Date of the Judgment: February 2, 2022
Citation: 2022 INSC 101
Judges: L. Nageswara Rao, J. and B.R. Gavai, J.
Can a power distribution company withdraw from a power purchase agreement (PPA) after initially seeking its approval? The Supreme Court of India recently addressed this question, emphasizing the importance of regulatory oversight and public interest in such agreements. The court’s decision clarifies the obligations of distribution companies and the role of state electricity regulatory commissions in approving PPAs.
Case Background
The case revolves around a long-standing dispute between the Southern Power Distribution Company Limited of Andhra Pradesh (APSPDCL) and Hinduja National Power Corporation Limited (HNPCL). It began with a Memorandum of Understanding (MoU) in 1992 between the Andhra Pradesh State Electricity Board (APSEB) and HNPCL, where APSEB transferred licenses and approvals for a power project to HNPCL. A Power Purchase Agreement (PPA) was initially signed in 1994, and later amended in 1998. However, the project remained inactive until 2007 when HNPCL sought to revive it as a merchant plant, offering 25% of the power to the state. Negotiations led to the state agreeing to purchase 100% of the power.
In 2011-2012, HNPCL participated in a bidding process and emerged as the second-lowest bidder. However, the Bid Evaluation Committee discarded HNPCL’s bid, stating that the entire capacity was encumbered to the State. In 2012, the State Government agreed to purchase 100% power from HNPCL as per the amended PPA. In 2013, a Memorandum of Agreement (MoA) was signed to continue the amended PPA, and HNPCL entered into a Fuel Supply Agreement (FSA). HNPCL then filed a petition for determination of capital cost and tariff in 2014. After the bifurcation of Andhra Pradesh in 2014, the newly formed distribution companies, including APSPDCL, entered into a Continuation Agreement with HNPCL in 2016. The distribution companies then sought approval of this agreement from the State Commission.
Timeline
Date | Event |
---|---|
July 17, 1992 | MoU signed between APSEB and HNPCL. |
December 9, 1994 | Initial PPA signed between APSEB and HNPCL. |
July 25, 1996 | Central Electricity Regulatory Commission (CERC) granted Techno Economic Clearance for the power project. |
April 15, 1998 | Amended and Restated PPA signed between APSEB and HNPCL. |
2007 | HNPCL approached the Government of Andhra Pradesh to revive the project as a merchant plant. |
2011-2012 | HNPCL participated in a bidding process and emerged as the second-lowest bidder. |
September 28, 2012 | Bid Evaluation Committee discarded HNPCL’s bid. |
December 26, 2012 | State Government agreed to purchase 100% power from HNPCL. |
January 14, 2013 | HNPCL agreed to supply 100% power to the State Distribution Companies. |
May 17, 2013 | MoA signed between APDISCOMS and HNPCL to continue the amended PPA. |
August 26, 2013 | Fuel Supply Agreement (FSA) signed between HNPCL and Mahanadi Coalfield Limited. |
March 12, 2014 | HNPCL filed a petition for determination of capital cost. |
June 2, 2014 | Andhra Pradesh State Reorganisation Act came into effect. |
July 28, 2015 | HNPCL filed an addendum application enhancing the capital cost. |
January 11, 2016 | First unit of the power project declared Commercial Operation Date (COD). |
March 1, 2016 | State Commission fixed the provisional tariff at Rs. 3.61 per unit. |
April 28, 2016 | Continuation Agreement signed between APSPDCL and HNPCL. |
May 11, 2016 | APSPDCL filed a petition for approval of the Continuation Agreement. |
June 1, 2016 | State Government accorded approval for purchase of 100% power from HNPCL. |
July 3, 2016 | Second unit of the HNPCL declared COD. |
August 6, 2016 | State Commission re-determined the provisional tariff at Rs. 3.82 per unit. |
May 15, 2017 | State Commission reserved judgment in both petitions. |
January 4, 2018 | APSPDCL filed applications to withdraw the approval petition and dispose of the tariff determination petition. |
January 31, 2018 | State Commission allowed withdrawal of the approval petition and dismissed the tariff determination petition. |
February 26, 2018 | Appellate Tribunal for Electricity (APTEL) admitted HNPCL’s appeal. |
