LEGAL ISSUE: Whether the State Electricity Regulatory Commission can reject a bid for electricity procurement if the quoted tariff is not aligned with prevailing market prices, even after a transparent bidding process. CASE TYPE: Electricity Procurement/Regulatory Law. Case Name: Jaipur Vidyut Vitran Nigam Ltd. & Ors. vs. MB Power (Madhya Pradesh) Limited & Ors. [Judgment Date]: 8 January 2024

Introduction

Date of the Judgment: 8 January 2024
Citation: 2024 INSC 23
Judges: B.R. Gavai, J. and Prashant Kumar Mishra, J.

Can a state electricity regulatory commission reject a bid in a transparent bidding process if the tariff quoted is not aligned with market prices? The Supreme Court of India recently addressed this critical question in a dispute over power procurement in Rajasthan. This case clarifies the extent of the regulatory body’s power and its responsibility to protect consumer interests. The judgment was delivered by a two-judge bench consisting of Justice B.R. Gavai and Justice Prashant Kumar Mishra.

Case Background

The dispute arose from a competitive bidding process initiated by Rajasthan Rajya Vidyut Prasaran Nigam Limited (RVPN) in 2009 to procure 1000 MW of power. Following the bidding process, seven bidders qualified for the financial bid round. PTC India, a power trading company, submitted a bid to procure power from multiple generators, including MB Power (Madhya Pradesh) Limited. The Bid Evaluation Committee (BEC) ranked the bids based on levelized tariff, with MB Power ranked seventh (L-7). Negotiations were held with the top three bidders (L-1, L-2, and L-3), leading to increased power allocations for them. However, the Energy Assessment Committee (EAC) later recommended reducing the procurement to 600 MW, and subsequently, the Government of Rajasthan approved the purchase of only 500 MW. This decision was challenged by various bidders, leading to a series of appeals and court cases.

Timeline

Date Event
21 September 2009 RVPN files petition before the Rajasthan Electricity Regulatory Commission (State Commission) seeking approval for procurement of 1000 MW of power.
28 May 2012 RVPN issues an RFP for procurement of 1000 MW of power.
February 2013 Bids are received from the bidders.
4 April 2013 BEC declares 7 bidders as qualified for opening of financial bids. MB Power was not a bidder in this process.
17 April 2013 – 22 April 2013 BEC places bids in ascending order of tariff. MB Power was ranked L-7.
4 June 2013 BEC gives opinion that negotiations can be held with bidders due to varying rates.
4 June 2013 Board of RVPN decides to hold negotiations with qualified bidders.
27 September 2013 Board of Directors of RVPN directs that LoI be issued in favor of L-1, L-2 and L-3 bidders.
1 November 2013 PPAs were signed with the L-1, L-2 and L-3 bidders.
29 January 2014 EAC recommends no requirement for long-term procurement of 1000 MW power.
7 February 2014 High Court refuses to entertain writ petitions by L-4 and L-5 bidders.
18 April 2014 High Court dismisses appeals by L-4 and L-5 bidders.
21 May 2014 EAC recommends demand of 600 MW power instead of 1000 MW.
25 July 2014 Government of Rajasthan approves purchase of 500 MW power on long term basis.
22 July 2015 State Commission approves purchase of 500 MW power and the tariff quoted by L-1 to L-3 bidders.
2 February 2018 Appellate Tribunal for Electricity (APTEL) directs State Commission to approve PPAs for L-2 and L-3 bidders for higher quantum.
25 April 2018 Supreme Court upholds APTEL’s decision on quantum but reverses increase in quantum through negotiation. Directs State Commission to consider tariff adoption for L-4 and L-5 bidders.
19 November 2018 Supreme Court directs State Commission to decide tariff under Section 63 of the Electricity Act.
26 February 2019 State Commission holds tariffs of L-4 and L-5 bidders not aligned with market prices.
3 February 2020 APTEL allows appeal of L-5 bidder, holding State Commission must adopt the tariff.
28 September 2020 Supreme Court passes interim order that L-5 bidder was entitled to supply power at the tariff of Rs.2.88 per unit.
14 December 2020 MB Power files writ petition before the High Court.
20 September 2021 High Court allows MB Power’s writ petition, directing purchase of power from it.
1 June 2023 APTEL stays the order of State Commission regarding procurement of 160 MW of power on medium term basis.
26 September 2023 Supreme Court permits appellant to proceed with tender process for procurement of 160 MW of power.
8 January 2024 Supreme Court allows appeals, quashing High Court’s order and upholding the power to reject misaligned bids.

