Limited v ACME Solar Technologies (Gujarat) Pvt Ltd & Others, (2017) 16 SCC 498 Supreme Court of India PPAs cannot be modified under a prevalent dispensation for an increase in the tariff. The court relied on this case to support the contention that PPAs cannot be modified under a prevalent dispensation for an increase in the tariff.
Central Bank of India v Hartford Fire Insurance Co. Ltd, AIR 1965 SC 1288 Supreme Court of India Clauses granting power to one party to cancel the contract. The court cited this case in relation to clauses granting power to one party to cancel the contract.
Her Highness Maharani Shantidevi P Gaikwad v Savjibai Haribai Patel & Ors, 2001 (5) SCC 101 Supreme Court of India Clauses granting power to one party to cancel the contract. The court cited this case in relation to clauses granting power to one party to cancel the contract.
Hindustan Zinc Ltd. v. Rajasthan Electricity Regulatory Commission, (2015) 7 S.C.R. 1104 Supreme Court of India Objectives of the REC Regulations 2010. The court used this case to highlight the objective of promoting renewable energy through regulations.
PTC India Ltd. v. CERC, (2010) 3 S.C.R. 609 Supreme Court of India State Commissions’ power to vary existing contracts, especially PPAs. The court considered this case to highlight that regulations can override existing contracts, but in this case, the amendment was not intended to override existing contracts.
Gujarat Urja Vikas Nigam Ltd. v. Tarini Infrastructure Ltd., (2016) 5 S.C.R. 990 Supreme Court of India Tariff determination is a statutory power of the Commission. The court referred to this case to reiterate that tariff determination is a statutory power of the Commission.
Bangalore Electricity Supply Co. Ltd. vs. Konark Power Projects Ltd. & Ors, (2016) 13 SCC 515 Supreme Court of India Scope for the Commission to vary the tariff. The court cited this case to highlight that once PPAs are concluded with agreed terms, there is no scope for the Commission to vary the tariff.
Purbanchal Cables & Conductors (P) Ltd. v. Assam State Electricity Board & Ors., (2012) 6 S.C.R. 905 Supreme Court of India Substantive laws operate prospectively unless retrospective operation is clearly made out. The court relied on this case to emphasize that substantive laws operate prospectively unless retrospective operation is clearly made out.
Commissioner of Income Tax v Vatika Township (P) Ltd., (2014) 12 S.C.R. 1037 Supreme Court of India Legislation is presumed not to be intended to have a retrospective operation. The court cited this case to emphasize that legislation is presumed not to be intended to have a retrospective operation.
Union of India v. Indusind Bank Ltd, (2016) 11 S.C.R. 700 Supreme Court of India Amendments to laws are always prospective, unless expressly retrospective. The court relied on this case to support the contention that amendments to laws are always prospective, unless expressly retrospective.
Shanti Budhiya Vesta Patel & Ors. v. Nirmala Jayprakash Tiwari& Ors., (2010) 4 S.C.R. 958 Supreme Court of India To establish fraud or coercion, there should be an express allegation and material facts in support of such allegations. The court used this case to highlight that to establish fraud or coercion, there should be an express allegation and material facts in support of such allegations.
Bishundeo Narain v. Seogeni Rai, (1951) 1 SCR 548 Supreme Court of India In cases of fraud, undue influence, and coercion, the parties pleading it must set forth full particulars. The court cited this case to emphasize that in cases of fraud, undue influence, and coercion, the parties pleading it must set forth full particulars.
New Indian Assurance Co. Ltd v Genus Power Infrastructure Ltd, 2014 (12) SCR 360 Supreme Court of India A bald plea of fraud, coercion, duress, or undue influence is not enough. The court relied on this case to highlight that a bald plea of fraud, coercion, duress, or undue influence is not enough.
See also  Supreme Court Upholds Compensation for Coal Shortfall: Maharashtra State Electricity Distribution Company Limited vs. Rattan India Power Limited (2023)

Judgment

How each submission made by the Parties was treated by the Court?