March 16, 2018 | APTEL directed parties to maintain status quo. |
May 2, 2018 | High Court of Andhra Pradesh dismissed writ petitions challenging APTEL orders. |
June 4, 2018 | Supreme Court refused to interfere with the APTEL’s interim order. |
January 7, 2020 | APTEL allowed HNPCL’s appeal, directing the State Commission to dispose of the petitions. |
July 14, 2020 | Supreme Court admitted the appeal and stayed the APTEL order. |
August 21, 2020 | Supreme Court modified its order, clarifying no stay on the interim order of APTEL. |
February 2, 2022 | Supreme Court dismissed the appeal. |
Course of Proceedings
Initially, HNPCL filed a petition (O.P. No. 21 of 2015) before the Andhra Pradesh Electricity Regulatory Commission (State Commission) for determination of the capital cost of the project and the tariff for the electricity generated. Subsequently, the distribution companies filed O.P. No. 19 of 2016 seeking approval of the Continuation Agreement. After the State Commission reserved its judgment, the distribution companies filed applications to withdraw their petition for approval of the PPA and to dispose of HNPCL’s petition for tariff determination. The State Commission allowed the withdrawal and dismissed HNPCL’s petition. HNPCL appealed to the Appellate Tribunal for Electricity (APTEL), which reversed the State Commission’s decision and directed it to dispose of both petitions on merits. The distribution companies then challenged the APTEL’s order in the High Court of Andhra Pradesh, which dismissed their petitions. Finally, the distribution companies appealed to the Supreme Court.
Legal Framework
The Supreme Court considered the following key legal provisions:
- Section 86(1)(b) of the Electricity Act, 2003: This section empowers the State Electricity Regulatory Commission to regulate the purchase and procurement of electricity by distribution licensees, including the price at which electricity is procured.
“to regulate electricity purchase and procurement process of distribution licensees including the price at which electricity shall be procured from the generating companies or licensees or from other sources through agreements.” - Section 21 of the Andhra Pradesh Electricity Reform Act, 1998: This section stipulates that any agreement related to generating, transmitting, distributing, or supplying energy without the prior written consent of the Commission is void.
“(5) Any agreement relating to any transaction of the nature described in sub sections (1), (2), (3) or (4) unless made with or subject to such consent as aforesaid, shall be void.”
The court also noted that the State Commission’s powers are guided by the principles of public interest and the need to ensure fair and just terms in power purchase agreements, as outlined in the Electricity Act, 2003 and related regulations.
Arguments
Arguments by the Distribution Companies (APSPDCL):
- The distribution companies argued that they had the right to withdraw their petition seeking approval of the PPA, as there was no legal prohibition against it. They cited Boal Quay Wharfingers Ltd. v. King’s Lynn Conservancy Board [(1971) 1 WLR 1558] and Hulas Rai Baij Nath v. Firm K.B. Bass and Co. [(1967) 3 SCR 886] to support this claim.
- They contended that the PPA was not valid until approved by the State Commission under Section 86(1)(b) of the Electricity Act, 2003 and that any agreement without prior consent of the Commission was void under Section 21 of the Andhra Pradesh Electricity Reform Act, 1998.
- The distribution companies argued that the MoA and Continuation Agreement were contrary to the National Tariff Policy and the State Commission’s Tariff Regulations.
- They claimed that HNPCL had made investments on its own accord and not based on assurances from the State, as the project was initially intended as a merchant plant.
- They argued that compelling them to purchase power from HNPCL at a high price would harm consumers and be against public interest.
Arguments by HNPCL:
- HNPCL argued that the APTEL’s order only directed the State Commission to dispose of the petitions on merits, which did not harm the distribution companies.