Course of Proceedings

The initial decision to reduce the power procurement from 1000 MW to 500 MW by the State Commission was challenged by L-2 and L-3 bidders before the Appellate Tribunal for Electricity (APTEL). APTEL ruled in favor of the bidders, stating the reduction was incorrect. This decision was then appealed to the Supreme Court, which upheld the APTEL’s decision on the total quantum but reversed the increase in quantum through negotiations. The Supreme Court directed the State Commission to consider the tariff adoption for L-4 and L-5 bidders. Subsequently, the State Commission found the tariffs of L-4 and L-5 bidders to be misaligned with market prices, which was again challenged before APTEL. APTEL ruled that the State Commission had to adopt the tariff and could not consider market alignment. Finally, MB Power, the L-7 bidder, filed a writ petition before the High Court, which was allowed, leading to the current appeals before the Supreme Court.

See also  Supreme Court overturns dismissal of bank employee in United Bank of India vs. Biswanath Bhattacharjee (2022)

Legal Framework

The case revolves around Section 63 of the Electricity Act, 2003, which allows the appropriate commission to adopt a tariff determined through a transparent bidding process as per the guidelines issued by the Central Government. The Bidding Guidelines, notified on 19th January 2005, aim to promote competitive procurement, ensure transparency, and protect consumer interests. Clause 5.15 of these guidelines states that the evaluation committee can reject all price bids if the rates are not aligned with prevailing market prices. Additionally, Section 86(1)(b) of the Electricity Act empowers the State Commission to regulate electricity purchase and procurement processes, including the price at which electricity is procured. The Supreme Court also considered Section 13(2) of the General Clauses Act, which states that words in the singular shall include the plural, and vice versa, in the context of interpreting the word “all” in the Bidding Guidelines.

Relevant legal provisions include:

  • Section 63, Electricity Act, 2003: “Determination of tariff by bidding process. – Notwithstanding anything contained in section 62, the Appropriate Commission shall adopt the tariff if such tariff has been determined through transparent process of bidding in accordance with the guidelines issued by the Central Government.”
  • Section 86(1)(b), Electricity Act, 2003: “Functions of State Commission. – (1) The State Commission shall discharge the following functions, namely: – (a) ……………. (b) regulate electricity purchase and procurement process of distribution licensees including the price at which electricity shall be procured from the generating companies or licensees or from other sources through agreements for purchase of power for distribution and supply within the State;”
  • Clause 5.15, Bidding Guidelines: “The bidder who has quoted lowest levellised tariff as per evaluation procedure, shall be considered for the award. The evaluation committee shall have the right to reject all price bids if the rates quoted are not aligned to the prevailing market prices.”

Arguments

Appellants’ Arguments:

  • The writ petition filed by MB Power was not maintainable before the High Court under Article 226 of the Constitution, as the Electricity Act provides a specific forum for dispute resolution.
  • MB Power was not a “successful bidder” as no Letter of Intent (LoI) was issued to them.
  • The theory of “filling the bucket,” which obligates the procurer to accept bids up to the required capacity, is not supported by the RFP or Bidding Guidelines.
  • The direction of the Supreme Court dated 25th April 2018 was specifically restricted to L-1 to L-5 bidders, and not for L-7 bidder.
  • The State Commission has the power to reject the adoption of tariff if it is not aligned to market prices, and the certificate stating the bidding process was in conformity with the RFP does not mean that L-7 was qualified to be selected as a successful bidder.
  • The State Commission, while adopting the tariff, must consider the protection of consumer interest.
  • Bidders have no vested right to contract, and Article 226 of the Constitution cannot be used to award a contract.

Respondents’ Arguments:

  • Under Section 63 of the Electricity Act, the Commission only “adopts” tariff, and does not “determine” it, and is bound by the guidelines issued by the Central Government.
  • The Commission can only consider if the bidding process was transparent and in accordance with the guidelines.
  • The issue of market alignment does not arise if the bidding process is transparent and follows the Bidding Guidelines.
  • MB Power’s quoted tariff was market-aligned, not only in 2013 but also today, and the recent bids for 160 MW electricity have higher tariffs.
  • Negotiations were not permissible, and the certificate issued by BEC confirms the transparency of the bid.
  • The power to reject bids is in respect of all price bids, and not individual bids, and the procurer cannot arbitrarily reject bids.
  • The consumers’ interest includes reliable, quality, and uninterrupted power on a long-term basis, besides being competitive.
  • The appellants are bound to procure 906 MW of power, and the RFP provides for “bucket filling” until the entire requisitioned capacity is met.
  • There was no delay and laches, as the occasion to revalidate the claim of the respondent No.1 arose only after knowing the incapacity of other bidders to honor their offered capacity.
Main Submission Sub-submissions of Appellants Sub-submissions of Respondents
Maintainability of Writ Petition
  • Writ petition not maintainable under Article 226.
  • Electricity Act provides specific dispute resolution forum.
  • High Court has power under Article 226.
Definition of “Successful Bidder”
  • MB Power not a “successful bidder” as no LoI issued.
  • MB Power was a qualified bidder.
  • Selection process continues till requisitioned capacity is achieved.
“Filling the Bucket” Theory
  • Theory not supported by RFP or Bidding Guidelines.
  • Obliges procurer to accept exorbitant tariffs.
  • RFP provides for bucket filling.
  • Appellants bound to procure 906 MW.
Scope of Supreme Court Order
  • Order of 25th April 2018 restricted to L-1 to L-5 bidders.
  • Order was in rem, applicable to all qualified bidders.
Power of State Commission
  • State Commission can reject misaligned tariffs.
  • Certificate doesn’t guarantee selection as successful bidder.
  • State Commission only “adopts” tariff.
  • Limited to transparency and compliance with guidelines.
Market Alignment of Tariff
  • State Commission must consider consumer interest.
  • MB Power’s tariff was market-aligned.
  • Recent bids have higher tariffs.
Right to Contract
  • Bidders have no vested right to contract.
  • Article 226 cannot be used to award a contract.
  • MB Power has a right to supply power as per the bidding process.
Power to Reject Bids
  • Power to reject bids exists if tariff misaligned.
  • Power to reject is for all bids, not selectively.
Consumer Interest
  • State Commission must consider consumer interest.
  • Consumer interest includes reliable, quality, uninterrupted power.
Delay and Laches
  • MB Power delayed in approaching the court.
  • MB Power acted once the incapacity of other bidders was known.
See also  Supreme Court Upholds State Laws on Jallikattu, Kambala, and Bullock Cart Races: Animal Welfare Board of India vs. Union of India (2023)

Issues Framed by the Supreme Court

The Supreme Court framed the following key issues:

  1. Whether the High Court was justified in entertaining the writ petition under Article 226 of the Constitution of India.
  2. Whether the State Commission has the power to reject a bid if the rates quoted are not aligned to the prevailing market prices.
  3. Whether the State Commission has the power to consider the aspect of consumer interest while adopting the tariff.
  4. Whether the High Court was justified in issuing a mandamus to the appellants to enter into a contract with the respondent No.1.

Treatment of the Issue by the Court

The following table demonstrates as to how the Court decided the issues:

Issue Court’s Decision Brief Reasons
Whether the High Court was justified in entertaining the writ petition under Article 226 of the Constitution of India. No The Electricity Act is a complete code, with specific forums for dispute resolution. High Court should not have entertained the petition when an alternate remedy was available.
Whether the State Commission has the power to reject a bid if the rates quoted are not aligned to the prevailing market prices. Yes Clause 5.15 of the Bidding Guidelines allows the evaluation committee to reject bids if rates are not market-aligned. Section 86(1)(b) of the Electricity Act also empowers State Commission to regulate electricity prices.
Whether the State Commission has the power to consider the aspect of consumer interest while adopting the tariff. Yes The Bidding Guidelines aim to protect consumer interests. The State Commission has a duty to balance consumer and generator interests.
Whether the High Court was justified in issuing a mandamus to the appellants to enter into a contract with the respondent No.1. No The High Court cannot issue a mandamus to enter into a contract that is not in the public interest. The decision-making process of the BEC was valid, and the High Court should not have interfered.