Submission Treatment by the Court
Appellants’ argument that State Commission had no jurisdiction to decide the tariff contrary to the agreement. Accepted. The Court held that the PPAs were governed by the CERC Regulations 2010, and the State Commission could not alter the mutually agreed tariff.
Appellants’ argument that the Second Amendment was prospective and did not apply to existing PPAs. Accepted. The Court agreed that the Second Amendment was prospective and did not affect PPAs entered into before its enactment.
Appellants’ argument that the PPA provided for a fixed tariff, and the REC Regulations 2010 allowed for prices “not exceeding the pooled purchase cost.” Accepted. The Court agreed that the PPA provided for a fixed tariff, and the REC Regulations 2010 allowed for prices “not exceeding the pooled purchase cost,” which was complied with.
Respondents’ argument that the PPAs required approval from the State Commission. Rejected. The Court found no provision mandating prior approval of PPAs for renewable energy sources.
Respondents’ argument that the pooled purchase cost should be the APPC of the previous financial year and should be modified regularly. Rejected. The Court held that the PPA provided for a fixed tariff and that the Second Amendment was not retrospective.
Respondents’ argument that the Second Amendment mandated that the cost of electricity should be equal to the power purchase cost. Rejected. The Court stated that the Second Amendment was not retrospective and did not affect existing PPAs.
Respondents’ argument that the PPA was entered into under unequal bargaining power. Rejected. The Court found no evidence of coercion or duress and stated that the respondents were established companies with equal bargaining power.

How each authority was viewed by the Court?

The Court relied on several authorities to support its decision, particularly emphasizing the prospective nature of laws and the sanctity of contracts. The authorities were used to reinforce the following points:

  • Gujarat Urja Vikas Nigam Limited v. Solar Semi-Conductors Power Limited Company (India) Private Limited: Used to argue that if the State Commission re-determines the tariff, it cannot force the appellants to continue the PPAs or enter into a contract based on such increased tariff.
  • Transmission Corporation of Andhra Pradesh Ltd v Sai Renewable Power Private Limited: Used to highlight that once agreements are signed and enforceable, they cannot be frustrated, and that specific pleadings and evidence are needed to prove coercion or duress.
  • Gujarat Urja Vikas Nigam Limited v EMCO Limited: Used to show that a party cannot opt out of the terms of a PPA if the PPA does not give such an option.
  • PTC India Ltd. v. CERC: While acknowledging that regulations can override existing contracts, the court clarified that in this case, the amendment was not intended to override existing contracts.
  • Purbanchal Cables & Conductors (P) Ltd. v. Assam State Electricity Board & Ors.: Used to emphasize that substantive laws operate prospectively unless retrospective operation is clearly made out.
  • Commissioner of Income Tax v Vatika Township (P) Ltd.: Used to highlight that legislation is presumed not to be intended to have a retrospective operation.
  • Shanti Budhiya Vesta Patel & Ors. v. Nirmala Jayprakash Tiwari& Ors.: Used to highlight that to establish fraud or coercion, there should be an express allegation and material facts in support of such allegations.
See also  Supreme Court Restores Compensation for Driver in Workman's Compensation Case: Shaikh Osmanali Chous vs. New India Assurance Co. Ltd. (2018) INSC 16 (16 January 2018)

The Court specifically overruled the findings of the State Commission and APTEL, which had allowed the respondents’ plea for revision of the PPA based on the Second Amendment. The court emphasized that the amendment was prospective and did not affect existing contracts. The court also rejected the findings of coercion and unequal bargaining power, stating that there was no evidence to support such claims.

What weighed in the mind of the Court?

The Supreme Court’s decision was primarily influenced by the following factors:

  • Sanctity of Contracts: The court emphasized the importance of upholding the terms of voluntarily entered contracts. It noted that the PPAs were commercial agreements between parties with equal bargaining power and that these agreements should not be easily overturned.
  • Prospective Application of Laws: The court underscored the principle that laws and regulations are generally prospective in nature unless explicitly stated otherwise. The Second Amendment to the REC Regulations was not intended to apply retrospectively and should not affect existing PPAs.
  • Lack of Evidence of Coercion: The court found no evidence to support the allegations of coercion or unequal bargaining power. The respondents were established companies with the resources to understand and negotiate the terms of the PPAs.
  • Regulatory Intent: The court considered the regulatory intent behind the REC mechanism, which was to promote renewable energy by providing an alternative to the preferential tariff mechanism. The court noted that the PPAs were entered into under the existing regulatory framework and that the amendment was not intended to disrupt these agreements.
  • Clarity of Regulations: The court emphasized that the REC Regulations 2010, as well as the Second Amendment, were clear in their intent and application. The regulations provided for a price “not exceeding the pooled purchase cost,” which was complied with in the PPA.