- They contended that the right to withdraw an application is not absolute, especially when it frustrates a contract and defeats the rights of the other party. They cited Madhu Jajoo v. State of Rajasthan [AIR 1999 Raj 1] and other cases to support this argument.
- HNPCL argued that the right to withdraw is not absolute and cannot be exercised after the judgment is reserved, citing Arjun Singh v. Mohindra Kumar [AIR 1964 SC 993] and other cases.
- HNPCL stated that they had intended to operate the plant as a merchant plant but were compelled by the State to supply 100% power to the State.
- They pointed out that the Bid Evaluation Committee had discarded their bid in the open bidding process because their entire capacity was encumbered to the State.
- They claimed that the State Government had repeatedly expressed its interest in purchasing 100% power from HNPCL.
- HNPCL argued that the distribution companies were purchasing power at a higher rate from other generators, demonstrating mala fide intent.
Main Submission | Sub-Submissions of Distribution Companies (APSPDCL) | Sub-Submissions of HNPCL |
---|---|---|
Right to Withdraw Application |
|
|
Validity of PPA |
|
|
Financial Implications |
|
|
Investments and Assurances |
|
|
Issues Framed by the Supreme Court
The Supreme Court framed the following key issues:
- Whether the distribution companies were entitled to withdraw their application (O.P. No. 19 of 2016) seeking approval of the PPA.
- Whether the State Commission was justified in dismissing HNPCL’s petition (O.P. No. 21 of 2015) for determination of capital cost and tariff.
Treatment of the Issue by the Court
The following table demonstrates as to how the Court decided the issues
Issue | Court’s Decision | Reason |
---|---|---|
Whether the distribution companies were entitled to withdraw their application (O.P. No. 19 of 2016) seeking approval of the PPA. | No | The court held that the distribution companies could not withdraw their application due to their conduct and the assurances given to HNPCL, which had altered HNPCL’s position. The court also noted that the withdrawal was not in the public interest. |
Whether the State Commission was justified in dismissing HNPCL’s petition (O.P. No. 21 of 2015) for determination of capital cost and tariff. | No | The court found that the State Commission was not justified in dismissing HNPCL’s petition, as HNPCL had the right to apply for tariff determination under Section 62 of the Electricity Act, 2003. |
Authorities
The Supreme Court considered the following authorities:
Authority | Court | Legal Point | How Considered |
---|---|---|---|
Boal Quay Wharfingers Ltd. v. King’s Lynn Conservancy Board [(1971) 1 WLR 1558] | Court of Appeal, England | Right to withdraw application | Distinguished; case arose from a licensing application, not a quasi-judicial proceeding. |
Hulas Rai Baij Nath v. Firm K.B. Bass and Co. [(1967) 3 SCR 886] | Supreme Court of India | Right to withdraw suit | Distinguished; case involved a suit for rendition of accounts, not a PPA approval. |
Madhu Jajoo v. State of Rajasthan [AIR 1999 Raj 1] | Rajasthan High Court | Withdrawal of application | Followed; withdrawal not permissible when it frustrates a contract. |
Kiran Girhotra & Ors. v. Raj Kumar & Ors. [(2009) 164 DLT 483] | Delhi High Court | Withdrawal of application | Followed; withdrawal not permissible when it frustrates a contract. |
M. Radhakrisna Murthy v. Government of A.P. & Ors. [(2001) 3 ALD 330 (DB)] | Andhra Pradesh High Court | Withdrawal of application | Followed; withdrawal not permissible when it frustrates a contract. |
Smt. Ajita Debi v. Musst. Hossenara Begum [AIR 1977 Cal 59] | Calcutta High Court | Withdrawal of application | Followed; withdrawal not permissible when it frustrates a contract. |
Mathuralal v. Chiranji Lal [AIR 1962 Raj 109] | Rajasthan High Court | Withdrawal of application | Followed; withdrawal not permissible when it frustrates a contract. |
The Registrar, Manonmaniam Sundaranar University v. Suhura Beevi [AIR 1995 Mad 422] | Madras High Court | Withdrawal of application | Followed; withdrawal not permissible when it frustrates a contract. |