Authorities

The Supreme Court considered the following authorities:

Authority Court Legal Point How it was used
PTC India Limited v. Central Electricity Regulatory Commission, (2010) 4 SCC 603 Supreme Court of India Electricity Act is an exhaustive code. Cited to emphasize that disputes should be resolved within the framework of the Electricity Act.
R. Viswanathan and others v. Rukn-ul-Mulk Syed Abdul Wajid since deceased and others, (1963) 3 SCR 22 Supreme Court of India Difference between judgment in rem and in personam. Cited to clarify that the Supreme Court’s previous order was not an order in rem.
Deccan Paper Mills Company Limited v. Regency Mahavir Properties & Ors., (2021) 4 SCC 786 Supreme Court of India Difference between judgment in rem and in personam. Cited to clarify that the Supreme Court’s previous order was not an order in rem.
Tata Power Company Limited Transmission v. Maharashtra Electricity Regulatory Commission & Ors., 2022 SCC Online 1615 Supreme Court of India State Commission has power to reject misaligned tariffs. Cited to support that the State Commission has the power to reject tariffs not aligned with market prices.
Energy Watchdog v. Central Electricity Regulatory Commission and others, (2017) 14 SCC 80 Supreme Court of India Appropriate Commission does not act as a mere post office under Section 63. Cited to emphasize that the Commission has regulatory power and must ensure tariffs are in accordance with guidelines.
GMR Warora Energy Limited v. Central Electricity Regulatory Commission (CERC) & Ors., 2023 SCC Online SC 464 Supreme Court of India Need for balancing consumer interest with that of the generators. Cited to highlight the importance of balancing consumer and generator interests.
Tata Cellular v. Union of India, (1994) 6 SCC 651 Supreme Court of India Bidders have no vested right to contract. Cited to emphasize that bidders do not have a vested right to a contract.
Rajasthan Housing Board and another v. G.S. Investments and another, (2007) 1 SCC 477 Supreme Court of India Bidders have no vested right to contract. Cited to emphasize that bidders do not have a vested right to a contract.
Laxmikant and others v. Satyawan and others, (1996) 4 SCC 208 Supreme Court of India Bidders have no vested right to contract. Cited to emphasize that bidders do not have a vested right to a contract.
Section 63, Electricity Act, 2003 Indian Parliament Determination of tariff by bidding process. Explained the provision for adoption of tariff through a bidding process.
Section 86(1)(b), Electricity Act, 2003 Indian Parliament Functions of State Commission. Explained the regulatory powers of the State Commission.
Clause 5.15, Bidding Guidelines Central Government Evaluation committee’s right to reject price bids. Explained the provision allowing the rejection of bids if rates are not aligned with market prices.
Section 13(2), General Clauses Act Indian Parliament Interpretation of singular and plural. Cited to interpret the word “all” in the Bidding Guidelines.
Vivek Narayan Sharma and others v. Union of India and others, (2023) 3 SCC 1 Supreme Court of India Interpretation of the word “any” and purposive interpretation of statutes. Cited for the principle that the word “any” can include “all” depending on the context and for the principle of purposive interpretation.
Chief Inspector of Mines v. Lala Karam Chand Thapar, (1962) 1 SCR 9 Supreme Court of India Interpretation of the word “any one”. Cited for the principle that the words “any one” can mean “every one” depending on the context.
Air India Ltd. v. Cochin International Airport Ltd. and others, (2000) 2 SCC 617 Supreme Court of India Award of contract is a commercial transaction. Cited to emphasize that the award of contract is a commercial decision and the court should be cautious in interfering.
Reliance Infrastructure Limited v. State of Maharashtra and others, (2019) 3 SCC 352 Supreme Court of India Judicial review is limited to cases of manifest unreasonableness or arbitrariness. Cited to emphasize the limited scope of judicial review.
Radha Krishan Industries v. State of Himachal Pradesh and others, (2021) 6 SCC 771 Supreme Court of India Alternate remedy and exceptions to the rule. Cited to explain the principles on the rule of alternate remedy and its exceptions.
South Indian Bank Ltd. and others v. Naveen Mathew Philip and another, 2023 SCC OnLine SC 435 Supreme Court of India Alternate remedy and exceptions to the rule. Cited to explain the principles on the rule of alternate remedy and its exceptions.
See also  Supreme Court clarifies jurisdiction for anticipatory bail in cross-state cases: Priya Indoria vs. State of Karnataka (2023) INSC 1008 (20 November 2023)

Judgment

How each submission made by the Parties was treated by the Court?