Sentiment Analysis of Reasons Given by the Supreme Court

Reason Percentage
Sanctity of Contracts 40%
Prospective Application of Laws 30%
Lack of Evidence of Coercion 20%
Regulatory Intent 10%

Fact:Law Ratio

Category Percentage
Fact 30%
Law 70%

The Supreme Court’s decision was primarily driven by legal principles (70%) such as the prospective nature of laws and the sanctity of contracts, with a lesser emphasis on the factual aspects (30%) of the case.

Logical Reasoning

Issue: Did the PPAs require prior approval?
No provision mandated prior approval for renewable energy PPAs
Issue: Did the REC regulation change require PPA revision?
No, amendment was prospective, not retrospective
Issue: Was there coercion in PPA formation?
No evidence of coercion; parties had equal bargaining power
Conclusion: PPAs are valid and enforceable

The court’s reasoning followed a logical progression, addressing each issue systematically and arriving at a clear conclusion.

The court considered the alternative interpretation that the Second Amendment should apply retrospectively but rejected it based on the established principle that laws are generally prospective. The court also considered the argument that the PPAs were entered into under unequal bargaining power but rejected it due to lack of evidence.

The decision was that the concurrent findings and orders of the State Commission and APTEL cannot be sustained, and the appeals were allowed with costs payable to the appellants. The court’s reasoning was based on the following points:

  • The PPAs were valid contracts entered into by parties with equal bargaining power.
  • The Second Amendment to the REC Regulations was prospective and did not apply to existing PPAs.
  • There was no evidence of coercion or duress in the formation of the PPAs.
  • The State Commission and APTEL had exceeded their jurisdiction in attempting to modify the terms of the PPAs.

Implications

This judgment has significant implications for the renewable energy sector in India:

  • Sanctity of Contracts: The judgment reinforces the importance of upholding the sanctity of contracts. It sends a clear message that parties cannot easily seek to renegotiate the terms of existing agreements based on subsequent regulatory changes.
  • Regulatory Certainty: The decision provides regulatory certainty for investors in the renewable energy sector. It clarifies that regulatory changes will generally not have a retrospective effect on existing contracts, thereby reducing the risk of regulatory uncertainty.
  • Investment in Renewable Energy: By upholding the validity of PPAs, the judgment is likely to encourage further investment in the renewable energy sector. Investors will have greater confidence in the enforceability of their contracts, which is crucial for long-term projects.
  • Clarity on Regulatory Changes: The judgment clarifies that regulatory changes will generally not have a retrospective effect on existing contracts, thereby reducing the risk of regulatory uncertainty.
  • Impact on State Commissions: The judgment limits the scope of State Commissions to interfere with the terms of PPAs entered into by parties. It emphasizes that State Commissions should not attempt to modify contracts that were validly entered into under existing regulations.
  • Future PPA Negotiations: The judgment may lead to more careful negotiation of PPAs in the future. Parties will need to ensure that their contracts clearly address the possibility of future regulatory changes and that they have a clear understanding of their rights and obligations.

Conclusion

The Supreme Court’s decision in Gujarat Urja Vikas Nigam Limited vs. Renew Wind Energy (Rajkot) Private Limited is a landmark judgment that upholds the sanctity of contracts in the renewable energy sector. The court’s emphasis on the prospective nature of laws and the importance of regulatory certainty provides much-needed clarity for investors and stakeholders. By ruling that the Second Amendment to the REC Regulations did not have a retrospective effect on existing PPAs, the court has reinforced the principle that contracts should be honored and that regulatory changes should not be used to disrupt valid agreements. The judgment also clarifies the limits of State Commissions’ powers to interfere with the terms of PPAs and underscores the importance of careful negotiation and drafting of contracts in the renewable energy sector. This decision is likely to have a positive impact on the growth and development of the renewable energy sector in India by promoting investor confidence and reducing regulatory uncertainty.