Arjun Singh v. Mohindra Kumar [AIR 1964 SC 993] | Supreme Court of India | Withdrawal after hearing | Followed; withdrawal not permissible after judgment is reserved. |
Bharati Behera v. Jhili Prava Behera [W.P. No.26254 of 2013 decided by Orissa High Court on 18.04.2014] | Orissa High Court | Withdrawal after hearing | Followed; withdrawal not permissible after judgment is reserved. |
Rabia Bi Qasim v. Countrywide Consumer Financial Services Limited [ILR 2004 KAR 2215] | Karnataka High Court | Withdrawal after hearing | Followed; withdrawal not permissible after judgment is reserved. |
Pujya Sindhi Panchayat v. Prof. C.L. Mishra [AIR 2002 Rajasthan 274 (DB)] | Rajasthan High Court | Withdrawal after hearing | Followed; withdrawal not permissible after judgment is reserved. |
Yash Mehra v. Arundhati Mehra [(2006) 132 DLT 166] | Delhi High Court | Withdrawal after hearing | Followed; withdrawal not permissible after judgment is reserved. |
Dharani Sugars and Chemicals Limited v. TMN Engineering Industry [CRP PD No.3309 to 3312 of 2011 and MP No.1 of 2011 decided by the Madras High Court on 30.08.2017] | Madras High Court | Withdrawal after hearing | Followed; withdrawal not permissible after judgment is reserved. |
Tata Power Company Limited v. Reliance Energy Limited and others [(2009) 16 SCC 659] | Supreme Court of India | Regulatory framework for electricity | Cited; clarified the role of the Commission in approving PPAs and regulating tariffs. |
Kumari Shrilekha Vidyarthi and others v. State of U.P. and others [(1991) 1 SCC 212] | Supreme Court of India | State’s obligation to act fairly | Cited; emphasized the State’s duty to act fairly and in the public interest. |
Food Corporation of India v. M/s Kamdhenu Cattle Feed Industries [(1993) 1 SCC 71] | Supreme Court of India | State’s obligation to act fairly | Cited; emphasized the State’s duty to act fairly and in the public interest. |
Indian Oil Corporation Limited and others v. Shashi Prabha Shukla and another [(2018) 12 SCC 85] | Supreme Court of India | State’s obligation to act fairly | Cited; emphasized the State’s duty to act fairly and in the public interest. |
Kalabharati Advertising v. Hemant Vimalnath Narichania and others [(2010) 9 SCC 437] | Supreme Court of India | Legal malice | Cited; explained the concept of legal malice and how it applies to State actions. |
Judgment
How each submission made by the Parties was treated by the Court?
Submission | Treatment by the Court |
---|---|
Distribution companies’ right to withdraw the application for PPA approval. | Rejected. The court held that the distribution companies could not withdraw their application due to their conduct, assurances given to HNPCL, and the public interest involved. |
Validity of the PPA without State Commission approval. | Acknowledged. The court recognized that the PPA required approval but emphasized that the State Commission has a duty to consider it fairly. |
Financial implications of purchasing power from HNPCL. | The court noted that the State Commission would determine the tariff and consider all relevant factors, including the cost of the project. |
HNPCL’s investments based on State’s assurances. | Accepted. The court agreed that HNPCL made investments based on the State’s assurances and the understanding that the State would purchase 100% power. |
How each authority was viewed by the Court?
- The authorities cited by the distribution companies regarding the right to withdraw an application, such as Boal Quay Wharfingers Ltd. v. King’s Lynn Conservancy Board [(1971) 1 WLR 1558] and Hulas Rai Baij Nath v. Firm K.B. Bass and Co. [(1967) 3 SCR 886], were distinguished on the facts of the case.
- The authorities cited by HNPCL regarding the limitations on the right to withdraw an application, such as Arjun Singh v. Mohindra Kumar [AIR 1964 SC 993], were followed to emphasize that the right to withdraw is not absolute and cannot be exercised after the judgment is reserved.