Submission Court’s Treatment
Writ petition maintainability Rejected the maintainability of the writ petition before High Court.
Definition of “successful bidder” Held that MB Power was not a successful bidder as no LoI was issued.
“Filling the bucket” theory Rejected the theory of “filling the bucket” as not supported by the RFP or Bidding Guidelines.
Scope of Supreme Court order dated 25th April 2018 Clarified that the order was limited to L-1 to L-5 bidders.
Power of State Commission Held that State Commission has the power to reject misaligned tariffs.
Market alignment of tariff Held that State Commission must consider market alignment and consumer interest.
Right to contract Held that bidders have no vested right to contract.
Power to reject bids Held that power to reject bids exists if tariff is misaligned.
Consumer interest Held that State Commission must consider consumer interest.
Delay and laches Held that the High Court should not have entertained the petition due to delay.

How each authority was viewed by the Court?

  • The Supreme Court relied on PTC India Limited v. Central Electricity Regulatory Commission [CITATION] to emphasize that the Electricity Act is a complete code and disputes should be resolved within its framework.
  • The Court cited Energy Watchdog v. Central Electricity Regulatory Commission and others [CITATION] to clarify that the Commission has regulatory power and must ensure tariffs are in accordance with guidelines, and does not act as a mere post office under Section 63 of the Electricity Act.
  • Tata Power Company Limited Transmission v. Maharashtra Electricity Regulatory Commission & Ors. [CITATION] was used to support that the State Commission has the power to reject tariffs not aligned with market prices.
  • The Court used GMR Warora Energy Limited v. Central Electricity Regulatory Commission (CERC) & Ors. [CITATION] to highlight the importance of balancing consumer and generator interests.
  • The Court cited Tata Cellular v. Union of India [CITATION], Rajasthan Housing Board and another v. G.S. Investments and another [CITATION], and Laxmikant and others v. Satyawan and others [CITATION] to emphasize that bidders do not have a vested right to a contract.
  • The Court referred to R. Viswanathan and others v. Rukn-ul-Mulk Syed Abdul Wajid since deceased and others [CITATION] and Deccan Paper Mills Company Limited v. Regency Mahavir Properties & Ors. [CITATION] to distinguish between judgments in rem and in personam and clarify that the Supreme Court’s previous order was not an order in rem.
  • The Court used Vivek Narayan Sharma and others v. Union of India and others [CITATION], Chief Inspector of Mines v. Lala Karam Chand Thapar [CITATION], to interpret the word “any” as including “all” depending on the context.
  • The Court used Air India Ltd. v. Cochin International Airport Ltd. and others [CITATION] to emphasize that the award of contract is a commercial decision and the court should be cautious in interfering.
  • The Court cited Reliance Infrastructure Limited v. State of Maharashtra and others [CITATION] to emphasize the limited scope of judicial review.
  • The Court cited Radha Krishan Industries v. State of Himachal Pradesh and others [CITATION] and South Indian Bank Ltd. and others v. Naveen Mathew Philip and another [CITATION] to explain the principles on the rule of alternate remedy and its exceptions.

What weighed in the mind of the Court?

The Supreme Court’s decision was heavily influenced by the need to protect consumer interests and ensure fair competition in electricity procurement. The Court emphasized that the State Commission has a crucial role in regulating electricity prices and cannot act as a mere post office. The Court was also concerned that accepting bids at exorbitant rates would burden consumers and undermine the objectives of the Electricity Act. The Court also focused on the fact that the High Court had interfered in a matter where an alternative remedy was available and that the High Court had issued a mandamus to enter into a contract that was not in the public interest.

Sentiment Percentage
Consumer Protection 40%
Regulatory Authority 30%
Fair Competition 20%
Judicial Restraint 10%

Decision

The Supreme Court allowed the appeals, setting aside the High Court’s order. The Court upheld the State Commission’s power to reject bids that are not aligned with prevailing market prices, even after a transparent bidding process. The Court emphasized that consumer interest is paramount in electricity procurement and that the State Commission has a regulatory role to ensure fair and reasonable prices. The Court also held that the High Court should not have entertained the writ petition under Article 226 of the Constitution of India when an alternate remedy was available under the Electricity Act. The Court also held that the High Court could not have issued a mandamus to enter into a contract that was not in the public interest.

Flowchart of the Case

RVPN initiates bidding for 1000 MW power
Bids received; MB Power ranked L-7
Negotiations with L-1 to L-3 bidders; procurement reduced to 500 MW
APTEL directs consideration of L-4 and L-5 bids
State Commission finds L-4 & L-5 tariffs misaligned
APTEL orders adoption of L-5 tariff
MB Power files writ petition in High Court
High Court orders purchase from MB Power
Supreme Court upholds rejection of misaligned bids