- The court relied on Tata Power Company Limited v. Reliance Energy Limited and others [(2009) 16 SCC 659] to emphasize that while generating companies can supply directly to consumers, they are still subject to regulatory oversight when supplying to distribution agencies.
- The court relied on Kumari Shrilekha Vidyarthi and others v. State of U.P. and others [(1991) 1 SCC 212], Food Corporation of India v. M/s Kamdhenu Cattle Feed Industries [(1993) 1 SCC 71], Indian Oil Corporation Limited and others v. Shashi Prabha Shukla and another [(2018) 12 SCC 85] and Kalabharati Advertising v. Hemant Vimalnath Narichania and others [(2010) 9 SCC 437] to highlight the State’s obligation to act fairly, non-arbitrarily, and in the public interest.
The Supreme Court held that the distribution companies’ decision to withdraw their application was arbitrary, irrational, and unreasonable. The court emphasized that the State and its instrumentalities must act in the public interest and cannot resile from their earlier stands without a valid reason. The court also held that the State Commission was wrong in dismissing HNPCL’s petition for tariff determination, which HNPCL was entitled to under the Electricity Act, 2003.
The court observed that the distribution companies, by not purchasing power from HNPCL at the rate of Rs. 3.82 per unit as per the interim orders, had acted against public interest by purchasing power at a higher rate from other generators. The court strongly deprecated such conduct.
The court quoted the following from the judgment:
“It is thus clear that the consistent stand of the appellants – DISCOMS from the year 2012, for the first time, changed on 4th January, 2018, when they filed Interlocutory Applications before the State Commission for withdrawal of O.P. No.19 of 2016 and disposal of O.P. No.21 of 2015.”
“We have no hesitation to hold that, on account of the assurance given by the State of Andhra Pradesh/APDISCOMS, HNPCL had altered its position and as such, it was not permissible for the appellants – DISCOMS to withdraw O.P. No.19 of 2016.”
“We strongly deprecate such a conduct of the appellants – DISCOMS, which are instrumentalities of the State. The appellants – DISCOMS, rather than acting in public interest, have acted contrary to public interest.”
What weighed in the mind of the Court?
The Supreme Court’s decision was heavily influenced by the need to uphold public interest, ensure fairness, and maintain the integrity of the regulatory framework. The court was critical of the distribution companies’ conduct, which it found to be arbitrary and against public good. The court emphasized that State instrumentalities must act in a fair, transparent, and non-arbitrary manner. The court also noted that the distribution companies had acted against public interest by not purchasing power at the rate of Rs. 3.82 per unit from HNPCL and instead purchasing it at a higher rate from other generators.
Reason | Percentage |
---|---|
Upholding Public Interest | 30% |
Ensuring Fairness | 25% |
Maintaining Regulatory Framework | 20% |
Condemning Arbitrary Conduct | 15% |
Protecting HNPCL’s Interests | 10% |
Fact:Law Ratio
Category | Percentage |
---|---|
Fact | 60% |
Law | 40% |
The court’s decision was more influenced by the factual aspects of the case, such as the conduct of the distribution companies, the assurances given to HNPCL, and the public interest involved, than by purely legal considerations.
Logical Reasoning
Conclusion
The Supreme Court’s judgment in the case of Southern Power Distribution Company Limited vs. Hinduja National Power Corporation Limited underscores the critical role of state electricity regulatory commissions in overseeing power purchase agreements. The court emphasized that distribution companies cannot arbitrarily withdraw from agreements after seeking regulatory approval, especially when such actions are against public interest and undermine the rights of other parties. The judgment reinforces the principle that State instrumentalities must act fairly, transparently, and in a manner that promotes public good. The court’s decision also highlights that the State Commission is the final authority that has to decide on the tariff after considering all the aspects. The judgment serves as a significant precedent for future disputes involving power purchase agreements and regulatory oversight in the electricity sector.